1
Seat No.: ________ Enrolment No.___________
GUJARAT TECHNOLOGICAL UNIVERSITY
BE - SEMESTER ?VI(NEW) ? EXAMINATION ? SUMMER 2019
Subject Code:2161303 Date:21/05/2019
Subject Name:Estimating, Specifications & Project Management
Time:10:30 AM TO 01:00 PM Total Marks: 70
Instructions:
1. Attempt all questions.
2. Make suitable assumptions wherever necessary.
3. Figures to the right indicate full marks.


Q.1 (a) Define: ( i) contract (ii) specifications 03
(b) What is plastering? What are the requirements of good plaster? 04
(c) Enlist types of foundations and explain any one in detail. 07

Q.2 (a) Enlist types of estimates. 03
(b) Write importance and purpose of specifications. 04
(c) Prepare rate analysis for 12 mm thick plastering. 07
OR
(c) Prepare rate analysis for R.C.C. (1:2:4) work. 07

Q.3 (a) What is subsurface investigation? 03
(b) Which are the factors affecting rate analysis. 04
(c) Explain long wall and short wall method of estimation with examples. 07
OR
Q.3 (a) Write a short note on measurement book. 03
(b) Describe Rubble masonry in detail. 04
(c) Write a short note on ?Earnest money? & ?security deposit?. 07

Q.4 (a) What is project planning? 03
(b) Explain the following terms for the condition of contract.
Alteration, Addition, Omission.
04
(c) Explain lump-sum contract in detail. 07
OR
Q.4 (a) What is SOR? 03
(b) Differentiate between PERT and CPM. 04
(c) What to do you understand by a ?dummy?? What are its uses? 07

Q.5 (a) Define Optimistic time and Pessimistic time. 03
(b) Define and briefly explain an activity & event of a project. 04
(c) Write detailed specifications of R.C.C.(1:2:4) work. 07
OR

Q.5 (a) What is unbalanced tender? 03
(b) Differentiate between Milestone chart and Bar chart. 04
(c) Prepare a tender notice inviting tenders for BOD incubator for R & D
laboratory with estimated cost of Rs. 65000.
07

*************