Download JNTU-Hyderabad MBA 3rd Sem R17 2018 Dec 743AA Production And Operations Management Question Paper

Download JNTUH (Jawaharlal Nehru Technological University Hyderabad) MBA (Master of Business Administration) 3rd Semester (Third Semester) R17 2018 Dec 743AA Production And Operations Management Previous Question Paper



Code No: 743AA
JAWAHARLAL NEHRU TECHNOLOGICAL UNIVERSITY HYDERABAD
MBA III Semester Examinations, December - 2018
PRODUCTION AND OPERATIONS MANAGEMENT
Time: 3hours Max.Marks:75

Note: This question paper contains two parts A and B.
Part A is compulsory which carries 25 marks. Answer all questions in Part A. Part B
consists of 5 Units. Answer any one full question from each unit. Each estion carries
10 marks and may have a, b, c as sub questions.

PART - A 5 ? 5 Marks = 25

1.a) Conceptualizing production system as a transformation process, explain atleast two
each of manufacturing and services with inputs and outputs. [5]
b) What are the attributes of a product? [5]
c) What do you understand by cellular layout? What are its merits? [5]
d) What are the disadvantages of Gantt chart as a scheduling tool? [5]
e) What do you understand by selective inventory control techniques? Explain atleast
one of them. [5]

PART - B 5 ? 10 Marks = 50

2.a) ?Production function, though is a vital function in an organization, it remains
essentially a behind the scene non glamorous function?. Comment on the statement.
b) What are generic strategies? [5+5]
OR
3.a) What is system concept of production/operation?
b) What is total productivity? What is partial productivity? Explain the difference. [5+5]

4.a) What is ergonomics? What is its relevance to production management?
b) What is value engineering? How does it differ from cost reduction? [5+5]
OR
5.a) What is standardization? What are its advantages in manufacturing?
b) What is process planning design? [5+5]

6. XYZ company is considering an additional facility. The company is heavily dependent
on water transportation. Therefore it has narrowed its choice of location to three port
facilities in Mumbai, Karwar and Machilipatnam. On the basis of the following data,
which location is preferable?

Relevant factors Mumbai Karwar Machilipatnam
Variable cost per
unit
Rs. 18 Rs. 20 Rs. 19.50
Fixed cost per year Rs. 15 lakhs Rs. 30 lakhs Rs. 40 lakhs
Price per unit Rs. 300 Rs. 300 Rs. 300
Volume(unit/year) 3 lakhs 2.5 lakhs 3.25 lakhs
[10]
OR

R17

FirstRanker.com - FirstRanker's Choice


Code No: 743AA
JAWAHARLAL NEHRU TECHNOLOGICAL UNIVERSITY HYDERABAD
MBA III Semester Examinations, December - 2018
PRODUCTION AND OPERATIONS MANAGEMENT
Time: 3hours Max.Marks:75

Note: This question paper contains two parts A and B.
Part A is compulsory which carries 25 marks. Answer all questions in Part A. Part B
consists of 5 Units. Answer any one full question from each unit. Each estion carries
10 marks and may have a, b, c as sub questions.

PART - A 5 ? 5 Marks = 25

1.a) Conceptualizing production system as a transformation process, explain atleast two
each of manufacturing and services with inputs and outputs. [5]
b) What are the attributes of a product? [5]
c) What do you understand by cellular layout? What are its merits? [5]
d) What are the disadvantages of Gantt chart as a scheduling tool? [5]
e) What do you understand by selective inventory control techniques? Explain atleast
one of them. [5]

PART - B 5 ? 10 Marks = 50

2.a) ?Production function, though is a vital function in an organization, it remains
essentially a behind the scene non glamorous function?. Comment on the statement.
b) What are generic strategies? [5+5]
OR
3.a) What is system concept of production/operation?
b) What is total productivity? What is partial productivity? Explain the difference. [5+5]

4.a) What is ergonomics? What is its relevance to production management?
b) What is value engineering? How does it differ from cost reduction? [5+5]
OR
5.a) What is standardization? What are its advantages in manufacturing?
b) What is process planning design? [5+5]

6. XYZ company is considering an additional facility. The company is heavily dependent
on water transportation. Therefore it has narrowed its choice of location to three port
facilities in Mumbai, Karwar and Machilipatnam. On the basis of the following data,
which location is preferable?

Relevant factors Mumbai Karwar Machilipatnam
Variable cost per
unit
Rs. 18 Rs. 20 Rs. 19.50
Fixed cost per year Rs. 15 lakhs Rs. 30 lakhs Rs. 40 lakhs
Price per unit Rs. 300 Rs. 300 Rs. 300
Volume(unit/year) 3 lakhs 2.5 lakhs 3.25 lakhs
[10]
OR

R17



7.a) Bring out the reasons with examples for layout revision.
b) What are the factors influencing plant layout? [5+5]

8. Consider the following three machines and five jobs flow shop problem. Check if
Johnson?s rule can be extended to this problem. If so, what is the optimal schedule and
the corresponding makes pan? [10]

Job Machine 1 Machine 2 Machine 3
1 11 10 12
2 13` 8 20
3 15 6 15
4 12 7 19
5 20 9 7
OR
9.a) What are the set of priority rules for scheduling ?m? jobs through single machine?
Explain briefly each of them.
b) What is quality control? What are its objectives and benefits? [5+5]

10.a) For a given item of constant demand rate, the yearly demand is 6025 units. The price
of the item per unit is Rs.60. The ordering cost is Rs. 300 per order. What should be
the optimum inventory policy?
b) Explain ABC analysis technique of inventory management? [5+5]
OR
11.a) A firm has a demand distribution of demand during a constant lead time with a
standard deviation of 400 units. The firm wants to provide 95 percent service.
i) What is the safety stock that needs to be provided?
ii) If the demand during lead time averages 1500 units, what is the appropriate order
level?
b) What are the functions of storekeeping? [6+4]