Code No: 741AG
JAWAHARLAL NEHRU TECHNOLOGICAL UNIVERSITY HYDERABAD
MBA I Semester Examinations, June/July-2018
PROJECT MANAGEMENT
Time: 3hours Max.Marks:75

Note: This question paper contains two parts A and B.
Part A is compulsory which carries 25 marks. Answer all questions in Part A. Part B
consists of 5 Units. Answer any one full question from each unit. Each question carries
10 marks and may have a, b, c as sub questions.

PART - A 5 ? 5 Marks = 25

1. Answer briefly on:
a) Systems approach to project management. [5]
b) Project Planning [5]
c) Profitability Index [5]
d) Scrum [5]
e) Stress Management [5]


PART ? B 5 ?10 Marks = 50

2. What is Project Management? Explain the need and importance of project management
in Construction field. [10]
OR
3. Explain different steps involved in a Project Life Cycle. [10]

4. Explain about Social cost benefit analysis in Project planning and appraisal. [10]
OR
5. Explain about financial, technical, commercial and economic aspects involved in project
appraisal. [10]

6. What is Project Evaluation? Explain the techniques for Project Evaluation? [10]
OR
7. From the information given below select any one project for investment according to
Net Present Value Method at 10 percent cost of Capital. [10]

Year Project A
(Amount in Rs.)
Project B
(Amount in Rs.)
0 15,00,000 32,00,000
1 5,00,000 10,00,000
2 8,00,000 10,00,000
3 9,00,000 9,00,000
4 10,00,000 9,00,000
5 6,00,000 8,00,000

R17
www.FirstRanker.com www.FirstRanker.com
www.FirstRanker.com
FirstRanker.com - FirstRanker's Choice
www.FirstRanker.com

Code No: 741AG
JAWAHARLAL NEHRU TECHNOLOGICAL UNIVERSITY HYDERABAD
MBA I Semester Examinations, June/July-2018
PROJECT MANAGEMENT
Time: 3hours Max.Marks:75

Note: This question paper contains two parts A and B.
Part A is compulsory which carries 25 marks. Answer all questions in Part A. Part B
consists of 5 Units. Answer any one full question from each unit. Each question carries
10 marks and may have a, b, c as sub questions.

PART - A 5 ? 5 Marks = 25

1. Answer briefly on:
a) Systems approach to project management. [5]
b) Project Planning [5]
c) Profitability Index [5]
d) Scrum [5]
e) Stress Management [5]


PART ? B 5 ?10 Marks = 50

2. What is Project Management? Explain the need and importance of project management
in Construction field. [10]
OR
3. Explain different steps involved in a Project Life Cycle. [10]

4. Explain about Social cost benefit analysis in Project planning and appraisal. [10]
OR
5. Explain about financial, technical, commercial and economic aspects involved in project
appraisal. [10]

6. What is Project Evaluation? Explain the techniques for Project Evaluation? [10]
OR
7. From the information given below select any one project for investment according to
Net Present Value Method at 10 percent cost of Capital. [10]

Year Project A
(Amount in Rs.)
Project B
(Amount in Rs.)
0 15,00,000 32,00,000
1 5,00,000 10,00,000
2 8,00,000 10,00,000
3 9,00,000 9,00,000
4 10,00,000 9,00,000
5 6,00,000 8,00,000

R17
www.FirstRanker.com www.FirstRanker.com
www.FirstRanker.com
www.FirstRanker.com



8.a) Explain the steps involved in Project Planning and Control?
b) Explain the concept of Quality Management with reference to a project. [5+5]
OR
9. From the information given in the table draw network diagram, calculate critical path
and duration of the project. [10]













10. What is organizational structure? Which organizational structure is suitable for a project
and why? [10]
OR
11. Explain the need and importance of leadership in successful execution and completion
of a project. [10]


--ooOoo ?



















Activity Predecessor
Activity
Most Likely
A - 6
B A 7
C A 8
D B 20
E B 18
F C 9
G E 8
H D,F 2
I G,H 7