FirstRanker Logo

FirstRanker.com - FirstRanker's Choice is a hub of Question Papers & Study Materials for B-Tech, B.E, M-Tech, MCA, M.Sc, MBBS, BDS, MBA, B.Sc, Degree, B.Sc Nursing, B-Pharmacy, D-Pharmacy, MD, Medical, Dental, Engineering students. All services of FirstRanker.com are FREE

Get the MBBS Question Bank Android App

Access previous years' papers, solved question papers, notes, and more on the go!

Install From Play Store

Get the Nursing Question Bank Android App

Access 10+ years of Question Papers with answers, notes for B.Sc Nursing on the go!

Install From Play Store

Download GTU BE/B.Tech 2018 Winter 7th Sem Old 172903 Production Planning And Maintenance Question Paper

Download GTU (Gujarat Technological University) BE/BTech (Bachelor of Engineering / Bachelor of Technology) 2018 Winter 7th Sem Old 172903 Production Planning And Maintenance Previous Question Paper

This post was last modified on 20 February 2020

GTU BE/B.Tech 2018 Winter Question Papers || Gujarat Technological University


FirstRanker.com

Subject Name: Production Planning & Maintenance

Time: 10:30 AM TO 01:00 PM

--- Content provided by⁠ FirstRanker.com ---

Instructions:

  1. Attempt all questions.
  2. Make suitable assumptions wherever necessary.
  3. Figures to the right indicate full marks.

Q.1

--- Content provided by⁠ FirstRanker.com ---

In a weaving unit 40 projectile looms are running with following quality of fabrics.

Fabric Details:

R.S.: 56” Reed count: 80s

Length contraction: 5% Warp/Weft: 2/80sNe / 50s Ne

Ends/dent: 2 GSM: 160

--- Content provided by‍ FirstRanker.com ---

Loom RPM: 320 Loom Effi.(%) : 89

Loom width: 130”

Calculate how many warp beams will be required per week for the above shed if maximum length of yarn on a beam is 3000 m (ignore selvedge during calculation) [09]

Calculate the time after which all cans will be exhausted on draw frame from following data. [05]

Doublings: 8 DF Speed: 450 mpm

--- Content provided by​ FirstRanker.com ---

DF Efficiency: 85% Count of sliver: 4.1 ktex

Wt. of sliver in one can: 27.8 Ibs Draft: 8

A fabric is to be produced having 40 inch Reed Space. The fabric has a weft way stripe of 50 threads per repeat comprising of 10 dark threads and 40 white threads. Find out requirement of dark and white weft yarn per 100 linear m of fabric. The PPI-are 60.Count of the weft yarn is 2/80s Ne. [07]

Calculate how many times warping creel needs to be changed from following data. [07]

Maximum length on warper’s beam : 20000 yds

--- Content provided by‌ FirstRanker.com ---

Length of yarn on weaver’s beam : 2000 yds

No. of ends'in weaver’s beam : 5328

No. of weaver’s beams required : 20

Count of yarn : 50s Ne

No. of threads in warping creel : 592

--- Content provided by FirstRanker.com ---

Wt. of yarn on package : 1.75 kg

OR

A mill wants to produce 8000 m of a particular fabric every day. Calculate number of bobbins required from winding and pirn winding departments from following details. [07]

R.S.:45” EPI: 80 Weight of fabric: 175 gsm

Count : 40s / 34s Ne

--- Content provided by​ FirstRanker.com ---

Length of yarn on wound bobbin : 70000 m

Winding speed/eff. : 1100 mpm / 85%

Pirn winding speed/eff. : 500 ypm / 75%

Length contraction : 6%

Weight of yarn on pirn : 1.2 ozs

--- Content provided by FirstRanker.com ---

FirstRanker.com

GUJARAT TECHNOLOGICAL UNIVERSITY

BE - SEMESTER-VII (OLD) EXAMINATION - WINTER 2018

Subject Code: 172903 Date: 19/11/2018

Total Marks: 70

--- Content provided by FirstRanker.com ---

Q.3

Loom no. Pick Counter Reading RPM PPI

Start End

1 10312 31696 98 90

2 09834 32514 210 80

--- Content provided by⁠ FirstRanker.com ---

3 18979 42739 220 52

Write all maintenance check points for winding and ordinary plain power loom. [07]

OR

Weaving department has following types of looms and the fabric varieties to be produced on particular loom. Calculate total requirement of yarn.(Assume 6 % contraction for each fabric) [10]

Loom details:

--- Content provided by FirstRanker.com ---

Type of loom Max. R.S. RPM Eff. % No. of looms

1. Air jet 190 cm 650 90 24

2. Rapier 220 cm 500 90 24

3. Autoloom 56” 200 90 48

Fabric Details & Requirement:

--- Content provided by​ FirstRanker.com ---

No. EPI/PPI R.S” Wp/ Wt Req.(m) To be woven on

1 80/52 42 34/34 35000 Autoloom

2 120/ 96 56 2/80/50 30000 Air jet

3 80/ 80 50 2/60/2/60 28000 Rapier

Q4

--- Content provided by‍ FirstRanker.com ---

Derive equation to work out length of yarn per weft bobbin, length of cloth produced per weft bobbin and no. of weft bobbins per loom per hour. [04]

What is the effect of change in PPI on number of weft bobbins required per hour? [04]

Write atleast five maintenance check points for carding machine [04]

An OE Spinning Plant has following requirement for a month (30 working days at 24 hrs per day) [10]

Count Requirement Rotor speed rpm eff.%

--- Content provided by‍ FirstRanker.com ---

9s 22,000 kgs 75000 95

Calculate no. of OE spindles required to produce above counts. Also calculate no. of cards required from following data.

Doffer dia:27” Doffer rpm: 35 Tension draft: 1.01

Count of sliver: 4.91 ktex Efficiency of Card : 85%

OR

--- Content provided by‍ FirstRanker.com ---

A texturising plant has following requirement per day: [07]

Count(Denier) Required Production in kg

75/36 1200

75/36/400 0800

Calculate no. of spindles required of SDS 600(94%efficiency) and of TFO (running at 13000 rpm and 91 % efficiency).

--- Content provided by‌ FirstRanker.com ---

There is a requirement of 300 kgs/day of 40s 100% cotton and 600 kgs/day of 54s PC blended (67:33)material. How many comber shifts required to cater requirement of material. Nips/min is 250 and feed/nip is 5 mm. Other data is as given below: [07]

Comber type Count lap wt.g/m noil % eff. %

Bicoiler 8 head 54s pc 68 15 90

FirstRanker.com

Q.5 (a) Ring frame department of a spinning unit supplies following yarns (from same mixing) to a weaving unit per day: [10]

--- Content provided by⁠ FirstRanker.com ---

Count Fibres Production in kg

32sK 100 % 500

40s C Cotton 600

Work out number of blow room laps required per hour from following data.

Lap roller speed: 5 mpm efficiency : 85%

--- Content provided by⁠ FirstRanker.com ---

Count of lap : 490 g/m lap length : 40 yds

(assume waste% at all stages)

(b) Calculate the production of a ring frame from following data: [04]

Count : 42sNe

Spindles: 1008 Spindle speed/eff.% : 21000/85%

--- Content provided by​ FirstRanker.com ---

OR

Q.5 (a) Calculate weight of doff, time after which doff is to be taken and time after which roving bobbin will be exhausted on ring frame from following data. [07]

Speed of RF: 15000 rpm Eff.: 87% Count of yarn: 42sNe

T™: 4.0 Wt. of roving bobbin: 3.5 lbs

Waste at RF: 2.5 % Count of roving: 0.59 ktex

--- Content provided by⁠ FirstRanker.com ---

No. of spindles: 880 Length of yarn on ring bobbin: 4200 m

(b) Calculate time after which the lap will be exhausted on card from following data. [07]

Lap weight: 490 ktex Lap length: 40 yd Doffer dia.: 277

Doffer rpm: 30 Efficiency: 86 % Tension draft: 1.01

Draft at card: 100

--- Content provided by‌ FirstRanker.com ---