Download AKTU B-Tech 5th Sem 2018-2019 RCE 503 Quantity Estimation And Management Question Paper

Download AKTU (Dr. A.P.J. Abdul Kalam Technical University (AKTU), formerly Uttar Pradesh Technical University (UPTU) B-Tech 5th Semester (Fifth Semester) 2018-2019 RCE 503 Quantity Estimation And Management Question Paper

This post was last modified on 29 January 2020

AKTU B-Tech Last 10 Years 2010-2020 Previous Question Papers || Dr. A.P.J. Abdul Kalam Technical University


FirstRanker.com

Printed Pages: 03

Paper Id: 100503

--- Content provided by‌ FirstRanker.com ---

Roll No:

Subject Code: RCE503

BTECH

(SEM V) THEORY EXAMINATION 2018-19

QUANTITY ESTIMATION AND MANAGEMENT

--- Content provided by FirstRanker.com ---

Time: 3 Hours Total Marks: 100

Notes: Assume any Missing Data.

SECTION A

2X7=14

  1. Attempt all questions in brief:
    1. What is the use of a dummy in a network?
    2. --- Content provided by‍ FirstRanker.com ---

    3. What do you mean by cash flow diagram?
    4. Define interest rate. How interest rate can be classified?
    5. What is centre line method?
    6. What is Arbitration?
    7. What are the characteristics of a good programme?
    8. --- Content provided by‌ FirstRanker.com ---

    9. Define contract.

SECTION B

7X 3=21

  1. Attempt any three of the following:
    1. What are the limitations of PERT network?
    2. --- Content provided by‍ FirstRanker.com ---

    3. Discuss the concept of time value of money?
    4. Enumerate the factors which affect the output of a dragline.
    5. Define salvage value, scrap value and book value.
    6. Discuss the time cost analysis.
  2. --- Content provided by‌ FirstRanker.com ---

SECTION C

7x1=7

  1. Attempt any one part of the following:
    1. Find the critical path ad project duration of the given CPM project. Also calculate EST, EFT, LST, LFT and all the floats in a tabular form.
    2. For the given PERT network, determine:
      1. Expected time, standard deviation and variance of the project and show the critical path also.
      2. Probability of completion of project in 35days.
      3. --- Content provided by⁠ FirstRanker.com ---

      4. Time duration that will provide 90% probability (z is 1.32) of its completion in time. (If z is 1, P is 84.13%), (if z is 0.9, P is 81.59%), (if z is 1.1, P is 86.43%)
      2-5-8
      4-9-20
      4-7-16
      8-11-20

      --- Content provided by‌ FirstRanker.com ---

      3-7-17
      7-10-13
      2-3-10
      3-5-13
      2-4-6
    3. --- Content provided by⁠ FirstRanker.com ---

  1. Attempt any one part of the following: 7x1=7
    1. Write short notes on: clamshell, Hoe, scraper and bulldozer.
    2. Explain in detail factors affecting the economic life of an equipment.
  1. Attempt any one part of the following: 7x1=7
    1. Alpha Industry is planning to expand its production. It has identified three different technologies for meeting the goal. The initial outlay and annual revenue with respect to each of the technologies are summarized in tale. Suggest the best technology which is to e implemented on the present worth method of comparison assuming 20% I.R., compounded annually.
      Technology Initial outlay (Rs.) Annual Revenue (Rs.) Life (years)
      Technology 1 12,00,000 4,00,000 10
      Technology 2 20,00,000 6,00,000 10
      Technology 3 18,00,000 5,00,000 10
    2. --- Content provided by​ FirstRanker.com ---

    3. What is depreciation? Also discuss the methods to calculate the depreciation.
  1. Attempt any one part of the following: 7x1=7
    1. Write short notes on: Tender, Earnest money deposit and Commissioning of project.
    2. What are the elements of tender preparation?
  2. --- Content provided by⁠ FirstRanker.com ---

  1. Attempt any one part of the following: 7x1=7
    1. Discuss the methods of estimating.
    2. Estimate the quantities of the following items of a two roomed building from the given plan and section:
      1. Earthwork in excavation in foundation
      2. Lime concrete in foundation
      3. 1st class brickwork in cement mortar 1:6 in foundation and plinth
      4. 2.5cm c.c. D.P.C.
      5. --- Content provided by FirstRanker.com ---

      6. 1st class brickwork in lime mortar in superstructure.
      All walls are of same section, lintels over doors, windows and shelves are 15 cm thick.
      Doors D- 1.20 m X 2.10 m
      Windows W 1.00 m X 1.50 m
      Shelves S 1.00 m X 1.50 m

      --- Content provided by‌ FirstRanker.com ---

      Room 4mx6m Room 6m x 6m

      6 m
      6m
      D

      --- Content provided by​ FirstRanker.com ---

      D
      Plan

      20 cm
      Section