- a) What do you mean by analysis of rate?
b) What are the units of measurement of plaster work and painting?
--- Content provided by FirstRanker.com ---
c) Write the general specification for first class brick work in superstructure?
d) What do you mean by abstract of estimated cost? (3x4=12)
UNIT-1
- What do you mean by estimate of a structure? Enlist different types of estimate and explain any two of them in detail. (12)
- Estimate the quantities of earthwork in excavation, brick work in foundation and 2.5 cm DPC for a given plan, elevation and section as shown in figure-1. (12)
- Estimate the quantities of lime concrete in foundation, brick work in superstructure and 25mm cement concrete flooring for a given plan, elevation and section as shown in figure-1. (12)