PTU B.Tech Industry Engineering 5th Semester May 2019 70994 MAINTENANCE and PROJECT MANAGEMENT Question Papers

PTU Punjab Technical University B-Tech May 2019 Question Papers 5th Semester Industry Engineering

Roll No.
Total No. of Pages : 02
Total No. of Questions : 09
B.Tech. (Ind. Engg. & Mgt.) (Spl. in TQM) (Sem.?5)
MAINTENANCE & PROJECT MANAGEMENT
Subject Code : IEM-503
M.Code : 70994
Time : 3 Hrs. Max. Marks : 40

INSTRUCTIONS TO CANDIDATES :
1.
Attempt All EIGHT questions from SECT ION-A carrying T WO marks each.
2.
Attempt any SIX questions out of EIGHT from SECT ION-B carrying FOUR marks
each.





SECTION-A
1. Answer the following :

a. Define maintenance. Explain the need of maintenance management in manufacturing

organizations.


b. Discuss the steps involved in maintenance planning in an organization.

c. How do organizations evolve standards for maintenance tasks?

d. Describe the objectives and organization structures for maintenance function.


e. Explain the effects of corrosion on machinery. How corrosion can be prevented?

f. Define project management. Elaborate the phases of project management.

g. Compare the characteristics of CPM and PERT.

h. Explain the steps involved in evaluating project deviations.


SECTION-B
2. Discuss the salient features, advantages, limitations and applications of predictive
maintenance in manufacturing organizations.
3. Discuss the documents used in manufacturing organizations for maintenance planning.
1 | M-70994

(S109)-3002


4. Explain the maintenance control strategies adopted by manufacturing organizations.
5. How do organizations plan training for optimizing maintenance performance?
6. What do you understand by vibration analysis? How do maintenance engineers plan for
monitoring and minimizing vibrations impact on machine performance?
7. Elaborate the common mistakes in planning and scheduling the projects. How these
mistakes can be avoided?
8. Draw the network for the activities given on right, thereby identifying the critical path, total
project duration and floats. If the activities 2-5, 3-7 and 8-9 involve the use of crane,
determine the minimum number of cranes so as that no delay is caused. If there is only one
crane, indicate the delay caused, if any.
Activity
Duration
Activity
Duration
1 - 2
2
3 - 7
5
1 - 3
2
4 - 6
3
1 - 4
1
5 - 8
1
2 - 5
4
6 -9
5
3 - 6
8
7 - 8
4


8 - 9
3
9. Describe the steps involved in project commissioning and performance review.






NOTE : Disclosure of Identity by writing Mobile No. or Making of passing request on any
page of Answer Sheet will lead to UMC against the Student.
2 | M-70994

(S109)-3002


This post was last modified on 04 November 2019