FirstRanker Logo

FirstRanker.com - FirstRanker's Choice is a hub of Question Papers & Study Materials for B-Tech, B.E, M-Tech, MCA, M.Sc, MBBS, BDS, MBA, B.Sc, Degree, B.Sc Nursing, B-Pharmacy, D-Pharmacy, MD, Medical, Dental, Engineering students. All services of FirstRanker.com are FREE

📱

Get the MBBS Question Bank Android App

Access previous years' papers, solved question papers, notes, and more on the go!

Install From Play Store

Download GTU BE/B.Tech 2019 Winter 6th Sem New 2161303 Estimating Specifications And Project Management Question Paper

Download GTU (Gujarat Technological University) BE/BTech (Bachelor of Engineering / Bachelor of Technology) 2019 Winter 6th Sem New 2161303 Estimating Specifications And Project Management Previous Question Paper

This post was last modified on 20 February 2020

GTU BE/B.Tech 2019 Winter Question Papers || Gujarat Technological University


FirstRanker.com

GUJARAT TECHNOLOGICAL UNIVERSITY
BE - SEMESTER- VI (New) EXAMINATION - WINTER 2019

--- Content provided by⁠ FirstRanker.com ---

Subject Code: 2161303 Date: 12/12/2019
Subject Name: Estimating, Specifications & Project Management
Time: 02:30 PM TO 05:00 PM Total Marks: 70

Instructions:

  1. Attempt all questions.
  2. --- Content provided by​ FirstRanker.com ---

  3. Make suitable assumptions wherever necessary.
  4. Figures to the right indicate full marks.

Q.1 (a) Define Project Management. 03

(b) Classify Contracts. 04

(c) Prepare a Tender Notice inviting tenders for BOD Incubator for an educational institute with estimated cost of Rs.48000/-. 07

--- Content provided by FirstRanker.com ---

Q.2 (a) Define Contract. 03

(b) Classify Specifications. 04

(c) Restate essential requirements of a valid Contract. 07

OR

(c) Describe Unbalanced Tender with example 07

--- Content provided by​ FirstRanker.com ---

Q.3 (a) Define Estimating. 03

(b) Enlist objectives & uses of Specification. 04

(c) Prepare rate analysis for Cement concrete (1:2:4). 07

OR

Q.3 (a) Define Rate analysis. 03

--- Content provided by‌ FirstRanker.com ---

(b) “Project Management is a tool for cost saving”, Argue. 04

(c) Outline detailed specifications for Excavation work. 07

Q.4 (a) Define Tender. 03

(b) Differentiate between CPM & PERT. 04

(c) Evaluate Lump-sum Contract and Unit-rate Contract for their suitability. 07

--- Content provided by⁠ FirstRanker.com ---

OR

Q.4 (a) Define SOR. 03

(b) Compare Long-wall, Short-wall method and Center line method. 04

(c) Restate Condition of Contract for Arbitration. 07

Q.5 (a) Define Project Scheduling. 03

--- Content provided by FirstRanker.com ---

(b) Differentiate between Earnest Money Deposit & Security Deposit. 04

(c) Describe the procedure to carry out the estimation of quantities for typical Septic Tank. 07

OR

Q.5 (a) Define Dummy Activity. 03

(b) Differentiate between Milestone chart & Bar chart. 04

--- Content provided by‌ FirstRanker.com ---

(c) Calculate the Completion period and prepare Network diagram for following details:

Activity Item A B C D E F G
Duration in Days 88 54 65 92 96 74 45
Activity Immediately Preceding --- A A B BC DE E
Activity Immediately Following B.C D.E E F F.G - -