Seat No.: Enrolment No.
GUJARAT TECHNOLOGICAL UNIVERSITY
--- Content provided by FirstRanker.com ---
BE - SEMESTER-VII (NEW) EXAMINATION - WINTER 2018
Subject Code: 2174002 Date: 19/11/2018
Subject Name: Construction Planning & Management
Time: 10:30 AM TO 01:00 PM Total Marks: 70
Instructions:
--- Content provided by FirstRanker.com ---
- Attempt all questions.
- Make suitable assumptions wherever necessary.
- Figures to the right indicate full marks.
MARKS
Q.1 (a) Differentiate between logical dummy and numbering dummy in a CPM network with suitable example. 03
--- Content provided by FirstRanker.com ---
(b) Activity i and j (duration di and dj) are having following logical relationships: Start to Start, Start to Finish, Finish to Finish. Derive equations for calculating event times of Activities i & J. ) 04
(c) Draw a CPM-AOA network for following project data and find out the floats available for all the activities 07
Activity | IPA | Duration (weeks) | Activity | IPA | Duration (weeks) |
---|---|---|---|---|---|
A | - | 4 | G | D | 6 |
B | - | 6 | H | C,G | 4 |
C | A | 5 | I | D | 7 |
D | A | 6 | J | H,F,I | 3 |
E | A | 5 | K | I | 5 |
F | E | 3 | L | K | 3 |
Draw the linked bar chart for the project data also.
Q.2 (a) Briefly explain the situations where a numbering dummy is included in a CPM-AOA network. Support your explanation with a network sketch. 02
(b) Draw the CPM-AON diagram and calculate the critical, total floats and free floats for the schedule shown below. 05
--- Content provided by FirstRanker.com ---
Activity | IPA | Duration (weeks) | Activity | IPA | Duration (weeks) |
---|---|---|---|---|---|
A | - | 2 | H | D | 9 |
B | A | 7 | I | F,G | 12 |
C | A | 10 | J | F | 5 |
D | A | 4 | K | E,J | 5 |
E | B | 6 | L | G,H | 6 |
F | B,C | 5 | M | F,H | 4 |
G | C,D | 8 | N | L,K,M | 3 |
(c) Draw a Late Start (LS) based resource histogram for the project data given in Q.1 (c) with following resource requirements 07
Activity | Total Resources (No) | Activity | Total Resources (No) |
---|---|---|---|
A | 16 | G | 18 |
B | 12 | H | 8 |
C | 25 | I | 49 |
D | 20 | J | 6 |
E | 5 | K | 20 |
F | 9 | L | 6 |
OR
(c) Draw the AON diagram and perform the CPM network computations (including floats) for the schedule shown next. 07
Activity | IPA | Duration (weeks) |
---|---|---|
A | - | 2 |
B | - | 6 |
C | A | 3 |
D | B | 1 |
E | B | 4 |
F | C,D | 8 |
G | C,D | 2 |
H | E | 11 |
I | F,G,H | 4 |
Q.3 (a) The expected completion time for a project is 32 months with a variance of 7.6 months. What is the probability that project will be completed in 30 months. 03
--- Content provided by FirstRanker.com ---
(b) Perform the forward and backward pass for the network shown below and calculate the activity times (ES, EF, LS & LF) 04
(c) A contractor agreed to build 30 dog houses in 90 days at a price of Rs. 8000 per unit. Twenty days later, the contractor has finished 8 dog houses with an actual total cost (that includes his overhead and profit) of Rs. 68000. What is the status of the project? 07
OR
Q.3 (a) Draw LOB Planning Diagram for following situations 03
Activity B is faster than Activity A
--- Content provided by FirstRanker.com ---
Activity D is faster than Activity C but both are to be completed together
(b) Briefly explain Work Break Down Structure and its use in project management. Use sketch to explain different hierarchy in WBS 04
(c) In Q. 2 (c), 10 days after the project has started, you receive the following report: 07
Activities A and D are complete, actual dates: A (0, 2), D (5, 9).
--- Content provided by FirstRanker.com ---
Activity B started on day 5. Remaining duration: 2 days.
Activity C started on day 2. Some problems were encountered. Remaining duration 4 days.
The duration for activity F was adjusted to 8 days.
Activity J has been canceled.
The duration for new activity P is 4 days. New logical relations: New IPA: E and F. Immediately succeeding activity) is K.
--- Content provided by FirstRanker.com ---
Update the network diagram.
Q.4 (a) Briefly explain how direct cost and indirect cost of a project vary with project completion time. How activities are prioritized/selected for crashing? 03
(b) Draw the network for the following project. 04
Activity | IPA | Duration (Days) | ||
---|---|---|---|---|
Optimistic (To) | Most Likely (Tm) | Pessimistic (Tp) | ||
A | - | 4 | 5 | 6 |
B | A | 10 | 12 | 14 |
C | A | 7 | 9 | 16 |
D | B | 14 | 17 | 22 |
E | B,C | 10 | 15 | 30 |
F | C | 4 | 7 | 13 |
G | D | 12 | 20 | 40 |
H | D,E | 10 | 12 | 15 |
I | F,H | 8 | 9 | 10 |
Compare the three paths: ABDHI, ABDG, and ABEHI. Calculate the Expected Duration and Standard Deviation for each path. Considering all three paths, what is the duration of the project with at least 95% confidence? 07
(c) Perform the forward and backward passes on the precedence network shown in Figure below. 07
--- Content provided by FirstRanker.com ---
OR
Q.4 (a) Draw the status bar chart (linked) of the above project data (Q.4b) at the end of 12 weeks.
Activity A, B, C are completed, C is 50% completed. 03
Q.5 (b) Activity details of a construction project are given below. Complete the following scheduling tasks: 04
--- Content provided by FirstRanker.com ---
Activity | IPA | Duration (Weeks) | Cost (Rs) |
---|---|---|---|
A | - | 5 | 4000 |
B | - | 7 | 20000 |
C | A | 3 | 6000 |
D | A | 10 | 10000 |
E | B | 4 | 9000 |
F | B | 5 | 8000 |
G | C,D | 6 | 6000 |
H | E,F | 2 | 10000 |
Calculate the cash flow requirement for first 10 weeks if the project is scheduled as per early start of activities (ES Schedule). 07
(a) Following data is available for a project. Find out the expected completion time of the project along with its standard deviation. What is the probability that the project will be completed in 19 months? 04
Activity (i-j) | Expected Time (months) | Variance |
---|---|---|
1-2 | 4 | 2 |
1-3 | 6 | 2 |
2-4 | 5 | 9 |
3-4 | 7 | 7 |
2-5 | 9 | 10 |
4-6 | 10 | 1 |
5-6 | 8 | 0 |
(b) How resource leveling is different from resource allocation? 03
(c) Enlist the steps/rules involved in the resource smoothening/leveling process in project planning/scheduling. 04
A real estate villa project of 15 houses involves 7 operations (A, B, C, D, E, F, G) in series with duration and other resource requirements are as given below. Using Line of Balance (LOB) concept, schedule the project. Use a minimum buffer of 0.5 weeks between operations. 07
--- Content provided by FirstRanker.com ---
Operation | Duration for one house (Weeks) | Labor Required (Number of Gangs) |
---|---|---|
A | 2 | 1 |
B | 5 | 2 |
C | 4 | 1 |
D | 1 | 2 |
E | 6 | 4 |
F | 4 | 1 |
G | 2 | 2 |
OR
Q.5 (a) State the suitability of Line of Balance (LOB} method as a construction project scheduling tool. 03
(b) A 10 story building construction involves 4 operations (A, B, C, D) in series with duration and other resource requirements are as given below. Using Line of Balance (LOB) concept, schedule the project. 04
--- Content provided by FirstRanker.com ---
Operation | Duration (Weeks) | Labour Required (Number of Gangs) |
---|---|---|
A | 4 | 2 |
B | 3 | 3 |
C | 6 | 4 |
D | 2 | 2 |
(c) Calculate the normal, least-cost, and crash durations for the following project‘. Calculate the cost associated with each duration. Indirect (overhead) costs are Rs.120 per day. 07
Activity | IPA | Duration (Days) | Cost (Rs.) | ||
---|---|---|---|---|---|
Normal | Crash | Normal | Crash | ||
A | - | 5 | 4 | 500 | 600 |
B | A | 7 | 5 | 350 | 500 |
C | A | 8 | 5 | 800 | 920 |
D | A | 11 | 7 | 1200 | 1400 |
E | C | 6 | 4 | 600 | 700 |
F | C | 4 | 4 | 500 | 500 |
G | D,F | 7 | 5 | 700 | 1000 |
H | E,F | 6 | 5 | 300 | 420 |
Normal Distribution Function
Normal Deviate (-) | Probability (%) | Normal Deviate (+) | Probability (%) |
---|---|---|---|
0 | 50.0 | 0 | 50.0 |
-0.1 | 46.0 | + 0.1 | 54.0 |
-0.2 | 42.1 | + 0.2 | 57.9 |
-0.3 | 38.2 | + 0.3 | 61.8 |
-0.4 | 34.5 | + 0.4 | 65.5 |
-0.5 | 30.8 | + 0.5 | 69.2 |
-0.6 | 27.4 | + 0.6 | 72.6 |
-0.7 | 24.2 | + 0.7 | 75.5 |
-0.8 | 21.2 | + 0.8 | 78.8 |
-0.9 | 18.4 | + 0.9 | 81.6 |
-1.0 | 15.9 | + 1.0 | 84.1 |
-1.1 | 13.6 | + 1.1 | 86.4 |
-1.2 | 11.5 | + 1.2 | 88.5 |
-1.3 | 9.7 | + 1.3 | 90.3 |
-1.4 | 8.1 | + 1.4 | 91.3 |
-1.5 | 6.7 | + 1.5 | 93.3 |
-1.6 | 5.5 | + 1.6 | 94.5 |
-1.7 | 4.5 | + 1.7 | 95.5 |
-1.8 | 3.6 | + 1.8 | 96.4 |
-1.9 | 2.9 | + 1.9 | 97.1 |
-2.0 | 2.3 | + 2.0 | 97.7 |
-2.1 | 1.8 | + 2.1 | 98.2 |
-2.2 | 1.4 | + 2.2 | 98.6 |
-2.3 | 1.1 | + 2.3 | 98.9 |
-2.4 | 0.8 | + 2.4 | 99.2 |
-2.5 | 0.6 | + 2.5 | 99.4 |
-2.6 | 0.5 | + 2.6 | 99.5 |
-2.7 | 0.3 | + 2.7 | 99.7 |
-2.8 | 0.3 | + 2.8 | 99.7 |
-2.9 | 0.2 | + 2.9 | 99.8 |
-3.0 | 0.1 | + 3.0 | 99.9 |