Download GTU BE/B.Tech 2019 Winter 7th Sem New 2170610 Professional Practices And Valuation Question Paper

Download GTU (Gujarat Technological University) BE/BTech (Bachelor of Engineering / Bachelor of Technology) 2019 Winter 7th Sem New 2170610 Professional Practices And Valuation Previous Question Paper

1
Seat No.: ________ Enrolment No.___________

GUJARAT TECHNOLOGICAL UNIVERSITY

BE - SEMESTER ? VII (New) EXAMINATION ? WINTER 2019
Subject Code: 2170610 Date: 03/12/2019

Subject Name: Professional Practices & Valuation
Time: 10:30 AM TO 01:00 PM Total Marks: 70

Instructions:
1. Attempt all questions.
2. Make suitable assumptions wherever necessary.
3. Figures to the right indicate full marks.


Q.1 (a) Write formulas for the following: (1) Area of Segment of Circle (2) Volume of
frustum of cone (3) Volume of sphere
03
(b) Define following terms ? Estimate, Contingencies, Spot Item, Prime Cost 04
(c) For the following given figure a, calculate the quantities of following items by
Centre line method
a) Earthwork in Excavation in foundation
b) Cement Concrete bed in Foundation
c) Brick masonry work in foundation up to plinth in cm 1:6.

07

Q.2 (a) Discuss accuracy criteria for concrete 03
(b) Compare revised estimate and supplementary estimate. 04
(c) What is Contract? List out Various types of Special contract and explain
Turnkey Contract in detail.
07
OR
(c) Enlist different types of tenders & explain anyone them 07
Q.3 (a) Provide the Prevailing market rate of the following materials in your city:
10 mm diameter MS Bar, Gully Trap, Kota Stone.
03
(b) Define rate analysis. How we can fix rate per unit of item in rate analysis? 04
(c) Calculate the following:
1. No. of bricks required for 5 cu. m. brickwork.
2. Materials required for M20 Grade of Concrete
07
OR
Q.3 (a) Write short note on Schedule of rates (S.O.R) & Task of Work 03
(b) Differentiate between Estimation & Valuation 04
(c) Write short note on :
1. Scrutiny of tender 2. Classification of tender
07
Q.4 (a) A person requires Rs. 20000 after 5 years for the repair of his house. What
amount he needs to invest at 7% to get required amount after said years?
03
(b) What should be the amount of loan instalment if loan amount is Rs. 12,00,000
to be paid at annual interest rate of 13.78 % in 363 months
04
(c) Calculate rent of newly constructed building from given data. 1) Cost of
Land=7,00,000 , 2) Cost of Construction = 5,50,000 , 3) Total outgoings
including sinking fund = 15.8 % of GI , 4) Net return @ 10% on construction
and 5% on Land

07
OR
FirstRanker.com - FirstRanker's Choice
1
Seat No.: ________ Enrolment No.___________

GUJARAT TECHNOLOGICAL UNIVERSITY

BE - SEMESTER ? VII (New) EXAMINATION ? WINTER 2019
Subject Code: 2170610 Date: 03/12/2019

Subject Name: Professional Practices & Valuation
Time: 10:30 AM TO 01:00 PM Total Marks: 70

Instructions:
1. Attempt all questions.
2. Make suitable assumptions wherever necessary.
3. Figures to the right indicate full marks.


Q.1 (a) Write formulas for the following: (1) Area of Segment of Circle (2) Volume of
frustum of cone (3) Volume of sphere
03
(b) Define following terms ? Estimate, Contingencies, Spot Item, Prime Cost 04
(c) For the following given figure a, calculate the quantities of following items by
Centre line method
a) Earthwork in Excavation in foundation
b) Cement Concrete bed in Foundation
c) Brick masonry work in foundation up to plinth in cm 1:6.

07

Q.2 (a) Discuss accuracy criteria for concrete 03
(b) Compare revised estimate and supplementary estimate. 04
(c) What is Contract? List out Various types of Special contract and explain
Turnkey Contract in detail.
07
OR
(c) Enlist different types of tenders & explain anyone them 07
Q.3 (a) Provide the Prevailing market rate of the following materials in your city:
10 mm diameter MS Bar, Gully Trap, Kota Stone.
03
(b) Define rate analysis. How we can fix rate per unit of item in rate analysis? 04
(c) Calculate the following:
1. No. of bricks required for 5 cu. m. brickwork.
2. Materials required for M20 Grade of Concrete
07
OR
Q.3 (a) Write short note on Schedule of rates (S.O.R) & Task of Work 03
(b) Differentiate between Estimation & Valuation 04
(c) Write short note on :
1. Scrutiny of tender 2. Classification of tender
07
Q.4 (a) A person requires Rs. 20000 after 5 years for the repair of his house. What
amount he needs to invest at 7% to get required amount after said years?
03
(b) What should be the amount of loan instalment if loan amount is Rs. 12,00,000
to be paid at annual interest rate of 13.78 % in 363 months
04
(c) Calculate rent of newly constructed building from given data. 1) Cost of
Land=7,00,000 , 2) Cost of Construction = 5,50,000 , 3) Total outgoings
including sinking fund = 15.8 % of GI , 4) Net return @ 10% on construction
and 5% on Land

07
OR
2
Q.4 (a) What do you mean by value? State the purposes of Valuation. 03
(b) Differentiate between Earnest Money Deposit & Security Deposit. 04
(c) Define the following terms: 1. Scrap value 2. Estimating 3. Cost 4. Salvage
value 5. Book Value 6. Free hold property 7. Lease hold property
07
Q.5 (a) Explain following terms ? Liquidated Damages, Unbalanced Tender,
Arbitration
03
(b) Discuss various reasons for rejection of the lowest tender. 04
(c) Discuss mode of payment to the contractor. How the first and final bill, running
or interim bills are paid to contractor?
07
OR
Q.5 (a) Write difference between: 'Depreciation and Obsolescence.' 03
(b) Define specification. What are the purpose of writing 04
(c) Explain in brief various principles of writing good specifications 07





Figure: a
In figure: In section-AB consider data for section starting from pcc (from bottom) pcc : 0.9 m, of step 1:
0.6 m, of step 2: 0.5 m, of step 3: 0.4 m, wall : 0.2 m

*************
FirstRanker.com - FirstRanker's Choice

This post was last modified on 20 February 2020