1
Seat No.: ________ Enrolment No.___________

GUJARAT TECHNOLOGICAL UNIVERSITY

BE - SEMESTER ? VI (New) EXAMINATION ? WINTER 2019
Subject Code: 2161303 Date: 12/12/2019

Subject Name: Estimating, Specifications & Project Management

Time: 02:30 PM TO 05:00 PM Total Marks: 70

Instructions:

1. Attempt all questions.

2. Make suitable assumptions wherever necessary.

3. Figures to the right indicate full marks.

Q.1 (a) Define Project Management. 03
(b) Classify Contracts. 04
(c) Prepare a Tender Notice inviting tenders for BOD Incubator for an educational
institute with estimated cost of Rs.48000/-.
07

Q.2 (a) Define Contract. 03
(b) Classify Specifications. 04
(c) Restate essential requirements of a valid Contract. 07
OR
(c) Describe Unbalanced Tender with example 07

Q.3 (a) Define Estimating. 03
(b) Enlist objectives & uses of Specification. 04
(c) Prepare rate analysis for Cement concrete (1:2:4). 07
OR
Q.3 (a) Define Rate analysis. 03
(b) ?Project Management is a tool for cost saving?, Argue. 04
(c) Outline detailed specifications for Excavation work. 07

Q.4 (a) Define Tender. 03
(b) Differentiate between CPM & PERT. 04
(c) Evaluate Lump-sum Contract and Unit-rate Contract for their suitability. 07
OR
Q.4 (a) Define SOR. 03
(b) Compare Long-wall, Short-wall method and Center line method. 04
(c) Restate Condition of Contract for Arbitration. 07

Q.5 (a) Define Project Scheduling. 03
(b) Differentiate between Earnest Money Deposit & Security Deposit. 04
(c) Describe the procedure to carry out the estimation of quantities for typical Septic
Tank.
07
OR

Q.5 (a) Define Dummy Activity. 03
(b) Differentiate between Milestone chart & Bar chart. 04
(c) Calculate the Completion period and prepare Network diagram for following
details:
Activity Item A B C D E F G
Duration in Days 88 54 65 92 96 74 45
Activity Immediately Preceding --- A A B B,C D,E E
Activity Immediately Following B,C D,E E F F,G --- ---

07


*************