FirstRanker Logo

FirstRanker.com - FirstRanker's Choice is a hub of Question Papers & Study Materials for B-Tech, B.E, M-Tech, MCA, M.Sc, MBBS, BDS, MBA, B.Sc, Degree, B.Sc Nursing, B-Pharmacy, D-Pharmacy, MD, Medical, Dental, Engineering students. All services of FirstRanker.com are FREE

📱

Get the MBBS Question Bank Android App

Access previous years' papers, solved question papers, notes, and more on the go!

Install From Play Store

Download GTU BE/B.Tech 2018 Winter 8th Sem Old 182506 Managing Projects Question Paper

Download GTU (Gujarat Technological University) BE/BTech (Bachelor of Engineering / Bachelor of Technology) 2018 Winter 8th Sem Old 182506 Managing Projects Previous Question Paper

This post was last modified on 20 February 2020

GTU BE/B.Tech 2018 Winter Question Papers || Gujarat Technological University


FirstRanker.com

Time: 02:30 PM TO 05:00 PM

Date: 29/11/2018

--- Content provided by‍ FirstRanker.com ---

Total Marks: 70

Instructions:

  1. Attempt all questions.
  2. Make suitable assumptions wherever necessary.
  3. Figures to the right indicate full marks.
  4. --- Content provided by​ FirstRanker.com ---

GUJARAT TECHNOLOGICAL UNIVERSITY
BE - SEMESTER-VIII (OLD) EXAMINATION - WINTER 2018
Subject Code: 182506
Subject Name: Managing Projects

Q.1 Draw AOA network. Calculate EST, EFT, LST, LFT and total float for each activity. Also find the critical path and project duration. 10

--- Content provided by​ FirstRanker.com ---

Activity | Precedence | Normal activity Duration
A | - | 5
B | A | 6
C | A | 4
D | C | 5

--- Content provided by‍ FirstRanker.com ---

E | B,C | 3

(b) Differentiate between PERT and CPM. 04

Q2 (a) What is RACI matrix? Discuss its usefulness to project manager. 07

(b) Discuss EVA for project control. 07

Q3 (a) Discuss matrix organization structure for project. How it is different from project type organization structure? 07

--- Content provided by‍ FirstRanker.com ---

(b) “Project control should always focus on critical path.” Comment. 07

OR

Q3 (a) Discuss Time-Cost Tradeoff for scheduling of the project. 07

(b) Consider a project as follows. Draw-AOA network, determine expected project duration. What is the probability that the project will be completed in expected project duration? 07

OR

--- Content provided by‍ FirstRanker.com ---

Q4 (a) List of activities for erecting a canteen in a factory is given below. Draw the AOA network and identify critical path. 07

Activity | A | B | C | D | E | F | G | H
Immediate Predecessor | - | A | A | C | B,C | B,C | C | D,E
Optimistic Time | 2 | 5 | 1 | 1 | 6 | 3 | 1 | 4
Most Likely Time | 2 | 25 | 15 | 25 | 7 | 4 | 2 | 6

--- Content provided by‌ FirstRanker.com ---

Pessimistic | 8 | 75 | 11 | 7 | 8 | 11 | 3 | 8

(b) What are some potential problems with top-down and bottom-up budgeting processes? What are some ways of dealing with these potential problems? 07

Q5 (a) Discuss Critical Chain Project Management (CCPM) 07

(b) Discuss Work Breakdown Structure (WBS) with an example. 07

OR

--- Content provided by‍ FirstRanker.com ---

Q5 (a) What is resource loading? How does it differ from resource leveling? 07

(b) Differentiate between general management and project management. 07

OR

Q5 (a) Discuss various skills to be considered in the selection of a project manager. 07

(b) Discuss the trade-off among the three prime objectives of project management. 07

--- Content provided by​ FirstRanker.com ---

OR

Q5 (a) List and briefly describe the ways projects may be terminated. 07

(b) What is Project? Discuss Project Life Cycle in detail. 07


--- Content provided by⁠ FirstRanker.com ---


This download link is referred from the post: GTU BE/B.Tech 2018 Winter Question Papers || Gujarat Technological University