Download JNTUH (Jawaharlal nehru technological university) MCA (Master of Computer Applications) 4th Sem (Fourth Semester) Regulation-R15 2018 January 824AG Software Process And Project Management Previous Question Paper
R15
Code No: 824AG
JAWAHARLAL NEHRU TECHNOLOGICAL UNIVERSITY HYDERABAD
MCA IV Semester Examinations, January - 2018
SOFTWARE PROCESS AND PROJECT MANAGEMENT
Time: 3hrs
Max.Marks:75
Note: This question paper contains two parts A and B.
Part A is compulsory which carries 25 marks. Answer all questions in Part A. Part B
consists of 5 Units. Answer any one full question from each unit. Each question carries
10 marks and may have a, b, c as sub questions.
PART - A
5 ? 5 Marks = 25
1.a) What are the improvements done to the basic waterfall model that would eliminate most
of the development risks?
[5]
b) Give the top five principles of a modern process.
[5]
c) What are the primary objectives of inception phase?
[5]
d) What will be the impact of periodic status assessments on software project?
[5]
e) List out the differences in workflow priorities between small and large projects. [5]
PART - B
5 ? 10 Marks = 50
2.
Describe the performance of conventional software project management.
[10]
OR
3.
What are the characteristics of a good estimate? Explain its role and significance in
pragmatic software cost estimation.
[10]
4.
Explain the steps to improve team effectiveness with relevant examples.
[10]
OR
5.
Discuss the top risks involved in conventional software process and how can a modern
software process resolves these risks.
[10]
6.
Describe the differences in emphasis between engineering stage and production stage.
[10]
OR
7.a)
Give typical release specification outline.
b)
Summarize the artifacts of the design set with neat UML diagram.
[5+5]
8.
Describe the artifacts and life-cycle emphases associated with seven workflows of a
software process.
[10]
OR
9.a)
What are the various levels of the evolutionary Work break down structure?
b)
Discuss the activities of software architecture team.
[5+5]
10.a) What social factors are observed on software projects?
b) Give life cycle overview of CCPDS-R project.
[5+5]
OR
11.
Explain about SLOC-to-ESLOC conversion factors that measures the performance of
CCPDS-R project.
[10]