FirstRanker Logo

FirstRanker.com - FirstRanker's Choice is a hub of Question Papers & Study Materials for B-Tech, B.E, M-Tech, MCA, M.Sc, MBBS, BDS, MBA, B.Sc, Degree, B.Sc Nursing, B-Pharmacy, D-Pharmacy, MD, Medical, Dental, Engineering students. All services of FirstRanker.com are FREE

📱

Get the MBBS Question Bank Android App

Access previous years' papers, solved question papers, notes, and more on the go!

Install From Play Store

Download GTU MBA 2018 Summer 8th Sem 4180503 Operations Management Question Paper

Download GTU (Gujarat Technological University) MBA (Master of Business Administration) 2018 Summer 8th Sem 4180503 Operations Management Previous Question Paper

This post was last modified on 19 February 2020

GTU MBA Last 10 Years 2010-2020 Question Papers || Gujarat Technological University


FirstRanker.com

Subject Code: 4180503

GUJARAT TECHNOLOGICAL UNIVERSITY

--- Content provided by FirstRanker.com ---

MBA (AM) SEMESTER 08 - EXAMINATION - SUMMER-2018

Subject Name: Operations Management

Time: 10:30 AM To 01:30 PM

Instructions:

  1. Attempt all questions.
  2. --- Content provided by​ FirstRanker.com ---

  3. Make suitable assumptions wherever necessary.
  4. Figures to the right indicate full marks.

Q.1 Explain following terms with suitable examples (ANY 7)

  1. Modern Operation Management
  2. Lean Manufacturing
  3. --- Content provided by FirstRanker.com ---

  4. Facility Location and Facility Layout
  5. Material Handling
  6. Reordering level in inventory management
  7. Job Sequencing
  8. Just in Time (JIT)
  9. --- Content provided by⁠ FirstRanker.com ---

  10. Bench Marking
  11. Inspection and Acceptance Sampling

Q.2 (a) Write a note on “Production Planning and Control (PPC)” [07]

(b) Draw the network find Critical Path and calculate EST,EFT,LST,LFT and Slack timing available [07]

Activity 1-2 1-6 2-3 2-4 3-5 4-5 6-7 5-8 7-8

--- Content provided by⁠ FirstRanker.com ---

Time (Days) 6 5 13 4 11 6 11 3 15

OR

(b) What is ‘line structure’ in waiting-lines? Explain single channel- single phase, multi channel- single phase and‘multi channel- multiphase line structures. [07]

Q.3 (a) “Operations management is a transformation process”. Support this statement with examples if you agree with it. [07]

(b) Take any service sector-of your choice. When you visit for this service what are the dimensions based on which you will judge overall service quality? If you are appointed as an operations manager, how will you creatively design or innovate the service to improve the quality? [07]

--- Content provided by⁠ FirstRanker.com ---

OR

(b) Discuss the types of processes. What are the merits and demerits of each? Give an example of each. [07]

Q.4 (a) Differentiate Product design and process design with suitable examples. [07]

(b) Define the various types of plant layout in brief with suitable examples of each. [07]

OR

--- Content provided by‌ FirstRanker.com ---

(a) What is inventory and inventory management? Discuss inventory management techniques. [07]

(b) What is meant by aggregate production planning? Why it is required? [07]

Q.5 (a) What is MRP? What are the inputs and outputs required by the MRP processing logic? [07]

(b) Mention various charting methods used in statistical quality control. [07]

FirstRanker.com

--- Content provided by‌ FirstRanker.com ---

OR

Q.5 (a) What is Six — Sigma? Write steps for implementing six — sigma. [07]

(b) Write a note on Industrial safety & safety management. [07]

Date:02/05/2018

Total Marks: 70

--- Content provided by FirstRanker.com ---

FirstRanker.com



This download link is referred from the post: GTU MBA Last 10 Years 2010-2020 Question Papers || Gujarat Technological University

--- Content provided by⁠ FirstRanker.com ---