Roll No.
Total No. of Pages : 02
Total No. of Questions : 09
--- Content provided by FirstRanker.com ---
B.Tech. (Ind. Engg. & Mgt.) (Spl. in TQM) (Sem.-3)
OPERATIONS MANAGEMENT
Subject Code : IEM-301
M.Code: 61011
Time: 3 Hrs.
--- Content provided by FirstRanker.com ---
Max. Marks : 40
INSTRUCTIONS TO CANDIDATES :
- Attempt All EIGHT questions from SECTION-A carrying TWO marks each.
- Attempt any SIX questions out of EIGHT from SECTION-B carrying FOUR marks each.
SECTION-A
--- Content provided by FirstRanker.com ---
Q1. Answer briefly :
- Explain the functions of operations management.
- Discuss the centre of gravity method of facilities location.
- What are the advantages of computer packages in plant layout?
- "Material Handling is considered necessary evil” Comment.
- Explain “Delphi Technique of Forecasting".
- Differentiate between design capacity, system capacity and installed capacity.
- Define MRP, CRP and BOM.
- What do you understand by dispatching and reporting?
--- Content provided by FirstRanker.com ---
SECTION-B
--- Content provided by FirstRanker.com ---
Q2. Differentiate between batch, job and continuous production systems.
Q3. Explain the factors that influence the location of sugar industries. Justify your answer.
Q4. Differentiate in brief between product, process, group technology and fixed position layout.
Q5. State for what applications the following material handling equipments are used :
- Fork lift truck
- Jib crane
- Belt conveyor
- Roller conveyor
--- Content provided by FirstRanker.com ---
Q6. The following data relates the cost of production and sales prices :
2004 | 2005 | 2006 | 2007 | 2008 | 2009 | 2010 | 2011 | 2012 | |
---|---|---|---|---|---|---|---|---|---|
Costs | 203 | 216 | 223 | 239 | 248 | 253 | 270 | 301 | 311 |
Prices | 225 | 242 | 250 | 271 | 275 | 277 | 295 | 318 | 329 |
Establish the co-efficient of correlation between costs and prices.
--- Content provided by FirstRanker.com ---
Q7. Discuss in detail the use of decision tree for capacity planning.
Q8. Elaborate the following :
- ERP
- Master production schedule
Q9. Five jobs are to be processed on two machines M1 and M2 in the order M1M2. Processing times in hours are given below :
--- Content provided by FirstRanker.com ---
Job | Machine M1 | Machine M2 |
---|---|---|
Processing times (hrs) | ||
1 | 5 | 2 |
2 | 1 | 6 |
3 | 9 | 7 |
4 | 3 | 8 |
5 | 10 | 4 |
Determine the sequence that minimizes total elapsed time. Find out the total elapsed time and idle time (if any) on M2.
NOTE : Disclosure of Identity by writing Mobile No. or Making of passing request on any page of Answer Sheet will lead to UMC against the Student.
--- Content provided by FirstRanker.com ---
This download link is referred from the post: PTU B.Tech 3rd Semester Last 10 Years 2011-2021 Previous Question Papers|| Punjab Technical University