Q.1 (a) Define PERT and CPM. Explain the rules of constructing a network. 07
--- Content provided by FirstRanker.com ---
Q.1 (b) Define Project. Explain the Project Life Cycle in details. 07
Q.2 (a) Why team work is important in Project Management? Describe the Five Stage Team Development Model. 07
Q.2 (b) Discuss the conditions for Project Closure. 07
OR
Q.2 (b) Explain the types of risks a Project Manager may face while handling a project. 07
--- Content provided by FirstRanker.com ---
Q.3 (a) What is the meaning of Resource Constrained Project? Explain the types of Resource Constraints. 07
Q.3 (b) Explain the Top-Down approach for Estimating Project Time and Costs. 07
OR
Q.3 (b) Define Project Scope. Discuss about the Project Scope Checklist. 07
Q.4 (a) What is WBS? Explain the process of developing WBS. 07
--- Content provided by FirstRanker.com ---
Q.4 (b) Explain the types of Ownership Securities. 07
OR
Q.4 (b) Discuss about Project Financing in India and SEBI Guidelines. 07
Q.5 (a) Why do firms outsource Project Work? Discuss the advantages and disadvantages of outsourcing the Project Work. 07
Q.5 (b) Explain in details the Project Control Process. 07
--- Content provided by FirstRanker.com ---
OR
Q.5 (b) Discuss the qualities of an effective Project Manager. 07
Q.5 (b) Write a note on responsibilities of various stakeholders involved in a Project. 07
OR
Q.5 (b) Discuss various types of Hybrid Securities. Explain various ways by which Project Financing can be regulated. 07
--- Content provided by FirstRanker.com ---
Following is the activity and duration details of a construction project. 07
Activity Normal Time (Days)
1-2 10
1-3 11
2-4 13
--- Content provided by FirstRanker.com ---
2-6 14
3-4 10
4-5 7
4-6 17
5-7 13
--- Content provided by FirstRanker.com ---
6-7 9
7-8 1
You are required to help the contractor of the construction project with the following:
- Draw the network diagram
- Calculate EST, EFT, LST, LFT and slack for each activity
- Find Critical Path
--- Content provided by FirstRanker.com ---
Date: 01/12/2015
Total Marks: 70
--- Content provided by FirstRanker.com ---
This download link is referred from the post: GTU MBA Last 10 Years 2010-2020 Question Papers || Gujarat Technological University