Subject Code: 2182506
GUJARAT TECHNOLOGICAL UNIVERSITY
--- Content provided by FirstRanker.com ---
BE - SEMESTER-VIII (NEW) EXAMINATION — WINTER 2018
Subject Name: Managing Projects
Date: 19/11/2018
Time: 02:30 PM TO 05:00 PM
Total Marks: 70
--- Content provided by FirstRanker.com ---
Instructions:
- Attempt all questions.
- Make suitable assumptions wherever necessary.
- Figures to the right indicate full marks.
- (a) Define Scope, Schedule and Cost in reference to project. (03 Marks)
--- Content provided by FirstRanker.com ---
(b) Describe the difference between AOA and AON project network. (04 Marks)
(c) Find the Project duration, EST, EFT, LST, LFT and total slack for each activity. Draw AOA network diagram. (07 Marks)
Activity A B C D E F G
Predecessor - - A B B C,D EF
Time (weeks) 1 10 6 5 4 3 2 - (a) Draw the AOA network for the following project. (03 Marks)
Activity A B C D E F G
Predecessor - - A B B C,D EF
(b) Differentiate between General Management and Project Management. (04 Marks)
(c) Discuss project-type organization structure for project. How it is different from matrix organization structure? (07 Marks)--- Content provided by FirstRanker.com ---
OR
What is a Work Breakdown Structure. (WBS)? What is a Responsibility Matrix? How are they related? - (a) Give name of any 10 resources used in a project (03 Marks)
(b) What is Project termination? Explain. (04 Marks)
(c) Describe Project Charter in Detail. (07 Marks)--- Content provided by FirstRanker.com ---
OR
What are some sources of conflict the project manager must deal with? - (a) Briefly explain project scope creep. (03 Marks)
(b) What are some essential skills for an effective project manager? How can these skills be developed? (04 Marks)
(c) List any five projects declared by Government of India after 2015. (07 Marks) - (a) What is Cost Variance? Explain. (03 Marks)
(b) Discuss Earned Value Analysis with suitable example. (04 Marks)
(c) What is an activity slope and what does it indicate? (07 Marks)
OR
(a) What is shown on RACI matrix? How is it useful to a PM? (03 Marks)--- Content provided by FirstRanker.com ---
(b) What is time-cost trade off in project schedule? (04 Marks)
(c) What is resource loading? How does it differ from resource leveling? (07 Marks)
--- Content provided by FirstRanker.com ---
--- Content provided by FirstRanker.com ---
- OR
(a) Identify the four reasons for project termination. (03 Marks)
(b) Describe the project budgeting process (04 Marks)--- Content provided by FirstRanker.com ---
(c) In preparing a budget, what indirect costs should be considered? (07 Marks) - (a) List four stages of Project Team building process. Explain any one of them. (03 Marks)
(b) Discuss the critical chain project management. (04 Marks)
--- Content provided by FirstRanker.com ---
This download link is referred from the post: GTU BE/B.Tech 2018 Winter Question Papers || Gujarat Technological University
--- Content provided by FirstRanker.com ---