Download GTU B.Tech 2020 Winter 7th Sem 2174002 Construction Planning And Management Question Paper

Download GTU (Gujarat Technological University Ahmedabad) B.Tech/BE (Bachelor of Technology/ Bachelor of Engineering) 2020 Winter 7th Sem 2174002 Construction Planning And Management Previous Question Paper

This post was last modified on 04 March 2021

GTU B.Tech 2020 Winter Question Papers || Gujarat Technological University


FirstRanker.com

Subject Code:2174002

GUJARAT TECHNOLOGICAL UNIVERSITY

--- Content provided by⁠ FirstRanker.com ---

BE- SEMESTER-VII (NEW) EXAMINATION — WINTER 2020

Date:21/01/2021

Subject Name:Construction Planning & Management

Time:10:30 AM TO 12:30 PM

Total Marks: 56

--- Content provided by‌ FirstRanker.com ---

Instructions:

  1. Attempt any FOUR questions out of EIGHT questions.
  2. Make suitable assumptions wherever necessary.
  3. Figures to the right indicate full marks.

MARKS

--- Content provided by FirstRanker.com ---

Q.1 (a) What are the construction management functions during the construction 03 phase of a project?

(b) Explain in brief: various life cycle phases of a typical construction 04 project.

(c) Explain the Project Work Breakdown Structure (WBS) in detail. Also 07 draw a typical WBS for a ‘Shopping Mall Construction Project’.

Q.2 (a) Explain various types of activity Floats in network diagram. How they are 03 evaluated?

(b) Draw a network diagram (AOA) for the following activities in a project. 04

--- Content provided by‍ FirstRanker.com ---

Activities IPA Labors/day Days(duration
A -- 5 3
B -- 8 3
C A 7 5
D B 6 2
E C,D 5 2

(c) Draw a network (AOA) from the following activities and find critical 07 path and duration of project.

Activities Duration (Days) Activities Duration (Days)
1-2 5 5-9 3
1-3 8 6-10 5
2-4 6 7-10 4
2-5 4 8-11 9
2-6 4 9-12 2
3-7 5 10-12 4
3-8 3 11-13 1
4-9 1 12-13 1

Q.3 (a) Briefly outline the concept of various management techniques/tools for 04 scheduling construction projects. Mention the suitability of each.

(b) Enlist the major potential risk areas of a Construction site. 03

(c) Convert the following CPM network in to AON network. 07

FirstRanker.com

--- Content provided by⁠ FirstRanker.com ---

FirstRanker.com

Q.4 (a) What are the limitations of the bar chart? 03

(b) Prepare a Health and Safety plan (HS plan) for a typical construction site 04 for a contractor to bid in pre-tendering process.

(c) Draw precedence diagram for the following data and find out critical path 07 and various floats. Lag/Lead relations are for a particular logical relation is given in brackets. Where ever explicit relations are not mentioned, it is F-S relations with zero lag/lead.

Activity A B C D E F G H
Predecessor - A[FS(1)] B B[SS(2)] D D,E E F[FF(4)],G
Duration 4 6 5 6 3 1 4 3 5

Q.5 (a) Enlist the cost associated for establishment of a typical construction site. 03

--- Content provided by‌ FirstRanker.com ---

(b) How resource levelling and resource allocation are different? Enlist the 04 general rules to be followed in resource levelling problems.

(c) A network is given below for a project. At the end of 10 days, following 07 information are available from site on the project status. Draw an updated network diagram using status report:

Activity D takes 6 days to finish.

Activity F takes 5 more days to complete.

It is expected that it will take total 15 days to finish activity B.

--- Content provided by​ FirstRanker.com ---

Activity H cannot start until day 17 because of the delay of material.

Q.6 (a) What are the typical responsibilities of a contractor at a construction site? 03

(b) In the Q.2(b) network, allocate the resources based on the early start and 04 late finish times of the network.

FirstRanker.com

Q7 (a) Explain the following terms:

--- Content provided by​ FirstRanker.com ---

  1. Actual cost of the work performed (ACWP)
  2. Budgeted cost of the work scheduled (BCWS)
  3. Budgeted cost of the work performed (BCWP)

(b) Explain central limit theorem and how it is used in PERT problems.

(c) PERT Data for a project is given. Calculate the completion time of project with 50% probability.

--- Content provided by​ FirstRanker.com ---

Activity IPA Most Optimistic time Most likely time Pessimistic time
A -- 2 4 12
B -- 10 12 26
C A 8 9 10
D A 10 15 20
E A 7 7.5 11
F B,C 9 9 9
G D 3 3.5 7
H EF.G 5 5 5
i j Act a M b
5 10 A 2.00 4.00 6.50
5 15 B 6.00 7.00 7.50
5 30 C 1.00 2.00 5.50
10 20 Y 2.50 4.50 5.50
10 25 U 5.00 6.00 7.00
15 30 I 3.00 4.00 7.50
20 35 O 2.50 5.50 8.00
25 35 P 2.00 3.00 5.00
25 40 L 3.00 4.00 4.00
30 45 K 1.00 2.00 3.50
35 50 J 5.00 6.50 8.00
40 50 H 4.00 5.00 6.50
45 55 G 2.00 3.00 5.00
50 60 F 6.50 7.50 9.50
55 60 D 3.50 5.00 7.00
60 65 S 3.00 4.00 4.50

Q.8 (a) Explain the following in terms of Variance analysis:

  1. Cost Variance
  2. % Cost Overrun / Underrun
  3. % Time Overrun

FirstRanker.com

--- Content provided by‍ FirstRanker.com ---

(b) Using resource aggregation method, schedule the project. sider no of gang as one for all the activities.)

Activity Duration (days)
A 3
B 2
C 4
D 3
E 2
F 3
G 1

(c) The table given gives the data about duration and costs of various activity 07 of network shown in figure.

Activity Normal Duration (Weeks) Normal cost (Rs.) Crash Duration (Weeks) Crash Cost (Rs.)
1-2 5 4000 3 12000
2-3 6 3000 3 7500
2-4 8 3600 6 6000
3-4 5 5000 3 10000

The project overhead cost are Rs. 1500 per week. Find the optimum duration and the cost associated with it. Also, show the least cost and duration graphically.

FirstRanker.com

FirstRanker.com

--- Content provided by‍ FirstRanker.com ---

Normal Deviate Probability (%) Normal Deviate Probability (%)
0 50.0 0 50.0
- 0.1 46.0 + 0.1 54.0
- 0.2 42.1 + 0.2 57.9
- 0.3 38.2 + 0.3 61.8
- 0.4 34.5 + 0.4 65.5
- 0.5 30.8 + 0.5 69.2
- 0.6 27.4 + 0.6 72.6
- 0.7 24.2 + 0.7 0.
- 0.8 21.2 + 0.8 78.8
- 0.9 18.4 + 0.9 81.6
- 1.0 15.9 + 1.0 84.1
=1.1 13.6 + 1.1 86.4
-1.2 11.5 + 1.2 88.5
- 1.3 9.7 + 1.3 90.3
- 1.4 8.1 + 1.4 91.3
- 1.5 6.7 + 1.5 93.3
- 1.6 5.5 + 1.6 94.5
- 1.7 4.5 + 1.7 95.5
- 1.8 3.6 + 1.8 96.4
- 1.9 2.9 + 1.9 97.1
- 2.0 2.3 + 2.0 97.7
- 2.1 1.8 + 2.1 98.2
- 2.2 1.4 + 2.2 98.6
- 2.3 1 + 2.3 98.9
- 2.4 0.8 + 2.4 99.2
- 2.5 0.6 + 2.5 99.4
- 2.6 0.5 + 2.6 99.5
- 2.7 0.3 + 2.7 L 4
- 2.8 0.3 + 2.8 99.7
- 2.9 0.2 + 2.9 99.8
- 3.0 0.1 + 3.0 99.9


This download link is referred from the post: GTU B.Tech 2020 Winter Question Papers || Gujarat Technological University