Download GTU (Gujarat Technological University) MBA (Master of Business Administration) 2018 Summer 1st Sem 2820006 Production And Operation Management Previous Question Paper
Seat No.: ________ Enrolment No.___________
GUJARAT TECHNOLOGICAL UNIVERSITY
MBA ? SEMESTER 01? ? EXAMINATION ? SUMMER 2018
Subject Code:2820006 Date:23/05/2018
Subject Name: Production and Operation Management
Time: 10:30 AM To 01:30 Total Marks: 70
Instructions:
1. Attempt all questions.
2. Make suitable assumptions wherever necessary.
3. Figures to the right indicate full marks.
Q.
No.
Question Text and Option 6
Q.1
(a)
Objective Questions
1.
Continuous Production process is used for __________________ of products.
A. Few Variety B. Many Variety
C. No Variety D. Infinitive Variety
2.
Example of Batch Production is _____________.
A. Construction B. Bakeries
C. Automobile D Paints
3.
Determine the best site for the warehouse using the centre of gravity
technique.
A B C
X 150 300 400
Y 250 100 500
W 140 110 170
A. X= 290.5 & Y=311.9 B. X=300.9 & Y=315.5
C. X= 275.7 & Y= 290.6 D. X= 305.7 & Y= 320.2
4.
Which one is the correct job sequence for the given data.
Job S T U V W
M1 16 3 21 31 6
M2 7 9 5 17 13
A. T-W-V-S-U B. U-V-S-W-T
C. S-U-V-W-T D. T-U-V-S-W
5.
In EOQ = ?2AO/c , what is ?c? ?
A. Cost per Unit Per Day B. Cost per Unit Per Week
C. Cost per Unit Per Month D. Cost per Unit Per Year
6.
Whether Johnson?s rule can be applied for the given data?
A. Can be applied B. Cannot be applied
C. Data is insufficient D. None of the above
Q.1 (b) Short / Definition Questions
1. Job Shop
2. Robust Design
3. Revenue
4. Cost of shortage
04
Q.1 (c) Draw the network diagram of the project for the following data.
Activity
A B C D E F G H I J K L M N
Duration
2 5 3 1 4 3 7 5 1 2 2 5 4 2
Predecessor
- - A A B B C D E F GHIJ GHIJ K L
04
FirstRanker.com - FirstRanker's Choice
1
Seat No.: ________ Enrolment No.___________
GUJARAT TECHNOLOGICAL UNIVERSITY
MBA ? SEMESTER 01? ? EXAMINATION ? SUMMER 2018
Subject Code:2820006 Date:23/05/2018
Subject Name: Production and Operation Management
Time: 10:30 AM To 01:30 Total Marks: 70
Instructions:
1. Attempt all questions.
2. Make suitable assumptions wherever necessary.
3. Figures to the right indicate full marks.
Q.
No.
Question Text and Option 6
Q.1
(a)
Objective Questions
1.
Continuous Production process is used for __________________ of products.
A. Few Variety B. Many Variety
C. No Variety D. Infinitive Variety
2.
Example of Batch Production is _____________.
A. Construction B. Bakeries
C. Automobile D Paints
3.
Determine the best site for the warehouse using the centre of gravity
technique.
A B C
X 150 300 400
Y 250 100 500
W 140 110 170
A. X= 290.5 & Y=311.9 B. X=300.9 & Y=315.5
C. X= 275.7 & Y= 290.6 D. X= 305.7 & Y= 320.2
4.
Which one is the correct job sequence for the given data.
Job S T U V W
M1 16 3 21 31 6
M2 7 9 5 17 13
A. T-W-V-S-U B. U-V-S-W-T
C. S-U-V-W-T D. T-U-V-S-W
5.
In EOQ = ?2AO/c , what is ?c? ?
A. Cost per Unit Per Day B. Cost per Unit Per Week
C. Cost per Unit Per Month D. Cost per Unit Per Year
6.
Whether Johnson?s rule can be applied for the given data?
A. Can be applied B. Cannot be applied
C. Data is insufficient D. None of the above
Q.1 (b) Short / Definition Questions
1. Job Shop
2. Robust Design
3. Revenue
4. Cost of shortage
04
Q.1 (c) Draw the network diagram of the project for the following data.
Activity
A B C D E F G H I J K L M N
Duration
2 5 3 1 4 3 7 5 1 2 2 5 4 2
Predecessor
- - A A B B C D E F GHIJ GHIJ K L
04
2
Q.2 (a) XYZ Pvt. Ltd. Is planning to start a new factory for manufacturing steel
utensils. It is considering three location namely Bokaro, Jaipur and Bhillai.
The fixed cost at the three location have been estimated at Rs. 8.15 million,
Rs. 7.377 million and Rs. 7.903 million respectively. The variable cost for
the three location have been estimated at Rs. 500 per unit, Rs. 580 per unit
and Rs. 490 per unit respectively. The factory will have an annual
production capacity of 10,000 steel utensils and in the initial year it will
operate at 75% efficiency. Find the best location option, which has lowest
total cost of production.
07
(b) Explain continuous production process with merits and demerits of it. 07
OR
(b) If you want to find out location for the Chemical Manufacturing Business
then which factors you will consider?
07
Q.3 (a) Write note on Material handling equipment. 07
(b) ?Shortages are undesirable, but some organizations create shortages
intentionally?- do you agree with this statement? Why? Derive an
expression for total cost in the inventory model for intentional shortage.
07
OR
Q.3 (a) Why is the ABC classification of items done? How is the ABC
distribution curve drawn?
07
(b) If you will implement Level Output Rate Plan for your product?s
production then what will you have advantages and disadvantages of it?
07
Q.4 (a) What is Six Sigma? How is it implemented? 07
(b) ABC furniture is a manufacturer of executive tables for corporate
institutions. In order to control the quality of its table, the QC Manager
selects 15 tables at random and inspects for the number of scratches on
each one of them. The results given in the following table. Prepare a
stable c chart based on this data.
Sample
No.
1 2 3 4 5 6 7 8
No. of
defects
13 9 19 7 8 10 12 0
Sample
No.
9 10 11 12 13 14 15 ---
No. of
defects
2 5 7 11 9 13 1
07
OR
Q.4 (a) What are the various types of certification in ISO 9000? What are the
major clauses of ISO 9001?
07
(b) Following table gives details about the various activities of a project.
Activity Node a m b
A 1-2 10 11 12
B 2-3 6 10 14
C 2-4 5 8 11
D 2-5 1 5 9
E 3-6 3 7 5
F 4-6 4 9 14
G 5-7 1 2 3
H 6-7 3 7 11
07
FirstRanker.com - FirstRanker's Choice
1
Seat No.: ________ Enrolment No.___________
GUJARAT TECHNOLOGICAL UNIVERSITY
MBA ? SEMESTER 01? ? EXAMINATION ? SUMMER 2018
Subject Code:2820006 Date:23/05/2018
Subject Name: Production and Operation Management
Time: 10:30 AM To 01:30 Total Marks: 70
Instructions:
1. Attempt all questions.
2. Make suitable assumptions wherever necessary.
3. Figures to the right indicate full marks.
Q.
No.
Question Text and Option 6
Q.1
(a)
Objective Questions
1.
Continuous Production process is used for __________________ of products.
A. Few Variety B. Many Variety
C. No Variety D. Infinitive Variety
2.
Example of Batch Production is _____________.
A. Construction B. Bakeries
C. Automobile D Paints
3.
Determine the best site for the warehouse using the centre of gravity
technique.
A B C
X 150 300 400
Y 250 100 500
W 140 110 170
A. X= 290.5 & Y=311.9 B. X=300.9 & Y=315.5
C. X= 275.7 & Y= 290.6 D. X= 305.7 & Y= 320.2
4.
Which one is the correct job sequence for the given data.
Job S T U V W
M1 16 3 21 31 6
M2 7 9 5 17 13
A. T-W-V-S-U B. U-V-S-W-T
C. S-U-V-W-T D. T-U-V-S-W
5.
In EOQ = ?2AO/c , what is ?c? ?
A. Cost per Unit Per Day B. Cost per Unit Per Week
C. Cost per Unit Per Month D. Cost per Unit Per Year
6.
Whether Johnson?s rule can be applied for the given data?
A. Can be applied B. Cannot be applied
C. Data is insufficient D. None of the above
Q.1 (b) Short / Definition Questions
1. Job Shop
2. Robust Design
3. Revenue
4. Cost of shortage
04
Q.1 (c) Draw the network diagram of the project for the following data.
Activity
A B C D E F G H I J K L M N
Duration
2 5 3 1 4 3 7 5 1 2 2 5 4 2
Predecessor
- - A A B B C D E F GHIJ GHIJ K L
04
2
Q.2 (a) XYZ Pvt. Ltd. Is planning to start a new factory for manufacturing steel
utensils. It is considering three location namely Bokaro, Jaipur and Bhillai.
The fixed cost at the three location have been estimated at Rs. 8.15 million,
Rs. 7.377 million and Rs. 7.903 million respectively. The variable cost for
the three location have been estimated at Rs. 500 per unit, Rs. 580 per unit
and Rs. 490 per unit respectively. The factory will have an annual
production capacity of 10,000 steel utensils and in the initial year it will
operate at 75% efficiency. Find the best location option, which has lowest
total cost of production.
07
(b) Explain continuous production process with merits and demerits of it. 07
OR
(b) If you want to find out location for the Chemical Manufacturing Business
then which factors you will consider?
07
Q.3 (a) Write note on Material handling equipment. 07
(b) ?Shortages are undesirable, but some organizations create shortages
intentionally?- do you agree with this statement? Why? Derive an
expression for total cost in the inventory model for intentional shortage.
07
OR
Q.3 (a) Why is the ABC classification of items done? How is the ABC
distribution curve drawn?
07
(b) If you will implement Level Output Rate Plan for your product?s
production then what will you have advantages and disadvantages of it?
07
Q.4 (a) What is Six Sigma? How is it implemented? 07
(b) ABC furniture is a manufacturer of executive tables for corporate
institutions. In order to control the quality of its table, the QC Manager
selects 15 tables at random and inspects for the number of scratches on
each one of them. The results given in the following table. Prepare a
stable c chart based on this data.
Sample
No.
1 2 3 4 5 6 7 8
No. of
defects
13 9 19 7 8 10 12 0
Sample
No.
9 10 11 12 13 14 15 ---
No. of
defects
2 5 7 11 9 13 1
07
OR
Q.4 (a) What are the various types of certification in ISO 9000? What are the
major clauses of ISO 9001?
07
(b) Following table gives details about the various activities of a project.
Activity Node a m b
A 1-2 10 11 12
B 2-3 6 10 14
C 2-4 5 8 11
D 2-5 1 5 9
E 3-6 3 7 5
F 4-6 4 9 14
G 5-7 1 2 3
H 6-7 3 7 11
07
3
I 7-8 9 12 15
J 7-9 3 5 7
Find: (a) the critical path of the project and its expected duration.
(b) the probability that the project will be completed in 50 days.
Q.5 For a special component outsourced to a vendor and used in textile
machinery manufactured by XYZ Machines Tools works at Coimbatore,
we have the following situations:
Yearly demand 300000 units
Purchase quantity 100000 units
Safety Stock 50000 units
The ordering cost, independent of purchase quantity, is Rs. 1500 for each
purchase. The purchase price of the components is Rs. 75 per unit.
Annual holding cost is 20% of the value of the components (inventory
interest rate is 20%). Assuming 230 working days per year, calculate:
1. The number of purchase during the year
2. Average inventory level including the safety stock
3. Average days of supply in inventory
4. Reorder point if the lead time is 15 working days
5. Total inventory costs per year and total inventory costs per
working days with purchase quantity of 100000 units.
6. EOQ
7. Total inventory costs per year and total inventory costs per
working days with EOQ and with a safety stock decreased to
5000 units.
14
OR
Q.5
ABC Ltd. Is a personal Computer assembling company based at
Hyderabad. Its marketing department has given the demand forecast
shown in the table for its PCs throughout the country in the coming six
months from January to June. Every worker assembles two computers a
day. The overtime cost is Rs. 3 per day per unit in excess of the
maximum capacity of the factory i.e. 200 units.
Month Jan Feb March April May June
Demand
forecast
(units)
1000 3000 1000 5000 7000 2000
No. of
working
days
24 25 20 22 20 24
Assume cost of change in output rate is:
1-100 2000
101-200 5000
201-300 8000
The company wants to find the total cost involved in the following plans:
(a) Level Output Rate Plan (b) Chase Plan
14
*************
FirstRanker.com - FirstRanker's Choice
This post was last modified on 19 February 2020