FirstRanker Logo

FirstRanker.com - FirstRanker's Choice is a hub of Question Papers & Study Materials for B-Tech, B.E, M-Tech, MCA, M.Sc, MBBS, BDS, MBA, B.Sc, Degree, B.Sc Nursing, B-Pharmacy, D-Pharmacy, MD, Medical, Dental, Engineering students. All services of FirstRanker.com are FREE

📱

Get the MBBS Question Bank Android App

Access previous years' papers, solved question papers, notes, and more on the go!

Install From Play Store

Download GTU MBA 2018 Summer 1st Sem 2820006 Production And Operation Management Question Paper

Download GTU (Gujarat Technological University) MBA (Master of Business Administration) 2018 Summer 1st Sem 2820006 Production And Operation Management Previous Question Paper

This post was last modified on 19 February 2020

GTU MBA Last 10 Years 2010-2020 Question Papers || Gujarat Technological University


FirstRanker.com

Seat No.: Enrolment No.

GUJARAT TECHNOLOGICAL UNIVERSITY

--- Content provided by‌ FirstRanker.com ---

MBA — SEMESTER 01- - EXAMINATION - SUMMER 2018

Subject Code:2820006 Date:23/05/2018

Subject Name: Production and Operation Management

Time:10:30 AM To 01:30 Total Marks: 70

Instructions:

--- Content provided by​ FirstRanker.com ---

  1. Attempt all questions.
  2. Make suitable assumptions wherever necessary.
  3. Figures to the right indicate full marks.

Q.1 Objective Questions

  1. Continuous Production process is used for of products.
    1. Few Variety
    2. --- Content provided by FirstRanker.com ---

    3. Many Variety
    4. No Variety
    5. Infinitive Variety
  2. Example of Batch Production is .
    1. Construction
    2. --- Content provided by​ FirstRanker.com ---

    3. Bakeries
    4. Automobile
    5. Paints
  3. Determine the best site for the warehouse using the centre of gravity technique.

    --- Content provided by​ FirstRanker.com ---

    A B C
    X 150 300 400
    Y 250 100 500
    w 140 110 170
    1. X=290.5&Y=311.9
    2. X=300.9 & Y=315.5
    3. X=275.7&Y=290.6
    4. X=305.7 & Y=320.2
  4. --- Content provided by‍ FirstRanker.com ---

  5. Which one is the correct job sequence for the given data.
    Job S T U V W
    M1 16 3 21 31 6
    M2 7 9 5 17 13
    1. T-W-V-S-U
    2. U-V-S-W-T
    3. S-U-V-W-T
    4. T-U-V-S-W
    5. --- Content provided by⁠ FirstRanker.com ---

  6. In EOQ =2A0/c, what is “c” ?
    1. Cost per Unit Per Day
    2. Cost per Unit Per Week
    3. Cost per Unit Per Month
    4. Cost per Unit Per Year
    5. --- Content provided by​ FirstRanker.com ---

  7. Whether Johnson’s rule can be applied for the given data?
    1. Can be applied
    2. Cannot be applied
    3. Data is insufficient
    4. None of the above
    5. --- Content provided by FirstRanker.com ---

Q.1 (b) Short / Definition Questions 04

  1. Job Shop
  2. Robust Design
  3. Revenue
  4. --- Content provided by‌ FirstRanker.com ---

  5. Cost of shortage

Q.1 (c) Draw the network diagram of the project for the following data. 04

Activity A B C D E F G H I J K L M N
Duration 2 1 5 1 3 1 4 1 3 1 2 1 2 5
Predecessor - - - A A B B C D E F G,H,I,J K L

Q.2 A company is planning to manufacture steel utensils. It is considering three location namely Bokaro, Jaipur and Bhillai. The fixed cost at the three location have been estimated at Rs. 8.15 million, Rs. 7.377 million and Rs. 7.903 million respectively. The variable cost for the three location have been estimated at Rs. 500 per unit, Rs. 580 per unit and Rs. 490 per unit respectively. The factory will have an annual production capacity of 10,000 steel utensils and in the initial year it will operate at 75% efficiency. Find the best location option, which has lowest total cost of production.

(b) Explain continuous production process with merits and demerits of it. 07

OR

--- Content provided by⁠ FirstRanker.com ---

(b) If you want to find out location for the Chemical Manufacturing Business then which factors you will consider? 07

Q.3 (a) Write note on Material handling equipment. 07

(b) “Shortages are undesirable, but some organizations create shortages intentionally’- do you agree with this statement? Why? Derive an expression for total cost in the inventory model for intentional shortage. 07

OR

Q.3 (a) Why is the ABC classification of items done? How is the ABC distribution curve drawn? 07

--- Content provided by‍ FirstRanker.com ---

(b) If you will implement Level Output Rate Plan for your product’s production then what will you have advantages and disadvantages of it? 07

Q.4 (a) What is Six Sigma? How is it implemented? 07

(b) ABC furniture is a manufacturer of executive tables for corporate institutions. In order to control the quality-ofiits table, the QC Manager selects 15 tables at random and inspects for the number of scratches on each one of them. The results given.in'the following table. Prepare a stable c chart based on this data. 07

Sample No. 1 2 3 4 5 6 7 8
No. of defects 13 9 19 7 8 10 12 0
Sample No. 9 10 11 12 13 14 15 ---
No. of defects 2 5 7 11 9 13 1

OR

Q.4 (a) What are the various types of certification in ISO 9000? What are the major clauses of ISO 9001? 07

--- Content provided by‌ FirstRanker.com ---

(b) Following table gives details about the various activities of a project. 07

Activity Node a m b
A 1-2 10 11 12
B 2-3 6 10 14
C 2-4 5 8 11
D 2-5 1 5 9
E 3-6 3 7 5
F 4-6 4 9 14
G 5-7 1 2 3
H 6-7 3 7 11
J 7-9 3 5 7

Q.5 Find: (a) the critical path of the project and its expected duration.

(b) the probability that the project will be completed in 50 days.

For a special component outsourced to a vendor and used in textile machinery manufactured by XYZ Machines Tools works at Coimbatore, we have the following situations:

Yearly demand 300000 units

--- Content provided by‌ FirstRanker.com ---

Purchase quantity 100000 units

Safety Stock 50000 units

The ordering cost, independent of purchase quantity, is Rs. 1500 for each purchase. The purchase price of the components is Rs. 75 per unit.

Annual holding cost is 20% of the value of the components (inventory interest rate is 20%). Assuming 230 working days per year, calculate:

  1. The number of purchase during the year
  2. --- Content provided by⁠ FirstRanker.com ---

  3. Average inventory level including the safety stock
  4. Average days of supply in inventory
  5. Reorder point if the lead time is 15 working days
  6. Total inventory costs per year and total inventory costs per working days with purchase quantity of 100000 units.
  7. EOQ
  8. --- Content provided by‍ FirstRanker.com ---

  9. Total inventory costs per year and total inventory costs per working days with EOQ and with a safety stock decreased to 5000 units.

OR

Q.5 ABC Ltd. Is a personal Computer assembling company based at Hyderabad. Its marketing department has‘given the demand forecast shown in the table for its PCs throughout the country in the coming six months from January to June. Every worker assembles two computers a day. The overtime cost is Rs. 3.per-day per unit in excess of the maximum capacity of the factory i.e. 200 units.

Month Jan Feb March April May June
Demand forecast (units) 1000 3000 1000 5000 7000 2000
No.of working days 24 25 20 22 20 24

Assume cost of change in output rate is:

1-100 2000

--- Content provided by‍ FirstRanker.com ---

101-200 5000

201-300 8000

The company wants to find the total cost involved in the following plans:

(a) Level Output Rate Plan (b) Chase Plan