Download PTU B.Arch 2019 May 9th Sem BACH 902 Building Construction And Materials VIII Question Papers

Download PTU (I.K. Gujral Punjab Technical University) B-Arch (Bachelor of Architecture) 2019 May 9th Sem BACH 902 Building Construction And Materials VIII Previous Question Papers

1 | M-74096 (S17)-2880



Roll No. Total No. of Pages : 03
Total No. of Questions : 06
B. Architecture (2012 & Onwards) (Sem.?9)
BUILDING CONSTRUCTION & MATERIALS-VIII
Subject Code : BACH-902
M.Code : 74096
Time : 4 Hrs. Max. Marks : 75
INSTRUCTIONS TO CANDIDATES :
1. Attempt THREE questions in ALL with at least ONE question from EACH UNIT.
2. Assume the missing data if any and mention that along with answer.

UNIT-I
1. Design a commercial kitchen of size 12 Mtrs ? 18 Mtrs for a restaurant of 150 person
sitting capacity in a commercial area. Draw the layout plans (above counter lvl & below
counter lvl) and 2 Nos detailed sections on suitable scale. (25)
2. Draw the working drawing of a residence as given plan (FIG l&2).The finished floor to
floor height is 3.30 mtrs and the type of foundation is steeped foundation. Use suitable
scale for drawings :
a) Detailed section as marked Y-Y
b) Centre line foundation plan (2?12.5=25)
3. a) Draw the working drawing detail of the toilet and dressing area as marked ?A? for
given plan (FIG 1) on suitable scale. The finished floor to floor height is 3.30 mtrs.
b) Write short note on Pre -tensioning of a RCC structure. (2?12.5=25)
UNIT-II
4. What is the role and function of curtain wall in a commercial building? Explain any three
different types of curtain wall construction details along Sketch for a RCC structure.
(25)
5. What is the basic principles and objectives of Modular construction? Explain in detail the
role of modular construction and standardization in reduction of cost of the project with
examples. (25)
6. Write the short notes on any two of the following with constructional details :
a) Elevators
b) Escalators
c) Refuse Chutes (2?12.5 =25)
FirstRanker.com - FirstRanker's Choice
1 | M-74096 (S17)-2880



Roll No. Total No. of Pages : 03
Total No. of Questions : 06
B. Architecture (2012 & Onwards) (Sem.?9)
BUILDING CONSTRUCTION & MATERIALS-VIII
Subject Code : BACH-902
M.Code : 74096
Time : 4 Hrs. Max. Marks : 75
INSTRUCTIONS TO CANDIDATES :
1. Attempt THREE questions in ALL with at least ONE question from EACH UNIT.
2. Assume the missing data if any and mention that along with answer.

UNIT-I
1. Design a commercial kitchen of size 12 Mtrs ? 18 Mtrs for a restaurant of 150 person
sitting capacity in a commercial area. Draw the layout plans (above counter lvl & below
counter lvl) and 2 Nos detailed sections on suitable scale. (25)
2. Draw the working drawing of a residence as given plan (FIG l&2).The finished floor to
floor height is 3.30 mtrs and the type of foundation is steeped foundation. Use suitable
scale for drawings :
a) Detailed section as marked Y-Y
b) Centre line foundation plan (2?12.5=25)
3. a) Draw the working drawing detail of the toilet and dressing area as marked ?A? for
given plan (FIG 1) on suitable scale. The finished floor to floor height is 3.30 mtrs.
b) Write short note on Pre -tensioning of a RCC structure. (2?12.5=25)
UNIT-II
4. What is the role and function of curtain wall in a commercial building? Explain any three
different types of curtain wall construction details along Sketch for a RCC structure.
(25)
5. What is the basic principles and objectives of Modular construction? Explain in detail the
role of modular construction and standardization in reduction of cost of the project with
examples. (25)
6. Write the short notes on any two of the following with constructional details :
a) Elevators
b) Escalators
c) Refuse Chutes (2?12.5 =25)
2 | M-74096 (S17)-2880

FIG. 1
FirstRanker.com - FirstRanker's Choice
1 | M-74096 (S17)-2880



Roll No. Total No. of Pages : 03
Total No. of Questions : 06
B. Architecture (2012 & Onwards) (Sem.?9)
BUILDING CONSTRUCTION & MATERIALS-VIII
Subject Code : BACH-902
M.Code : 74096
Time : 4 Hrs. Max. Marks : 75
INSTRUCTIONS TO CANDIDATES :
1. Attempt THREE questions in ALL with at least ONE question from EACH UNIT.
2. Assume the missing data if any and mention that along with answer.

UNIT-I
1. Design a commercial kitchen of size 12 Mtrs ? 18 Mtrs for a restaurant of 150 person
sitting capacity in a commercial area. Draw the layout plans (above counter lvl & below
counter lvl) and 2 Nos detailed sections on suitable scale. (25)
2. Draw the working drawing of a residence as given plan (FIG l&2).The finished floor to
floor height is 3.30 mtrs and the type of foundation is steeped foundation. Use suitable
scale for drawings :
a) Detailed section as marked Y-Y
b) Centre line foundation plan (2?12.5=25)
3. a) Draw the working drawing detail of the toilet and dressing area as marked ?A? for
given plan (FIG 1) on suitable scale. The finished floor to floor height is 3.30 mtrs.
b) Write short note on Pre -tensioning of a RCC structure. (2?12.5=25)
UNIT-II
4. What is the role and function of curtain wall in a commercial building? Explain any three
different types of curtain wall construction details along Sketch for a RCC structure.
(25)
5. What is the basic principles and objectives of Modular construction? Explain in detail the
role of modular construction and standardization in reduction of cost of the project with
examples. (25)
6. Write the short notes on any two of the following with constructional details :
a) Elevators
b) Escalators
c) Refuse Chutes (2?12.5 =25)
2 | M-74096 (S17)-2880

FIG. 1
3 | M-74096 (S17)-2880

FIG. 2
NOTE : Disclosure of Identity by writing Mobile No. or Making of passing request on any
page of Answer Sheet will lead to UMC against the Student.