Download GTU BE/B.Tech 2018 Winter 3rd Sem New 2132905 Basic Engineering In Textile Question Paper

Download GTU (Gujarat Technological University) BE/BTech (Bachelor of Engineering / Bachelor of Technology) 2018 Winter 3rd Sem New 2132905 Basic Engineering In Textile Previous Question Paper

www.FirstRanker.com
1
Seat No.: ________ Enrolment No.___________

GUJARAT TECHNOLOGICAL UNIVERSITY

BE - SEMESTER?III (New) EXAMINATION ? WINTER 2018
Subject Code: 2132905 Date:14/12/2018

Subject Name: Basic Engineering in Textile

Time: 10:30 AM TO 01:00 PM Total Marks: 70

Instructions:

1. Attempt all questions.

2. Make suitable assumptions wherever necessary.

3. Figures to the right indicate full marks.



MARKS

Q.1 (a) Differentiate between fire tube boiler and water tube boiler. 03
(b) Define maintenance. What are the types of maintenance?

04
(c) Explain basic steps in Method Study by algorithm. 07

Q.2 (a) Give the detail classification of boiler. 03
(b) Advantages and disadvantages of water tube boiler over the fire tube boiler. 04
(c) Describe the Hungarian method procedure for Assignment problem in detail. 07
OR
(c) Use graphical method to solve following LPP.
Maximize Z = 20 x 1 + 10 x 2
Subject to, x 1+2 x 2 ? 40
3x1+ x2 ? 30
4x1+ 3x2 ? 60
x 1, x 2, ? 0
07
Q.3 (a) What is standard time? Describe briefly how you will calculate ?standard time?
from the observed time obtained by time study?

03
(b) Explain functions or elements of preventive maintenance. 04
(c)
Consider the project consist of following activities in weeks

Activity 1-2 1-3 2-4 3-4 3-5 4-9 5-6 5-7 6-8 7-8 8-10 9-10
Duration 4 1 1 1 6 5 4 8 1 2 5 7

Calculate the total project duration, critical path and total float
07
OR
Q.3 (a) Explain humidification and dehumidification. 03
(b) Explain work measurement by algorithm. 04
(c) Write a short note on Flow process chart 07
Q.4 (a) Draw two handed process chart for signing a letter and give summary for same. 03
(b) Explain any one feed water treatment with neat sketch. 04
(c) A company has 5 jobs to be done on five machines. Any job can be done on any
machine. The cost of doing the jobs on different machines is given below. Assign the
jobs for different machines so as to minimize the total cost.


07
www.FirstRanker.com www.FirstRanker.com
www.FirstRanker.com
FirstRanker.com - FirstRanker's Choice
www.FirstRanker.com
1
Seat No.: ________ Enrolment No.___________

GUJARAT TECHNOLOGICAL UNIVERSITY

BE - SEMESTER?III (New) EXAMINATION ? WINTER 2018
Subject Code: 2132905 Date:14/12/2018

Subject Name: Basic Engineering in Textile

Time: 10:30 AM TO 01:00 PM Total Marks: 70

Instructions:

1. Attempt all questions.

2. Make suitable assumptions wherever necessary.

3. Figures to the right indicate full marks.



MARKS

Q.1 (a) Differentiate between fire tube boiler and water tube boiler. 03
(b) Define maintenance. What are the types of maintenance?

04
(c) Explain basic steps in Method Study by algorithm. 07

Q.2 (a) Give the detail classification of boiler. 03
(b) Advantages and disadvantages of water tube boiler over the fire tube boiler. 04
(c) Describe the Hungarian method procedure for Assignment problem in detail. 07
OR
(c) Use graphical method to solve following LPP.
Maximize Z = 20 x 1 + 10 x 2
Subject to, x 1+2 x 2 ? 40
3x1+ x2 ? 30
4x1+ 3x2 ? 60
x 1, x 2, ? 0
07
Q.3 (a) What is standard time? Describe briefly how you will calculate ?standard time?
from the observed time obtained by time study?

03
(b) Explain functions or elements of preventive maintenance. 04
(c)
Consider the project consist of following activities in weeks

Activity 1-2 1-3 2-4 3-4 3-5 4-9 5-6 5-7 6-8 7-8 8-10 9-10
Duration 4 1 1 1 6 5 4 8 1 2 5 7

Calculate the total project duration, critical path and total float
07
OR
Q.3 (a) Explain humidification and dehumidification. 03
(b) Explain work measurement by algorithm. 04
(c) Write a short note on Flow process chart 07
Q.4 (a) Draw two handed process chart for signing a letter and give summary for same. 03
(b) Explain any one feed water treatment with neat sketch. 04
(c) A company has 5 jobs to be done on five machines. Any job can be done on any
machine. The cost of doing the jobs on different machines is given below. Assign the
jobs for different machines so as to minimize the total cost.


07
www.FirstRanker.com www.FirstRanker.com
www.FirstRanker.com
www.FirstRanker.com
2



Jobs
Machines
A B C D E
1 13 8 16 18 19
2 9 15 24 9 12
3 12 9 4 4 4
4
6

12 10 8 13
5 15 17 18 12 20
OR
Q.4 (a)
Explain basic procedure for the method study.
03
(b) Differentiate breakdown maintenance and preventive maintenance. 04
(c)
Obtain the initial basic feasible solution for the following transportation problem by
north-west corner rule. Also find the optimality
Origin/Destination D 1 D 2 D 3 Supply
O 1 2 7 4 5
O 2 3 3 1 8
O 3 5 4 7 7
O 4 1 6 2 14
Demand 7 9 18 34

07
Q.5 (a) Define three floats in CPM and PERT 03
(b) Explain Cochran boiler with neat sketch 04
(c) A Consider the following project. Find the path and standard deviation. Also find
probability of completing the project by 18 weeks.
Activity Optimistic
time
Most likely
time
Pessimistic
time
A(1-2) 3 6 9
B(1-3) 2 5 8
C(2-4) 2 4 6
D(3-4) 2 3 10
E(3-5) 1 3 11
F(4-6) 4 6 8
G(5-6) 1 5 15

07
OR
Q.5 (a) Define terms in PERT network: i) Optimistic time ii) Most likely time iii)
expected time
03
(b) Explain necessity of water treatment of boiler feed water 04
(c) Explain PMTS and MTM in brief 07

*************