GUJARAT TECHNOLOGICAL UNIVERSITY
BE- SEMESTER-VII (NEW) EXAMINATION - WINTER 2020
--- Content provided by FirstRanker.com ---
Subject Code:2170611 Date:19/01/2021Subject Name:Infrastructure Engineering And Management
Time:10:30 AM TO 12:30 PM Total Marks: 56
Instructions:
- Attempt any FOUR questions out of EIGHT questions.
- Make suitable assumptions wherever necessary.
- Figures to the right indicate full marks.
--- Content provided by FirstRanker.com ---
MARKS | ||
Q.1 | (a) Explain in brief general overview of infrastructure development history in India. | 03 |
(b) What are the different types of project organization? Explain any one in detail. | 04 | |
(c) Draw a flow chart and explain various steps to be followed for successful completion of large scale construction project. | 07 | |
Q.2 | (a) Explain in brief key issues you would examine in preliminary screening exercise for a large scale construction project. | 03 |
(b) What is life cycle analysis? What are the goals and purposes of life cycle analysis? | 04 | |
(c) Discuss case study of any typical infrastructure project giving technical and planning details. | 07 | |
Q.3 | (a) Enlist the points to be kept in mind while estimating the working capital requirement for a large scale construction project. | 03 |
(b) Explain in brief different types of risk involved in a large scale construction project. | 04 | |
(c) What is project appraisal? Explain in brief technical aspects of a project appraisal. | 07 | |
Q.4 | (a) Explain the procedure for awarding a contract. | 03 |
(b) Define Infrastructure. Enlist hard and soft infrastructure. | 04 | |
(c) What is a work schedule? What are the purposes and objectives of preparing work schedule? | 07 | |
Q.5 | (a) Write a short note on Contractual disputes | 03 |
(b) Discuss the guidelines to be kept in mind while estimating the incremental cash flows of a project. | 04 | |
(c) What is meant by scope verification? Explain application of MCA (Multi critical analysis) in decision making with example. | 07 | |
Q.6 | (a) List out the points to be kept in mind while preparing tender document. | 03 |
(b) Enlist different type of tenders and explain anyone in detail. | 04 | |
(c) Explain following steps of project management process with examples: Project Initiating, Project Planning, Project Executing, and Project Controlling. | 07 | |
Q.7 | (a) Define Contract and explain its importance in infrastructure projects. | 03 |
(c) Why it is important to identify critical path in project scheduling? Discuss the procedure of critical path method analysis with the help of simple example. | 07 | |
Q.8 | (a) Write a short note on Liquidated damages | 03 |
(b) Explain in brief application of network analysis for a particular project. | 04 | |
(c) Enlist different type of engineering contracts and write a short note on different clauses of engineering contracts | 07 |
--- Content provided by FirstRanker.com ---
This download link is referred from the post: GTU B.Tech 2020 Winter Question Papers || Gujarat Technological University