FirstRanker Logo

FirstRanker.com - FirstRanker's Choice is a hub of Question Papers & Study Materials for B-Tech, B.E, M-Tech, MCA, M.Sc, MBBS, BDS, MBA, B.Sc, Degree, B.Sc Nursing, B-Pharmacy, D-Pharmacy, MD, Medical, Dental, Engineering students. All services of FirstRanker.com are FREE

📱

Get the MBBS Question Bank Android App

Access previous years' papers, solved question papers, notes, and more on the go!

Install From Play Store

Download GTU BE/B.Tech 2018 Winter 6th Sem New 2160604 Water And Waste Water Engineering Question Paper

Download GTU (Gujarat Technological University) BE/BTech (Bachelor of Engineering / Bachelor of Technology) 2018 Winter 6th Sem New 2160604 Water And Waste Water Engineering Previous Question Paper

This post was last modified on 20 February 2020

GTU BE/B.Tech 2018 Winter Question Papers || Gujarat Technological University



FirstRanker.com


--- Content provided by‍ FirstRanker.com ---

GUJARAT TECHNOLOGICAL UNIVERSITY

BE - SEMESTER-VI (NEW) EXAMINATION - WINTER 2018

Subject Code:2160604 Date:30/11/2018

--- Content provided by⁠ FirstRanker.com ---


Subject Name:Water & Waste Water Engineering

Time: 02:30 PM TO 05:00 PM Total Marks: 70


--- Content provided by FirstRanker.com ---

Instructions:

1. Attempt all questions.

2. Make suitable assumptions wherever necessary.

--- Content provided by‌ FirstRanker.com ---


3. Figures to the right indicate full marks.

Q.1 (a) Give the classification of intake. 03

(b) Differentiate between slow sand filter and rapid sand filter 04

--- Content provided by FirstRanker.com ---


(c) Design a plain sedimentation tank for treating 10 MLD of water 07

Q.2 (a) What are the objectives of water treatment 03

(b) State and explain different components of water supply scheme 04

--- Content provided by⁠ FirstRanker.com ---


(c) Explain with neat sketch the working of trickling filter 07


OR


--- Content provided by⁠ FirstRanker.com ---

(c) Enlist different types of pipes used for water supply. Explain Cast iron pipe in detail. 07

Q.3 (a) How will determine the optimum dose of a coagulant for a given quality of raw water 03

(b) Explain different factors affecting the selection of a proper water treatment train. 04

--- Content provided by​ FirstRanker.com ---

(c) A main combined sewer is to be designed to serve an area of 20 sq. km with a population density of 250 persons/hectare. The average rate of sewage flow is 300 litres/capita/day. The maximum flow is 60% in excess of average together with the rainfall equivalent of 15 mm in 24 hours, all of which appears as runoff. Determine the capacity of the sewer. Taking the maximum velocity of flow as 2.0 m/s, determine the size of the circular sewer. 07


OR


Q.3 (a) Define: 1. Super chlorination 2. Dechlorination 3. Post chlorination 03

--- Content provided by⁠ FirstRanker.com ---


(b) What are the requirements of a good distribution system? 04

(c) Explain different layouts of distribution network with their relative advantages and disadvantages. 07

Q.4 (a) Write a short note on soak pit. 03

--- Content provided by‌ FirstRanker.com ---


(b) What is rising main? Explain how you will find out economical diameter of rising main and head loss in rising main. 04

(c) Draw a typical flow sheet of a municipal wastewater treatment plant and explain the functions of each unit. 07


--- Content provided by⁠ FirstRanker.com ---

OR


Q.4 (a) Explain how symbiotic relationship between algae and bacteria is used in oxidation pond used for treatment of sewage. 03

(b) Explain break point chlorination. 04

--- Content provided by​ FirstRanker.com ---


(c) Explain the need of low cost sanitation system. Explain the design steps of septic tank 07

Q.5 (a) Differentiate between separate and combined sewerage system. 03

(b) Differentiate between trickling filter and activated sludge unit. 04

--- Content provided by⁠ FirstRanker.com ---


(c) Enlist different sewer appurtenances and describe deep man hole in detail. 07


OR


--- Content provided by‍ FirstRanker.com ---

(a) What is meant by water softening? Enlist different methods used for water softening. 03

(b) Explain how will find the capacity of an elevated service reservoir in a water distribution system. 04

(c) Why preliminary treatment is needed before primary and secondary treatment of wastewater. Explain working of any two units used for preliminary treatment of wastewater. 07