GUJARAT TECHNOLOGICAL UNIVERSITY
MBA - SEMESTER- IV EXAMINATION — WINTER 2019
Subject Code: 3549286 Date: 29-11-2019
Subject Name: Project Management for Entrepreneurs
Time: 2.30 PM to 5.30 PM Total Marks: 70
--- Content provided by FirstRanker.com ---
Instructions:
- Attempt all questions.
- Make suitable assumptions wherever necessary.
- Figures to the right indicate full marks.
Q1. Define the following terms- 14
--- Content provided by FirstRanker.com ---
- PPP
- BOOT
- WBS
- PERT
- Crowd financing
- Angel investors
- Virtual teams
--- Content provided by FirstRanker.com ---
Q2. (A) Discuss the characteristics of a project and explain skill and responsibilities needed by a project manager? 07
Q2. (B) What is a project life cycle? Explain with some example. 07
OR
--- Content provided by FirstRanker.com ---
Q2. (B) What are the virtual teams? How that can be managed? 07
Q3. (A) what are the different sources finance in a project? 07
Q3. (B) What is WBS? How it helps in project management? 07
OR
Q3. (A) What is project planning? Explain. 07
--- Content provided by FirstRanker.com ---
Q3. (B) What is project control process? How important it is ? 07
Q4. (A) what are the project closures? Explain the same with some practical example. 07
Q4. (B) explain top-down approaches for time and cost estimation in projects. 07
OR
Q4. (A) What are the ideal characteristics of a project manager? Explain. 07
--- Content provided by FirstRanker.com ---
Q4. (B) “Risk is an essential part of project management”, explain the types of risk with relevance of the statement. 07
PTO
FirstRanker.com Page 1 of 2
FirstRanker.com
Firstranker's choice
--- Content provided by FirstRanker.com ---
Q5. A project has been defined to contain the following activities, along with their estimates for completion- 14
activity | predecessor | Time (a) | Time (m) | Time (b) |
---|---|---|---|---|
A | - | 1 | 4 | 7 |
B | A | 2 | 6 | 7 |
C | A,D | 3 | 4 | 6 |
D | A | 6 | 12 | 14 |
E | D | 3 | 6 | 12 |
F | B,C | 6 | 8 | 16 |
G | E,F | 1 | 5 | 6 |
(a) Calculate expected time and variance for each activity
(b) Draw critical path
(a) What is crashing of projects?
OR
--- Content provided by FirstRanker.com ---
(b) What is project communication? How communication plays an important role in managing projects?