Paper ID: 2012361 Roll No. NOE-077
B. TECH.
Regular Theory Examination (Odd Sem-VII), 2016-17
SOFTWARE PROJECT MANAGEMENT
--- Content provided by FirstRanker.com ---
Time: 3 Hours Max. Marks: 100
SECTION-A
Attempt all parts. All parts carry equal marks. Write answer of each part in short. (10×2=20)
- What are the characteristics that make Software Projects different from other projects?
- How do you define project activities in Software Project Management?
- What is the requirement of having stepwise project planning?
- How does the Milestone chart helps in Scheduling?
- What do you mean by Code Review? Why is it needed in project?
- Differentiate between Schedule Performance Index(SPI) and Cost Performance Index(CPI)
- What is the role of stake holders in Software Project?
- Distinguish between verification and validation of Software Products.
- What is Test case? Give an example.
- What do you understand by the term CASE Tools?
--- Content provided by FirstRanker.com ---
--- Content provided by FirstRanker.com ---
SECTION -B
Note: Attempt any 5 questions from this section(5×10=50)
--- Content provided by FirstRanker.com ---
- If project cannot be delivered within the deadline, explain how it will be changed in stepwise project planning. Explain your answer with a suitable example?
- What is the need of Software Project estimation? How it is utilized in project plan? Discuss the various estimation methods with neat example?
- What is mean by earned value analysis? What are the different types of earned value indicators? Describe any two earned value indicators with suitable examples?
- Explain the SEI/CMM process model, its maturity levels and the key process areas for each level?
- Compare product life cycle and Project life cycle with an example. What is Gantt charts? Explain their use in Scheduling?
- Discuss briefly about the Cost variance and Schedule Variance with example?
- What is mean by proof of Correctness? Also discuss the difference between Code Inspection and Code Walkthrough?
- With a suitable illustration, explain how Risk Management is managed during critical part in Software Project Management?
--- Content provided by FirstRanker.com ---
SECTION-C
Note: Attempt any 2 questions from this section(2×15=30)
--- Content provided by FirstRanker.com ---
- Explain with examples the scheduling fundamental. Explain PERT and CPM scheduling in terms of network diagram with neat sketches?
- Elaborate on the planning and organizing for Software Configuration Management(SCM) which includes potential SCM problem classes, staffing and tools. Also state the benefits of SCM process and tools.
- Write short note on the following:
- Project Validation Technique
- Risk Monitoring
- Network diagrams