Download GTU B.Tech 2020 Winter 8th Sem 2180903 Power System Planning And Design Question Paper

Download GTU (Gujarat Technological University Ahmedabad) B.Tech/BE (Bachelor of Technology/ Bachelor of Engineering) 2020 Winter 8th Sem 2180903 Power System Planning And Design Previous Question Paper

This post was last modified on 04 March 2021

GTU B.Tech 2020 Winter Question Papers || Gujarat Technological University


FirstRanker.com

GUJARAT TECHNOLOGICAL UNIVERSITY

BE- SEMESTER-VIII (NEW) EXAMINATION — WINTER 2020

--- Content provided by⁠ FirstRanker.com ---

Subject Code: 2180903

Subject Name: Power System Planning and Design

Time: 02:00 PM TO 04:00 PM

Date: 25/01/2021

Total Marks: 56

--- Content provided by FirstRanker.com ---

Instructions:

  1. Attempt any FOUR questions out of EIGHT questions.
  2. Make suitable assumptions wherever necessary.
  3. Figures to the right indicate full marks.
Q.1 (a) Why transmission should be carried out at high voltages?

--- Content provided by‌ FirstRanker.com ---

(b) What do you mean by compensation with refer to transmission line? Explain shunt compensation
(c) Discuss the following factors to be taken into consideration in the mechanical design of a transmission line. (1) Loading on the conductors (2) Span, sag and tension. (3) Clearance from the ground.
MARKS
03
04
07
Q.2 (a) Explain the terms with reference to reliability assessment (1) MTTF (2) MTTR (3) MTBF

--- Content provided by‍ FirstRanker.com ---

(b) Differentiate between equipment earthing and system grounding.
(c) What is meant by stringing of line conductors? What is a stringing chart? How it is prepared and what is its use?
03
04
07
Q.3 (a) What do you understand by tuned power lines?
(b) Define critical disruptive voltage and visual critical voltage

--- Content provided by​ FirstRanker.com ---

(c) A two conductor street main AB, 500 meters in length is fed from both the ends at 250 V. Loads of 50 A, 60 A, 40 A and 30 A are tapped at distances of 100 m, 250 m, 350 m and 400 m from the end A respectively. If the cross/section of the conductors is 1 em’and specific resistance-of the material of the conductors is 1.7p Q-cm, determine the‘'minimum consumer voltage.
03
04
07
Q.4 (a) What are sag templates?
(b) Discuss the various methods of voltage regulation used in distribution system
(c) A single phase a.c. distributor 500 m long has a total loop impedance of (0.02 +j0.04) Q and is fed from one end at 250V. It is loaded as under:
  1. 50 A at unity power factor, 200 m from the feeding point.
  2. --- Content provided by FirstRanker.com ---

  3. 100 A at 0.8 power factor lag, 300 m from the feeding point.
  4. 50 A at 0.6 power factor lag, at the far end.
Calculate the total voltage drop in the distributor and the voltage at the far end.
03
04
07
Q.5 (a) Explain (1) BIL (2) protective margin

--- Content provided by FirstRanker.com ---

(b) Discuss why earth wire is required for overhead transmission lines. Where is it located on the transmission line towers?
(c) Explain any one method of measuring soil resistivity and earthing resistance
03
04
07
Q.6 (a) Define dry flash over voltage, wet flashover voltage and impulse voltage
(b) Write a note on location of lightning arrester

--- Content provided by​ FirstRanker.com ---

(c) Explain main considerations in planning and designing generating stations in power systems with reference to the following: (1) Role of different types of power plants in large power systems. (2) Choice of generator unit constants.
03
04
07
Q.7 (a) Write a note on selection of location for power plants
(b) Write a note on transmission system planning.
(c) Discuss in detail the steps in planning and designing electrical distribution schemes
03

--- Content provided by​ FirstRanker.com ---

04
07
Q.8 (a) Explain radio and television interference.
(b) What are the different methods of load forecasting?
(c) Explain the financial aspects of power system improvement scheme.
03
04

--- Content provided by​ FirstRanker.com ---