FirstRanker Logo

FirstRanker.com - FirstRanker's Choice is a hub of Question Papers & Study Materials for B-Tech, B.E, M-Tech, MCA, M.Sc, MBBS, BDS, MBA, B.Sc, Degree, B.Sc Nursing, B-Pharmacy, D-Pharmacy, MD, Medical, Dental, Engineering students. All services of FirstRanker.com are FREE

📱

Get the MBBS Question Bank Android App

Access previous years' papers, solved question papers, notes, and more on the go!

Install From Play Store

Download GTU B.Tech 2020 Winter 7th Sem 2172903 Production Planning And Maintenance Question Paper

Download GTU (Gujarat Technological University Ahmedabad) B.Tech/BE (Bachelor of Technology/ Bachelor of Engineering) 2020 Winter 7th Sem 2172903 Production Planning And Maintenance Previous Question Paper

This post was last modified on 04 March 2021

GTU B.Tech 2020 Winter Question Papers || Gujarat Technological University


FirstRanker.com

Subject Code:2172903

GUJARAT TECHNOLOGICAL UNIVERSITY

--- Content provided by⁠ FirstRanker.com ---

BE- SEMESTER-VII (NEW) EXAMINATION - WINTER 2020

Subject Name:Production Planning & Maintenance

Date:21/01/2021

Time:10:30 AM TO 12:30 PM

Total Marks: 56

--- Content provided by FirstRanker.com ---

Instructions:

  1. Attempt any FOUR questions out of EIGHT questions.
  2. Make suitable assumptions wherever necessary.
  3. Figures to the right indicate full marks.

Q.1

--- Content provided by‌ FirstRanker.com ---

  1. Write the equation for calculation of total number of ends and total number of picks in the fabric. (MARKS 03)
  2. Calculate number of Warping machines running at 550 mts/min with 51% efficiency and having 450 ends/beam with a set length of 25000 mts/beam to receive the wound packages weighing 15000 kgs and having 30° yarn count per day from a Unit having Winding machines. (MARKS 04)
  3. Prepare production schedule to produce 1200 kgs/shift of 60s Ne semi combed warp and 800 kgs/shift of 60s Ne semi combed weft on modern spinning line. Hence calculate number of bales required at Blow room if each bale is of 200 kgs and trash removed at Blow room is 6%. (MARKS 07)

Q.2

  1. Calculate production of Carding machine per shift from following data:
    • Hank of lap fed - 0.0014
    • --- Content provided by‌ FirstRanker.com ---

    • Draft - 90
    • Efficiency - 85%
    • Doffer rpm - 40
    • Doffer diameter - 27 inch
    (MARKS 03)
  2. --- Content provided by⁠ FirstRanker.com ---

  3. Calculate the weight of warp and weft threads to be required to produce 1.50 lac metres of grey fabric per day having following details :
    • Reed/Pick—96/56
    • Warp/Weft — 30/36
    • Fabric Width — 52 inches
    (MARKS 04)
  4. Calculate the number of Texturing machines each having 160 spindles and running at 1200 mts/min with 95 % efficiency to be required to supply 76 Denier warp & 76 Denier weft textured yarn per day to the Weaving unit having following details :
    • 240 Waterjet Weaving machines running at 750 rpm to produce shirting fabric
    • --- Content provided by‍ FirstRanker.com ---

    • Reed/Pick : 66/56
    • 52 inches of width
    • 94 % efficiency
    (MARKS 07)

Q.3

--- Content provided by‌ FirstRanker.com ---

  1. State importance of maintenance in winding department. (MARKS 03)
  2. Explain, in detail, the daily, weekly and monthly check points for warping machines. (MARKS 04)
  3. Calculate the number of sizing machines having following details to be required to supply sized beams per day to a weaving unit having 224 plain power looms, weaving 60 picks/inch quality of fabric and running at 145 rpm with 96% efficiency.

    Sizing machine details :

    • speed -160 feet/min,
    • using 36 yarn count
    • --- Content provided by FirstRanker.com ---

    • efficiency % - 48
    • 600 metres of warp sheet length per sized beam
    • 3000 ends/beam
    (MARKS 07)

Q.4

--- Content provided by‍ FirstRanker.com ---

  1. Calculate time after which the weft package is to be replaced using following details :
    • Speed rpm / Efficiency % -510/95
    • R.S.(cm)-140
    • Weft Denier — 66
    • PPI-76
    • Weight of Yarn on package — 1.2 kgs
    • --- Content provided by‍ FirstRanker.com ---

    (MARKS 03)
  2. A mill wants to produce 6000 m of a particular fabric every day. Calculate no. of bobbins required from pirn winding department using following details :
    • R.S.-48”
    • PPI-56
    • Count-36 Ne
    • Length contraction — 5%
    • --- Content provided by⁠ FirstRanker.com ---

    • Weight of yarn on pirn — 1.4 ozs
    • Pirn winding speed/Eff. — 450 ypm/72%
    (MARKS 04)
  3. Calculate allocation of looms for a weaving unit having plain power looms running at 140 rpm if the frequency of warp breaks, weft breaks, shuttle change and weft change observed for 92,000 picks are found to be 19,9,63, and 81 respectively. (MARKS 07)

Q.5

--- Content provided by​ FirstRanker.com ---

  1. Calculate the rpm of Air jet loom if the weft insertion rate is 2000 metres/min and the fabric width is 56 inches. Assume efficiency of 97 %. (MARKS 03)
  2. Explain, in detail, the daily, weekly and monthly check points for sizing machines. (MARKS 04)
  3. A Yarn Preparatory Unit having 6 Warping machines running at 550 mts/min with 55 % efficiency and having 520 ends/beam with a set length of 24000 mts/beam. Calculate number of Winding machines each having 120 spindles and running at 1100 mts/min with 89% efficiency to be required to supply wound packages having 30 yarn count per day to meet with the requirements of the said Yarn Preparatory Unit. (MARKS 07)

Q.6

  1. Calculate length of roving available on roving bobbin from following data :
    • Hank of roving- 1.2
    • --- Content provided by⁠ FirstRanker.com ---

    • TM-1.0
    • Spindle RPM - 1400
    • Efficiency - 90%
    • Time to fill one doff - 5 Hrs
    (MARKS 03)
  2. --- Content provided by‍ FirstRanker.com ---

  3. Discuss in detail maintenance of carding machine. (MARKS 04)
  4. Prepare production schedule for comber to produce 1000 kgs of comber sliver of 80s Ne. Assume noil 12 % . Hence calculate number of comber required from following data:
    • Feed/nip - 8 mm
    • Nips/min - 350
    • Efficiency - 88%
    • Hank of lap fed - 0.016
    • --- Content provided by​ FirstRanker.com ---

    (MARKS 07)

Q.7

  1. Calculate number of laps produced in blow room/shift, if lap roller rpm is 10, diameter is 10 inch, efficiency is 84% , length of lap is 40 mts , number of scutcher are 2. (MARKS 03)
  2. Calculate production of Draw frame department having 2 Draw frames with twin deliveries, if hank of sliver delivered is 0.14, delivery speed is 800 mts/min, efficiency is 92%. (MARKS 04)
  3. Prepare spin plan to produce rotor spun yarn of 14s Ne warp & 16s Ne weft, if hank of lap used is 0.0012 and twist contraction is 5.5 % for warp and 5.2% for weft. (MARKS 07)
  4. --- Content provided by​ FirstRanker.com ---

Q.8

  1. Calculate number of cans filled/shift at single delivery draw frame if can accommodates 5000 mts of drawn sliver. The draw frame is running at 600 mts/min and 90% efficiency. (MARKS 03)
  2. Following data refers to rotor spinning machine :
    • Rotor Rpm — 1,00,000
    • TM-5.5
    • Count—24s Ne
    • --- Content provided by⁠ FirstRanker.com ---

    • Efficiency — 90%
    Calculate :
    1. Production/rotor spindle /shift
    2. Time to fill package of 1 kg
    (MARKS 04)
  3. A ring frame department is working with following parameters:
    • Hank of roving fed - 1.4
    • --- Content provided by FirstRanker.com ---

    • Draft-26
    • TM-4.0
    • Spindle rpm - 16000
    • Efficiency -90%
    • Number of spindles /machine - 864
    • --- Content provided by⁠ FirstRanker.com ---

    Calculate
    • production /spindle/shift .
    • number of spindles required for producing 1000kgs of yarn/day
    (MARKS 07)