Subject Code:132905 Date:29/11/2017Subject Name: Basic Engineering in Textile
Time: 10:30 AM to 01:00 PM Total Marks: 70
Instructions:
1. Attempt all questions.
--- Content provided by FirstRanker.com ---
2. Make suitable assumptions wherever necessary.3. Figures to the right indicate full marks.
Q.1 (a) What is coal fired boiler? Explain the working of any one fire tube boiler with neat sketch. 07
(b) Explain humidification by air washer method with neat sketch. 07
Q.2 (a) Explain importance of preventive maintenance vs. breakdown maintenance. 07
--- Content provided by FirstRanker.com ---
(b) A company produces 2 types of hats A and B. every hat A requires twice as much labor time as the second hat B. if company produces only hat B then it can produce a total of 500 hats per day. The market limits daily sales of hat A and B to 150 and 250 respectively. The profits on hat A and B Rs.8 and Rs. 5 respectively. Solve graphically to get the optimal solution of LPP. 07OR
(b) 1. Explain the basic procedure for work-study-and its definition. 07
2. Define work measurement technique.
3. Define standard time, normal time-and definition of rating.
--- Content provided by FirstRanker.com ---
Q.3 (a) A company has four plants.each of which can manufacture any one of four products. Product differ.from one plant to another as follows: 07
Plant | P | Q | R | S |
---|---|---|---|---|
1 | 33 | 40 | 43 | 32 |
2 | 45 | 28 | 30 | 23 |
3 | 42 | 29 | 35 | 29 |
4 | 27 | 42 | 45 | 38 |
Find out which product each plant should produce to minimize cost.
(b) Write short note on SIMO chart. 07
OR
--- Content provided by FirstRanker.com ---
Maximize Z = 15X1+6X+9X3+2X4
Subject to, 2X1+X2 +5X3+6X4 < 20
3X1+X2 +3X3+25X4 < 24
7X1+4X4 < 70
X1≥0, X2≥0, X3≥0, X4≥0
--- Content provided by FirstRanker.com ---
(b) How is the job selected for method study? 07
Q.4 (a) Explain the various steps involved in time study. 07
(b) Discuss the merits and demerits of water tube boiler and fire tube boiler. 07
OR
--- Content provided by FirstRanker.com ---
Q.4 (a) A small project involves 7 activities, and their time estimates are listed in the following table. Activities are identified by their beginning and ending node number. 07
Activity (i-j) | Optimistic | Most likely | Pessimistic |
---|---|---|---|
1-2 | 1 | 1 | 7 |
1-3 | 1 | 4 | 7 |
1-4 | 2 | 2 | 8 |
2-5 | 1 | 1 | 1 |
3-5 | 2 | 5 | 14 |
4-6 | 2 | 5 | 8 |
5-6 | 3 | 6 | 15 |
1. Draw the network Diagram of the activities in the project.
2. Find expected duration and variance for each activity. What is expected project length?
3. What is probability that project will be completed at least 4 weeks earlier than expected time?
(b) Explain any one feed water treatment method with neat sketch. 07
--- Content provided by FirstRanker.com ---
Q.5 (a) Solve the following transportation problem starting with the initial solution obtained by VAM. 07
D1 | D2 | D3 | D4 | Supply | |
---|---|---|---|---|---|
O1 | 2 | 11 | 10 | 3 | 7 |
O2 | 1 | 0 | 8 | 5 | 4 |
O3 | 7 | 6 | 6 | 8 | 5 |
Demand | 4 | 3 | 4 | 4 | 15 |
(b) 1. Explain humidification and dehumidification. 07
2. Define: RH, WBT,DPT.
OR
--- Content provided by FirstRanker.com ---
Q.5 (a) A project consist of a series of tasks labeled A, B.....H, | with the following constraints, A<D, E; B,D<F,C<G;B<H;F,G<I; W< X, Y means X and Y cannot start until W is completed. You are required to construct a network using this network using the notation. Also find the minimum time of completion of the project when the time of completion of each task is given as follows: 07
Task | A | B | C | D | E | F | G | H | I |
---|---|---|---|---|---|---|---|---|---|
Time(Days) | 23 | 8 | 20 | 16 | 24 | 18 | 19 | 4 | 10 |
(b) Define and distinguish the earliest and the latest start time and the earliest and the latest finish time. Explain optimistic time, pessimistic time, most likely time in relation to PERT. 07