Download GTU BE/B.Tech 2019 Winter 8th Sem New 2180611 Construction Management Question Paper

Download GTU (Gujarat Technological University) BE/BTech (Bachelor of Engineering / Bachelor of Technology) 2019 Winter 8th Sem New 2180611 Construction Management Previous Question Paper

This post was last modified on 20 February 2020

GTU BE/B.Tech 2019 Winter Question Papers || Gujarat Technological University


FirstRanker.com

GUJARAT TECHNOLOGICAL UNIVERSITY
BE - SEMESTER- VIII (New) EXAMINATION — WINTER 2019

--- Content provided by‌ FirstRanker.com ---

Subject Code: 2180611 Date: 21/11/2019
Subject Name: Construction Management
Time: 02:30 PM TO 05:00 PM Total Marks: 70

Instructions:

  1. Attempt all questions.
  2. --- Content provided by‌ FirstRanker.com ---

  3. Make suitable assumptions wherever necessary.
  4. Figures to the right indicate full marks.

MARKS

Q.1

  1. Distinguish between CPM and PERT. 03
  2. --- Content provided by‍ FirstRanker.com ---

  3. Define “project” and state different phases through which a construction project passes. 04
  4. A contractor has been awarded a job that requires procurement of an equipment. Two brands “A” and “B” are available to perform the job. Brand “A” requires an investment of Rs. 5.00 lakhs, while brand “B” requires an investment of Rs.8.00 lakhs. The annual saving generated by brands A and B are given in table. Which brand of equipment should the contractor choose if rate of interest is 8% ?. 07

Equipment Year wise saving details (Rs. In Lakh)

1 2 3
Brand - A 3.00 3.00 3.00
Brand - B 3.60 3.60 3.60

Q.2

  1. What you mean by, a “construction company”? Distinguish between authority, responsibility and accountability. 03
  2. --- Content provided by‍ FirstRanker.com ---

  3. Write shortnote on “Effect of inflation on cash flow”. 04
  4. What are the traits of a project manager? Explain in detail. 07

OR

  1. Discuss in brief about different forms of business organization. 07

Q.3

--- Content provided by​ FirstRanker.com ---

  1. Define (i) Event (ii) Activity (iii) Network 03
  2. What is WBS? How is it helpful in planning, monitoring and controlling the projects? 04
  3. Find the expected time for completion of project for the activities tabled below. Draw the network diagram. 07

FirstRanker.com

Q.3

--- Content provided by⁠ FirstRanker.com ---

Q.4

Q.4

Q.5

  1. What do you understand by “ crashing of an activity”? How is it used for optimizing project cost? Explain with help of diagram. 03
  2. Enlist different types of schedules and explain staff and material scheduling. 04
  3. --- Content provided by‍ FirstRanker.com ---

  4. The following data shows time duration and activities of the project. The project overhead costs are Rs.2000/week. Calculate the optimum duration and cost associated with it. 07
Activity Duration (in week) Cost (Rs.)
Normal Crash Normal Crash
1-2 5 2 5000 10000
2-3 6 3 3000 7000
2-4 7 5 4000 6000
3-4 5 3 3500 9000
  1. What is meant by assets and liabilities? Give examples of assets and liabilities in context of construction organization. 03
  2. What are the different functions of material management? 04
  3. What is inventory? Write note on inventory and inventory related cost. 07

OR

--- Content provided by⁠ FirstRanker.com ---

  1. How do you define quality in construction? Discuss the concept of “quality” for construction industry. 03
  2. What do you mean by total quality management (TQM)? 04
  3. Explain the role and responsibilities of safety officer deputed at construction site. 07
  1. Write assumptions need to be followed prior to formulating model. 03
  2. Write traditional parameters on which project performance is measured. 04
  3. --- Content provided by⁠ FirstRanker.com ---

  4. Company manufacturing windows and doors has three plants. Plant -1 making aluminum frame, plant-2 making wooden frame and plant -3 making assembly. Product A- Aluminum frame door with glass and product B- wooden frame door with glass. How many units of A and B should be produced to generate maximum profit? The plant capacity available and utilized is given below. 07
Plant % plant capacity used % plant capacity available
A B
1 1 0 4
2 0 1 12
3 3 2 18
Unit profit 3 5

Q.5

  1. Write criteria for project evaluation. 03

OR

  1. Explain effect of various elements on project performance. 04
  2. --- Content provided by‌ FirstRanker.com ---

  3. A construction project consists of 11 activities. The predecessor relationship is shown by their node numbers in the table. Draw network diagram and critical path of project. 07
Activity Identity Duration (week)
(1,2) 4
(2,4) 16
(2,3) 14
(2,7) 30
(3,4) 8
(3,5) 16
(4,6) 6
(5,6) 15
(5,7) 9
(7,8) 24
(6, 8) 4