Download PTU M.Tech. EE 1st Semester 75215 POWER SYSTEM ANALYSIS Question Paper

Download PTU. I.K. Gujral Punjab Technical University (IKGPTU) M.Tech. EE 1st Semester 75215 POWER SYSTEM ANALYSIS Question Paper.

1 | M-75215 (S35)-1051

Roll No. Total No. of Pages : 02
Total No. of Questions : 08
M.Tech. (EE) (2018 Batch) (Sem.?1)
POWER SYSTEM ANALYSIS
Subject Code : MTEE-101-18
M.Code : 75215
Time : 3 Hrs. Max. Marks : 60

INSTRUCTIONS TO CANDIDATES :
1. Attempt any FIVE questions out of EIGHT questions.
2. Each question carries TWELVE marks.

1. a) Explain sparsity technique and optimal ordering. (4)
b) The following is the system data for a load flow solution. The line admittances :
Bus Code Admittance
1-2 2-j8
1-3 1-j4
2-3 0.666-j2.664
2-4 1-j4
3-4 2-j8
The schedule of active and reactive powers :
Bus Code P Q V Remarks
1 -- -- 1.06 Slack
2 0.5 0.2 1+j0 PQ
3 0.4 0.3 1+j0 PQ
4 0.3 0.1 1+j0 PQ
Determine the voltages at the end of first iteration using Gauss-Seidal method. Take
? =1.6. (8)
FirstRanker.com - FirstRanker's Choice
1 | M-75215 (S35)-1051

Roll No. Total No. of Pages : 02
Total No. of Questions : 08
M.Tech. (EE) (2018 Batch) (Sem.?1)
POWER SYSTEM ANALYSIS
Subject Code : MTEE-101-18
M.Code : 75215
Time : 3 Hrs. Max. Marks : 60

INSTRUCTIONS TO CANDIDATES :
1. Attempt any FIVE questions out of EIGHT questions.
2. Each question carries TWELVE marks.

1. a) Explain sparsity technique and optimal ordering. (4)
b) The following is the system data for a load flow solution. The line admittances :
Bus Code Admittance
1-2 2-j8
1-3 1-j4
2-3 0.666-j2.664
2-4 1-j4
3-4 2-j8
The schedule of active and reactive powers :
Bus Code P Q V Remarks
1 -- -- 1.06 Slack
2 0.5 0.2 1+j0 PQ
3 0.4 0.3 1+j0 PQ
4 0.3 0.1 1+j0 PQ
Determine the voltages at the end of first iteration using Gauss-Seidal method. Take
? =1.6. (8)
2 | M-75215 (S35)-1051

2. a) With the help of a neat flow chart, explain the Newton-Raphson method of load flow
solution when the system contains voltage-controlled buses in addition to swing bus
and load bus. (8)
b) Compare G-S method and N-R method of load flow solutions. (4)
3. Discuss symmetrical component analysis of unsymmetrical faults. How is fault
computation done using Z bus formulation? (12)
4. a) Derive the expression for the fault current and terminal voltage for a line to line fault
occurs at the terminal of an unloaded 3-phase alternator. Assume that the alternator
has an isolated neutral. (6)
b) A 30 MVA, 11kV generator has Z
1
= Z
2
= j0.2 pu, Z
0
= j0.05 pu. A line to ground
fault occurs on the generator terminals. Find the fault current and line to line voltages
during the fault conditions. Assume that the generator neutral is solidly grounded. (6)
5. Write short notes on :
a) State estimation of power systems. (6)
b) State estimation of the line power flow. (6)
6. Discuss contingency analysis for power system using Brown's Method. (12)
7. a) What is voltage collapse? Explain its causes and prevention methods taken against it.
(6)
b) Draw PV graph for a typical line. What is the use of this graph in voltage stability
studies? (6)
8. a) Give a flow chart for a load flow study on a power system using Fast Decoupled load
flow method. (8)
b) Explain why N-R method is preferred to G-S method for load flow studies in power
system. (4)


NOTE : Disclosure of Identity by writing Mobile No. or Making of passing request on any
page of Answer Sheet will lead to UMC against the Student.
FirstRanker.com - FirstRanker's Choice

This post was last modified on 13 December 2019