FirstRanker Logo

FirstRanker.com - FirstRanker's Choice is a hub of Question Papers & Study Materials for B-Tech, B.E, M-Tech, MCA, M.Sc, MBBS, BDS, MBA, B.Sc, Degree, B.Sc Nursing, B-Pharmacy, D-Pharmacy, MD, Medical, Dental, Engineering students. All services of FirstRanker.com are FREE

📱

Get the MBBS Question Bank Android App

Access previous years' papers, solved question papers, notes, and more on the go!

Install From Play Store

Download GTU B.Tech 2020 Winter 8th Sem 2180611 Construction Management Question Paper

Download GTU (Gujarat Technological University Ahmedabad) B.Tech/BE (Bachelor of Technology/ Bachelor of Engineering) 2020 Winter 8th Sem 2180611 Construction Management Previous Question Paper

This post was last modified on 04 March 2021

GTU B.Tech 2020 Winter Question Papers || Gujarat Technological University


FirstRanker.com

GUJARAT TECHNOLOGICAL UNIVERSITY
BE- SEMESTER-VIII (NEW) EXAMINATION — WINTER 2020

--- Content provided by FirstRanker.com ---

Subject Code:2180611 Date:19/01/2021
Subject Name:Construction Management
Time:02:00 PM TO 04:00 PM Total Marks: 56

Instructions:

  1. Attempt any FOUR questions out of EIGHT questions.
  2. --- Content provided by​ FirstRanker.com ---

  3. Make suitable assumptions wherever necessary.
  4. Figures to the right indicate full marks.

Q.1 (a) Explain tendering stage of project. [03]
(b) Explain (i) Total float (ii) Dummy activity [04]
(c) Calculate Earliest start time, Latest start time, Earliest Finish Time and Latest Finish time and critical path for the following project [07]

--- Content provided by‍ FirstRanker.com ---

Activity Predecessor Duration in weeks
A - 3
B A 4
C A 2
D B 5
E C 1
F C 2
G D,E 4
H F,G 3

Q.2 (a) Describe limitations of Bar chart. [03]
(b) For different activities of certain project, to, tm and tp in days are given below, calculate expected duration, Variance and standard deviation for each activity. [04]

Activity to tm tp
A 3 7 15
B 2 8 12
C 1 3 7
D 6 18 26

(c) What are the functions of organizations? Describe Line or military organization. [07]

Q.3 (a) Why PERT is considered better than CPM, for research and complicated projects? [03]
(b) Describe advantages of Project scheduling. [04]

--- Content provided by​ FirstRanker.com ---

(c) Describe resources smoothing. [07]

Q.4 (a) Explain (i) Earliest start time (ii) Latest finish time [03]
(b) Explain (i) Balance sheet (ii) Working capital [04]
(c) Discuss Principles and various steps in accounting process [07]

Q.5 (a) Explain ABC Analysis of Inventory control for material management [03]

--- Content provided by‍ FirstRanker.com ---

(b) Explain A-O-A and A-O-N Network [04]
(c) What is TQM? Describe Principles of TQM [07]

Q.6 (a) Explain significance of Quality control [03]
(b) Explain Building Block of TQM [04]
(c) Explain EOQ Model for material procurement [07]

--- Content provided by​ FirstRanker.com ---

Q.7 (a) Explain value Engineering [03]
(b) Prepare Job Layout for seven storeyed building. [04]
(c) Describe (i) causes of accidents and (ii) Contractor as stakeholder of construction Industry. [07]

Q.8 (a) Explain principles of safety [03]
(b) Explain graphical method of linear programming. [04]

--- Content provided by FirstRanker.com ---

(c) Explain Success attributes for project performance evaluation. [07]