Printed Paes: 02 Sub Code: NCE603
Paperld: llllmli RouNo.| | | | | | | | | | |
B. TECH
(SEM-VI) THEORY EXAMINATION 2017-18
CONSTRUCTION TECHNOLOGY & MANAGEMENT
T ime: 3 Hours T otal Marks: 100
Note: Attempt all Sections. If require any missing data; then choose suitably.
SECTION A
1. Attempt all questions in brief. 2 x 10 = 20
a) What do you mean by project cycle?
b) Write a short note on ?construction team?.
c) What is Bar chart?
(1) Define Dummy activity
e) What do you mean by depreciation?
i) What is break-even cost analysis?
g) Write a note on project contract?
h) What is land acquisition?
i) what is operational cost?
j) What are the various types of crane?
SECTION B
2. Attempt any three of the following: 10 x 3 = 30
a) What is ?job Layout"? Explain factors affecting ?Job Layout?.
b) What do you mean by CPM and PERT? Illustrate with examples the difference between
CPM and PERT.
c) What are the advantages and disadvantages of debt financing?
(1) Write note on the following:
1. Tender
II. Earnest money deposit
III. Settlement of dispute
IV. Commissioning of project
e) What are the various types of hauling equipment vehicles? Also write in detail their
relative advantages and disadvantages.
SECTION C
3. Attempt any one part of the following: 10 x 1 = 10
a) What are the advantages and disadvantages of:
1. Line organization
11. Line and staff organization
b) Explain various type of construction in detaili

4.
Attempt any one part of the following: 10 x 1 = 10
a) A project consists of eight events predecessor relationship as under. construct the
network.
EVENT 1 2 3 4 5 6
IMMEDIATE PREDECCESSOR -- 1 1 2,3 3,4 3,5 6 4,7
\]
00
b) Define the following:
1. Direct cost and indirect cost
11. Crash time and crash cost
111. Cost slop
IV. Optimum time and optimum cost
Attempt any one part of the following: 10 x 1 = 10
a) The ?xed cost for the year 2013-14 are 60000 Rs. The estimated sales for the period are
valued at 200000 Rs. The variable cost per unit for the single product made is 5 Rs. If
each unit sells at 25 Rs and the no, of units involved coincide with the expected volume
of output. Construct break- even chart and determine the following:
I. The break-even point
11. Margin of safety
b) What do you mean by cash ?ow diagram? How it is classified?
Attempt any one part of the following: 10 x 1 = 10
a) What are the plans for labour safety on construction site?
b) Describe importance of construction contracts for the successful completion of the civil
engineering projects,
Attempt any one part of the following: 10 x 1 = 10
a) Estimate the number of dump trucks required for transportation of 1500 cum of material
per day for average load of 5 Km with the following data:
Capacity of one dump truck = 20 cum
Speed during empty haul @ 30kIn/hr and loaded haul 25 km/hr
Loading time of one dump truck = 15 minutes
b) explain a central batching and mixing plant for a very large construction project.