Download GTU (Gujarat Technological University) BE/BTech (Bachelor of Engineering / Bachelor of Technology) 2019 Summer 4th Sem New 2142905 Statistical Quality Control And Textile Costing Previous Question Paper
Seat No.: ________ Enrolment No.___________
GUJARAT TECHNOLOGICAL UNIVERSITY
BE - SEMESTER ?IV(NEW) ? EXAMINATION ? SUMMER 2019
Subject Code:2142905 Date:15/05/2019
Subject Name: Statistical Quality Control & Textile Costing
Time: 02:30 PM TO 05:00 PM Total Marks: 70
Instructions:
1. Attempt all questions.
2. Make suitable assumptions wherever necessary.
3. Figures to the right indicate full marks.
MARKS
Q.1 (a) Define the term: 1. Standard Deviation 2. PMD 3. Coefficient of variation 03
(b) Explain significance of control chart. 04
(c) Following are the results of the fabric strength (in 10 gm) obtained from the
samples of two different fabrics.
Fabric A 22.0 21.5 22.8 21.0 23.0 20.9 21.6 22.0 22.8 21.2
Fabric B 22.3 21.6 22.0 22.1 22.0 22.3 21.8 21.8 21.6 21.8
Find out using above data which fabric is more consistent in terms of the
strength.
07
Q.2 (a) Ten-count tests carried out on the yarn of a cone have shown AM 25.62 and
another 15-count tests carried out on the yarn of same cone have shown AM
26.25. what is the AM of the yarn if all 25 tests taken together?
03
(b) Explain Binomial distribution with their properties. 04
(c) Conduct the analysis of variance (one-way classification) for the following
data. State whether the lea cunt differ between the bobbins.
Lean
No.
Bobbin No.
1 2 3 4 5 6
1 22 23 24 21 20 19
2 21 20 22 23 24 19
3 20 19 21 20 22 23
4 18 24 20 19 22 24
Table value of F for 5, 18 d.f. at 5% level=2.77 & level=4.25
07
OR
(c) An experiment was conducted to study the effect of the speed of the ring
frame on the count of the yarn. The yarn was spun with four different speeds
on three different ring frames and the results yarn counts are follows.
Speed (RPM)
Ring
Frame
15000 16000 17000 18000
I 85 88 85 90
II 70 85 90 95
III 80 82 88 92
Carry out analysis of the above data and write the conclusions.
(Table value of F for 3, 6 degree of freedom at 5% level = 4.76)
(Table value of F for 2, 6 degree of freedom at 5% level = 5.14)
07
Q.3 (a) What is correlation? Explain positive and negative correlation. 03
(b) Find out Quartile deviation of the following data and its relative measure.
Value 10 15 20 25 30 35 40
Frequency 5 10 16 20 14 8 4
04
(c) Compute karl pearson?s coefficient of correlation from following data of
percentage humidity and warp breakages were recorded from a weaving
factory and comment on it.
07
FirstRanker.com - FirstRanker's Choice
1
Seat No.: ________ Enrolment No.___________
GUJARAT TECHNOLOGICAL UNIVERSITY
BE - SEMESTER ?IV(NEW) ? EXAMINATION ? SUMMER 2019
Subject Code:2142905 Date:15/05/2019
Subject Name: Statistical Quality Control & Textile Costing
Time: 02:30 PM TO 05:00 PM Total Marks: 70
Instructions:
1. Attempt all questions.
2. Make suitable assumptions wherever necessary.
3. Figures to the right indicate full marks.
MARKS
Q.1 (a) Define the term: 1. Standard Deviation 2. PMD 3. Coefficient of variation 03
(b) Explain significance of control chart. 04
(c) Following are the results of the fabric strength (in 10 gm) obtained from the
samples of two different fabrics.
Fabric A 22.0 21.5 22.8 21.0 23.0 20.9 21.6 22.0 22.8 21.2
Fabric B 22.3 21.6 22.0 22.1 22.0 22.3 21.8 21.8 21.6 21.8
Find out using above data which fabric is more consistent in terms of the
strength.
07
Q.2 (a) Ten-count tests carried out on the yarn of a cone have shown AM 25.62 and
another 15-count tests carried out on the yarn of same cone have shown AM
26.25. what is the AM of the yarn if all 25 tests taken together?
03
(b) Explain Binomial distribution with their properties. 04
(c) Conduct the analysis of variance (one-way classification) for the following
data. State whether the lea cunt differ between the bobbins.
Lean
No.
Bobbin No.
1 2 3 4 5 6
1 22 23 24 21 20 19
2 21 20 22 23 24 19
3 20 19 21 20 22 23
4 18 24 20 19 22 24
Table value of F for 5, 18 d.f. at 5% level=2.77 & level=4.25
07
OR
(c) An experiment was conducted to study the effect of the speed of the ring
frame on the count of the yarn. The yarn was spun with four different speeds
on three different ring frames and the results yarn counts are follows.
Speed (RPM)
Ring
Frame
15000 16000 17000 18000
I 85 88 85 90
II 70 85 90 95
III 80 82 88 92
Carry out analysis of the above data and write the conclusions.
(Table value of F for 3, 6 degree of freedom at 5% level = 4.76)
(Table value of F for 2, 6 degree of freedom at 5% level = 5.14)
07
Q.3 (a) What is correlation? Explain positive and negative correlation. 03
(b) Find out Quartile deviation of the following data and its relative measure.
Value 10 15 20 25 30 35 40
Frequency 5 10 16 20 14 8 4
04
(c) Compute karl pearson?s coefficient of correlation from following data of
percentage humidity and warp breakages were recorded from a weaving
factory and comment on it.
07
2
% Humidity 60 62 59 70 56 58 75
Warp
Breakages
112 110 120 102 122 118 90
OR
Q.3 (a) Explain Poisson distribution with their properties. 03
(b) State the properties of Normal distribution. 04
(c) Following are the marks obtained by eight different students in the subjects
of mathematics and the subject of statistics.
Student no. 1 2 3 4 5 6 7 8
Marks in
Mathematics
50 52 68 70 72 70 63 75
Marks in
statistics
50 90 60 80 67 62 65 80
Calculate rank correlation coefficient using the above data and comment on
it.
07
Q.4 (a) Briefly explain about the small sample t-test. 03
(b) Five knitted garments each were selected at eight different times during the
production and following results of number of defective garments were
obtained.
Sample nos. 1 2 3 4 5 6 7 8
No. of defective garments 0 2 1 1 2 0 0 0
Draw the np-chart for the above data.
04
(c) Ten ring bobbins selected from the production of the day shift and fifteen
ring bobbins selected from the production of the night shift have shown
following results.
Day shift Night shift
No. of tests 10 15
Average count 40.2 39.3
Std. dev. of count 2.5 3.8
From these sample results, is there any evidence that the yarn spun during
night shift is coarser than the day shift? Use 10% los. (Table value
t23,0.1=1.319)
07
OR
Q.4 (a) Explain about collection and types of data. 03
(b) Following data represents average and range of linear density of the yarn
obtained from eight different samples each size five, selected during a
spinning process.
Sample nos. 1 2 3 4 5 6 7 8
Avg. Linear density 19.6 20.1 20.5 19.4 22.3 21.7 20.3 19.9
Range 1.2 2.1 1.6 1.8 2.0 1.7 2.0 1.8
Draw the mean charts for the above data.(A2=0.577)
04
(c) The following data are related to the percentage of humidity and the warp
breakage rate recorded for a week in a loom shed.
% Humidity 54 85 86 50 42 75 65 56
Warp breakage rate 2.45 1.21 1.20 2.84 3.25 1.86 1.90 2.32
Using equation of line of regression, find warp breakage rate if humidity
percentage on a specific day is 60 for given data.
07
Q.5 (a) Find out median from the following data.
Class 0-10 10-20 20-30 30-40 40-50
Frequency 18 30 46 34 22
03
(b) Discuss about population and sample. 04
(c) Explain in detail about DMAIC process. 07
FirstRanker.com - FirstRanker's Choice
1
Seat No.: ________ Enrolment No.___________
GUJARAT TECHNOLOGICAL UNIVERSITY
BE - SEMESTER ?IV(NEW) ? EXAMINATION ? SUMMER 2019
Subject Code:2142905 Date:15/05/2019
Subject Name: Statistical Quality Control & Textile Costing
Time: 02:30 PM TO 05:00 PM Total Marks: 70
Instructions:
1. Attempt all questions.
2. Make suitable assumptions wherever necessary.
3. Figures to the right indicate full marks.
MARKS
Q.1 (a) Define the term: 1. Standard Deviation 2. PMD 3. Coefficient of variation 03
(b) Explain significance of control chart. 04
(c) Following are the results of the fabric strength (in 10 gm) obtained from the
samples of two different fabrics.
Fabric A 22.0 21.5 22.8 21.0 23.0 20.9 21.6 22.0 22.8 21.2
Fabric B 22.3 21.6 22.0 22.1 22.0 22.3 21.8 21.8 21.6 21.8
Find out using above data which fabric is more consistent in terms of the
strength.
07
Q.2 (a) Ten-count tests carried out on the yarn of a cone have shown AM 25.62 and
another 15-count tests carried out on the yarn of same cone have shown AM
26.25. what is the AM of the yarn if all 25 tests taken together?
03
(b) Explain Binomial distribution with their properties. 04
(c) Conduct the analysis of variance (one-way classification) for the following
data. State whether the lea cunt differ between the bobbins.
Lean
No.
Bobbin No.
1 2 3 4 5 6
1 22 23 24 21 20 19
2 21 20 22 23 24 19
3 20 19 21 20 22 23
4 18 24 20 19 22 24
Table value of F for 5, 18 d.f. at 5% level=2.77 & level=4.25
07
OR
(c) An experiment was conducted to study the effect of the speed of the ring
frame on the count of the yarn. The yarn was spun with four different speeds
on three different ring frames and the results yarn counts are follows.
Speed (RPM)
Ring
Frame
15000 16000 17000 18000
I 85 88 85 90
II 70 85 90 95
III 80 82 88 92
Carry out analysis of the above data and write the conclusions.
(Table value of F for 3, 6 degree of freedom at 5% level = 4.76)
(Table value of F for 2, 6 degree of freedom at 5% level = 5.14)
07
Q.3 (a) What is correlation? Explain positive and negative correlation. 03
(b) Find out Quartile deviation of the following data and its relative measure.
Value 10 15 20 25 30 35 40
Frequency 5 10 16 20 14 8 4
04
(c) Compute karl pearson?s coefficient of correlation from following data of
percentage humidity and warp breakages were recorded from a weaving
factory and comment on it.
07
2
% Humidity 60 62 59 70 56 58 75
Warp
Breakages
112 110 120 102 122 118 90
OR
Q.3 (a) Explain Poisson distribution with their properties. 03
(b) State the properties of Normal distribution. 04
(c) Following are the marks obtained by eight different students in the subjects
of mathematics and the subject of statistics.
Student no. 1 2 3 4 5 6 7 8
Marks in
Mathematics
50 52 68 70 72 70 63 75
Marks in
statistics
50 90 60 80 67 62 65 80
Calculate rank correlation coefficient using the above data and comment on
it.
07
Q.4 (a) Briefly explain about the small sample t-test. 03
(b) Five knitted garments each were selected at eight different times during the
production and following results of number of defective garments were
obtained.
Sample nos. 1 2 3 4 5 6 7 8
No. of defective garments 0 2 1 1 2 0 0 0
Draw the np-chart for the above data.
04
(c) Ten ring bobbins selected from the production of the day shift and fifteen
ring bobbins selected from the production of the night shift have shown
following results.
Day shift Night shift
No. of tests 10 15
Average count 40.2 39.3
Std. dev. of count 2.5 3.8
From these sample results, is there any evidence that the yarn spun during
night shift is coarser than the day shift? Use 10% los. (Table value
t23,0.1=1.319)
07
OR
Q.4 (a) Explain about collection and types of data. 03
(b) Following data represents average and range of linear density of the yarn
obtained from eight different samples each size five, selected during a
spinning process.
Sample nos. 1 2 3 4 5 6 7 8
Avg. Linear density 19.6 20.1 20.5 19.4 22.3 21.7 20.3 19.9
Range 1.2 2.1 1.6 1.8 2.0 1.7 2.0 1.8
Draw the mean charts for the above data.(A2=0.577)
04
(c) The following data are related to the percentage of humidity and the warp
breakage rate recorded for a week in a loom shed.
% Humidity 54 85 86 50 42 75 65 56
Warp breakage rate 2.45 1.21 1.20 2.84 3.25 1.86 1.90 2.32
Using equation of line of regression, find warp breakage rate if humidity
percentage on a specific day is 60 for given data.
07
Q.5 (a) Find out median from the following data.
Class 0-10 10-20 20-30 30-40 40-50
Frequency 18 30 46 34 22
03
(b) Discuss about population and sample. 04
(c) Explain in detail about DMAIC process. 07
3
OR
Q.5 (a) Write short note on Material cost. 03
(b) Write short note on labour cost. 04
(c) A spinning mill is working with following mix:
Cotton Variety Proportion (%) Cost/Kg. (in Rs.)
P1 10 4
P2 20 5
P3 30 6
P4 40 7
Calculate clean cotton cost/kg. If yarn realization is 88% & that out of the 25
kg lost per 100kg. put through, 8 kg. are saleable at 1.75 Rs./kg.
07
*************