1
Seat No.: ________ Enrolment No.___________

GUJARAT TECHNOLOGICAL UNIVERSITY

BE - SEMESTER ? VIII (New) EXAMINATION ? WINTER 2019
Subject Code: 2182504 Date: 02/12/2019

Subject Name: Facilities Planning
Time: 02:30 PM TO 05:00 PM Total Marks: 70

Instructions:
1. Attempt all questions.
2. Make suitable assumptions wherever necessary.
3. Figures to the right indicate full marks.



MARKS

Q.1 (a) Define the terms:
1. Facility Planning
2. Industrial Wage
3. Depreciation
03
(b) How the work in process is reduced in Chemical
manufacturing plant?
04
(c) Describe the various factors to be considered in selecting
the location for the automobile repair shop.
07

Q.2 (a) Construct a layout of a small cotton mill. 03
(b) What should you keep in mind while preparing a facility
plan?
04
(c) Describe the general procedure for layout design using
flow chart.
07
OR
(c) Explain the steps for layout design using ALDEP. 07

Q.3 (a) What are the different factors that are responsible to
replace the equipment?
03
(b) Determine merits and demerits of Process Layout. 04
(c) What do you mean by JIT? Describe the elements and
characteristics of Just-in-time.
07
OR
Q.3 (a) Define accident. State the causes of industrial accidents. 03
(b) Briefly explain Minimum Wages Act, 1948. 04
(c) Describe Flexible Automation System with suitable
example.
07

Q.4 (a) Briefly explain Industrial Dispute Act, 1947. 03
(b) Give a brief classification of depreciation. 04
(c) Calculate the depreciation charges per hours for the
following data, using the machine hour basis method:
Cost of machine Rs. 11,000
Scrap value Rs. 1,000
Life of the machine 10 years.
07
OR
Q.4 (a) Explain planning of a facility plan. 03
(b) Describe the various types of replacement situations. 04
FirstRanker.com - FirstRanker's Choice
1
Seat No.: ________ Enrolment No.___________

GUJARAT TECHNOLOGICAL UNIVERSITY

BE - SEMESTER ? VIII (New) EXAMINATION ? WINTER 2019
Subject Code: 2182504 Date: 02/12/2019

Subject Name: Facilities Planning
Time: 02:30 PM TO 05:00 PM Total Marks: 70

Instructions:
1. Attempt all questions.
2. Make suitable assumptions wherever necessary.
3. Figures to the right indicate full marks.



MARKS

Q.1 (a) Define the terms:
1. Facility Planning
2. Industrial Wage
3. Depreciation
03
(b) How the work in process is reduced in Chemical
manufacturing plant?
04
(c) Describe the various factors to be considered in selecting
the location for the automobile repair shop.
07

Q.2 (a) Construct a layout of a small cotton mill. 03
(b) What should you keep in mind while preparing a facility
plan?
04
(c) Describe the general procedure for layout design using
flow chart.
07
OR
(c) Explain the steps for layout design using ALDEP. 07

Q.3 (a) What are the different factors that are responsible to
replace the equipment?
03
(b) Determine merits and demerits of Process Layout. 04
(c) What do you mean by JIT? Describe the elements and
characteristics of Just-in-time.
07
OR
Q.3 (a) Define accident. State the causes of industrial accidents. 03
(b) Briefly explain Minimum Wages Act, 1948. 04
(c) Describe Flexible Automation System with suitable
example.
07

Q.4 (a) Briefly explain Industrial Dispute Act, 1947. 03
(b) Give a brief classification of depreciation. 04
(c) Calculate the depreciation charges per hours for the
following data, using the machine hour basis method:
Cost of machine Rs. 11,000
Scrap value Rs. 1,000
Life of the machine 10 years.
07
OR
Q.4 (a) Explain planning of a facility plan. 03
(b) Describe the various types of replacement situations. 04
2
(c) A machine costing Rs. 4,50,000 has a scrap value of Rs.
50,000 after 10 years of service. The estimated rate of
production is 12 units per hour. Using the productive unit
method calculate the rate of depreciation and also
depreciation per year. Assume 50 week per year and 48
working hours per week.
07

Q.5 (a) What are the causes and sources of accidents? 03
(b) Describe any four material handling equipments used in
casting industry.
04
(c) Classify material handling devices. Draw and explain
working of a hand trucks.
07
OR

Q.5 (a) What are the various methods of depreciation? Explain
any one method of calculating depreciation.
03
(b) Explain material handling in product layout. 04
(c) Draw any two types of cranes and state its specific uses. 07

*************
FirstRanker.com - FirstRanker's Choice