GUJARAT TECHNOLOGICAL UNIVERSITY
BE - SEMESTER-VII (NEW) EXAMINATION - WINTER 2018
--- Content provided by FirstRanker.com ---
Subject Code: 2173611 Date: 29/11/2018Subject Name: Project & Plant Engineering
Time: 10:30 AM TO 01:00 PM Total Marks: 70
Instructions:
- Attempt all questions.
- Make suitable assumptions wherever necessary.
- Figures to the right indicate full marks.
--- Content provided by FirstRanker.com ---
MARKS
Q.1 (a) Explain the significance of plant design. 03
(b) Write a note on 1) Chilling water, 2) Compress air 04
--- Content provided by FirstRanker.com ---
(c) Explain various stages of project implementation. 07Q.2 (a) Define 1) Salvage value 2) Scrap value 3) Cost index 03
(b) Explain the importance of safety in chemical process industry. 04
(c) Discuss in detail about preliminary feasibility report 07
OR
--- Content provided by FirstRanker.com ---
(c) What are the different methods used for profitability evaluation? Explain any two in detail. 07Q.3 (a) Explain cash flow. 03
(b) Write a short note on pilot plant. 04
(c) Explain various factors affecting plant location. 07
OR
--- Content provided by FirstRanker.com ---
Q.3 (a) Write a note on alternative investment. 03(b) What are the different methods used for estimating capital investment? 04
Explain any one in detail.
(c) Explain factors affecting production-cost. 07
Q.4 (a) Explain the various methods of waste water treatment. 03
--- Content provided by FirstRanker.com ---
(b) Write a short note on boiler feed water. 04(c) Explain various methods used for estimating depreciation. 07
OR
Q.4 (a) Write a short note on steam as a utility. 03
(b) Explain cost index in detail. 04
--- Content provided by FirstRanker.com ---
(c) The initial cost of CSTR is ? 50.00 lakh. At the end of useful life of 15 years its salvage value is estimated to be ? 1.25 lakh. Determine the asset value of the CSTR at the end of 7 years usingI. Straight-line method
II. Double declining balance method. 07
Q.5 (a) Write a short note on payback period. 03
(b) Explain various utilities used in chemical plants. 04
--- Content provided by FirstRanker.com ---
(c) Explain break-even analysis in detail. 07OR
Q.5 (a) Explain selection criteria for process equipment. 03
(b) Explain standard and special equipment’s. 04
(c) Write a note on CPM and PERT. 07