Seat No.: ________ Enrolment No.___________

GUJARAT TECHNOLOGICAL UNIVERSITY
MBA ? SEMESTER III ? EXAMINATION ? WINTER 2019

Subject Code: 4539273 Date:05/12/2019
Subject Name: Production Planning and Control
Time: 10:30 AM TO 01:30 PM Total Marks: 70
Instructions:
1. Attempt all questions.
2. Make suitable assumptions wherever necessary.
3. Figures to the right indicate full marks.

Q. No. Question Text and Description Marks
Q.1 Briefly explain the following terms
(a) Production System
(b) Master production schedule (MPS)
(c) Subsidiary order
(d) Preventive maintenance
(e) Bill of materials (BOM)
(f) Design capacity
(g) Material handling
14
Q.2 (a) Explain the importance of Production Planning and Control. 07
(b) Explain the various types of Production System. 07


OR
(b) Explain the various Stages of Production Planning and Control. 07

Q.3 (a) What is Aggregate Planning? List the Steps in Developing an Aggregate
Plan.
07
(b) Discuss material handling principles and classify material handling
equipment.
07
OR
Q.3 (a) What is layout planning? Explain the Facility Layout Objective. 07
(b) Define Routing and explain the Techniques of Routing in Production
Planning and Control.
07

Q.4 (a) Explain the Principles and Types of Scheduling in brief. 07
(b) What is the Material Requirement Planning (MRP)? Explain the
objectives of the MRP in brief.
07
OR
Q.4 (a) What is meant by maintenance management? Explain the Objectives of
maintenance in brief.
07
(b) What is safety audit? What is the need of safety audit? 07
FirstRanker.com - FirstRanker's Choice
Page 1 of 2


Seat No.: ________ Enrolment No.___________

GUJARAT TECHNOLOGICAL UNIVERSITY
MBA ? SEMESTER III ? EXAMINATION ? WINTER 2019

Subject Code: 4539273 Date:05/12/2019
Subject Name: Production Planning and Control
Time: 10:30 AM TO 01:30 PM Total Marks: 70
Instructions:
1. Attempt all questions.
2. Make suitable assumptions wherever necessary.
3. Figures to the right indicate full marks.

Q. No. Question Text and Description Marks
Q.1 Briefly explain the following terms
(a) Production System
(b) Master production schedule (MPS)
(c) Subsidiary order
(d) Preventive maintenance
(e) Bill of materials (BOM)
(f) Design capacity
(g) Material handling
14
Q.2 (a) Explain the importance of Production Planning and Control. 07
(b) Explain the various types of Production System. 07


OR
(b) Explain the various Stages of Production Planning and Control. 07

Q.3 (a) What is Aggregate Planning? List the Steps in Developing an Aggregate
Plan.
07
(b) Discuss material handling principles and classify material handling
equipment.
07
OR
Q.3 (a) What is layout planning? Explain the Facility Layout Objective. 07
(b) Define Routing and explain the Techniques of Routing in Production
Planning and Control.
07

Q.4 (a) Explain the Principles and Types of Scheduling in brief. 07
(b) What is the Material Requirement Planning (MRP)? Explain the
objectives of the MRP in brief.
07
OR
Q.4 (a) What is meant by maintenance management? Explain the Objectives of
maintenance in brief.
07
(b) What is safety audit? What is the need of safety audit? 07
Page 2 of 2

Q.5

















CASE STUDY:
TVS Motor Company is the third largest two-wheeler company in India
and is among the top ten in the world. The company exports its vehicle
unassembled to reduce shipping costs. It was facing problems in the
order-fulfillment process. The order fulfillment process was entirely
manual without any controls integrated into the process and the
employees walked through the company?s warehouse fulfilling each
order. The process resulted in missing or mismatched parts, and the
company had to incur extra costs to reship the correct parts. The company
lacked visibility of its picking, packing and shipping processes, and a
large number of employees were required to fulfill orders.

The company has been using SAP ERP, and it decided to customize it to
improve its order fulfillment process. It integrates barcode and wireless
technology with the sales and distribution function of SAP ERP. It
developed a cart that houses a scanner, a barcode printer, and weighing
scale that communicates wirelessly with SAP ERP. Each part?s exact
location is transmitted to the chart, and hence Employees do not waste
time looking for them. Employees do not now count the parts such as
nuts and bolts that are shipped in quantity. The parts are weighted on the
cart?s scale, and when the predetermined weight is reached, a barcode
sticker is generated. SAP ERP also ensures that orders are optimally
packed and arranged in shipping containers to maximize utilization of
space and reduce freight costs. The company was able to eliminate
missing and mismatched part in its export orders, and since SAP ERP
provides full traceability of international shipments, it can address
customer order inquiries quickly. Productivity has improved
dramatically. Earlier an employee walked 9.6kilometers to fulfill 90
orders, but now he has to walk just 40 meters to fulfill the same number
of orders.



















(a) What problem did the company face? 07
(b) How did it solve the problem? 07
OR
Q.5 (a) What else could have been done? 07
(b) Which benefits gained by the company after integrated its control? 07

*************