Seat No.: ________
Enrolment No.___________
GUJARAT TECHNOLOGICAL UNIVERSITY
BE- SEMESTER?VII (NEW) EXAMINATION ? WINTER 2020
Subject Code:2170611 Date:19/01/2021
Subject Name:Infrastructure Engineering And Management
Time:10:30 AM TO 12:30 PM Total Marks: 56
Instructions:
1. Attempt any FOUR questions out of EIGHT questions.

2. Make suitable assumptions wherever necessary.

3. Figures to the right indicate full marks.


MARKS
Q.1 (a) Explain in brief general overview of infrastructure development
03
history in India.

(b) What are the different types of project organization? Explain any
04
one in detail.

(c) Draw a flow chart and explain various steps to be followed for
07
successful completion of large scale construction project.



Q.2 (a) Explain in brief key issues you would examine in preliminary
03
screening exercise for a large scale construction project.

(b) What is life cycle analysis? What are the goals and purposes of life
04
cycle analysis?

(c) Discuss case study of any typical infrastructure project giving
07
technical and planning details.



Q.3 (a) Enlist the points to be kept in mind while estimating the working
03
capital requirement for a large scale construction project.

(b) Explain in brief different types of risk involved in a large scale
04
construction project.

(c) What is project appraisal? Explain in brief technical aspects of a
07
project appraisal.



Q.4 (a) Explain the procedure for awarding a contract.
03

(b) Define Infrastructure. Enlist hard and soft infrastructure.
04

(c) What is a work schedule? What are the purposes and objectives of
07
preparing work schedule?



Q.5 (a) Write a short not on Contractual disputes
03

(b) Discuss the guidelines to be kept in mind while estimating the
04
incremental cash flows of a project.

(c) What is meant by scope verification? Explain application of MCA
07
(Multi critical analysis) in decision making with example.



Q.6 (a) List out the points to be kept in mind while preparing tender
03
document.

(b) Enlist different type of tenders and explain anyone in detail.
04

(c) Explain following steps of project management process with
07
examples: Project Initiating, Project Planning, Project Executing,
and Project Controlling.
Q.7 (a) Define Contract and explain its importance in infrastructure
03
projects.
1


(b) Explain in brief CPM and PERT.
04

(c) Why it is important to identify critical path in project scheduling?
07
Discuss the procedure of critical path method analysis with the help
of simple example.



Q.8 (a) Write a short note on Liquidated damages
03
(b) Explain in brief application of network analysis for a particular
04
project.
(c) Enlist different type of engineering contracts and write a short note
07
on different clauses of engineering contracts


*********