Subject Code: 2172011
GUJARAT TECHNOLOGICAL UNIVERSITY
BE - SEMESTER- VII (New) EXAMINATION — WINTER 2019
--- Content provided by FirstRanker.com ---
Subject Name: Production Optimization Techniques
Time: 10:30 AM TO 01:00 PM
Instructions:
- Attempt all questions.
- Make suitable assumptions wherever necessary.
- Figures to the right indicate full marks.
--- Content provided by FirstRanker.com ---
Q.1 (a) Explain the evolution of modern management. [03]
(b) What do you meant by a feasible solution of an LPP? [04]
(c) Explain application of linear programming. [07]
Q.2 (a) Explain how a profit maximization transportation problem can be converted to an equivalent cost minimization transportation problem. [03]
--- Content provided by FirstRanker.com ---
(b) Find the initial basic feasible solution for given problem by using least cost method: [04]
D1 | D2 | D3 | D4 | Supply | |
---|---|---|---|---|---|
P1 | 2 | 3 | 11 | 7 | 6 |
P2 | 1 | 0 | 6 | 1 | 1 |
P3 | 5 | 8 | 15 | 9 | 10 |
Demand | 7 | 5 | 3 | 2 |
(c) Use the Big-M method to solve the following LPP [07]
Maximize Z=5X1+3X2
Subject to constraints,
2X1+4X2 <= 12, 2X1 +2X2 =10,
--- Content provided by FirstRanker.com ---
5X1 +2X2>=10 and X1, X2>=0.
OR
Use the two-phase method to solve the following LPP
Minimize Z=X1+X2
Subject to constraints,
--- Content provided by FirstRanker.com ---
2X1+X2>= 4, X1 +7X2>=7 and X1, X2>=0.
Q.3 (a) What is an assignment problem? Give the applications also. [03]
(b) What are the methods used for solving an assignment problem? [04]
(c) Apply MODI method to obtain optimal solution of transportation problem: [07]
D1 | D2 | D3 | D4 | supply | |
---|---|---|---|---|---|
S1 | 19 | 30 | 50 | 10 | 7 |
S2 | 70 | 30 | 40 | 60 | 9 |
S3 | 40 | 8 | 70 | 20 | 18 |
Demand | 5 | 8 | 7 | 14 | 34 |
OR
--- Content provided by FirstRanker.com ---
(a) What is the need of Decision tree analysis? [03]
(b) Explain the Kendall’s notation for Queuing models. [04]
(c) A travelling salesman has to visit five cities. He wishes to start from a particular city, visit each city once and then return to his starting point. Suggest him such that his constraint is fulfilled as well as he consumes least cost.The travelling cost of each city from a particular city is given below: [07]
A | B | C | D | E | |
---|---|---|---|---|---|
A | 0 | 2 | 5 | 7 | 1 |
B | 6 | 0 | 3 | 8 | 2 |
C | 8 | 7 | 0 | 4 | 7 |
D | 12 | 4 | 6 | 0 | 5 |
The GAFRIFTFS ARAYKEr BB AY crage INtGRAN FirstRanker.com and the average time to serve coffee per person is Sminutes. Calculate:
(1). Counter utilization level;
--- Content provided by FirstRanker.com ---
(2). Average no. of customers in the including at service system;
(3). Average no. of customers in queue.
Q.4 (a) Discuss the various costs involved in an inventory problems. [03]
(b) Discuss the various costs involved in an inventory problems. [04]
(c) The following information is provided for an item: [07]
--- Content provided by FirstRanker.com ---
Annual usage=12000, Ordering cost=Rs. 60 per order, carrying cost=10%, unit cost of item = Rs. 10, and lead time 10 days.
Find: (1) EOQ, (2) No. of order per year, (3) Average usage if there are 300 working days per year, (4) safety stock if highest usage rate is 70 units per day, (5) R. O. L., (6) Average inventory, (7) Inventory carrying cost per year.
OR
Q.4 (a) Explain the reasons for incorporating dummy activities in a network diagram. In what why do these differ from the normal activities? [03]
(b) Discuss the types of failure in the context of replacement decisions. [04]
--- Content provided by FirstRanker.com ---
(c) Following data gives the average cost of spares per year, overhead cost of maintenance per year and the resale value of certain equipment whose purchase price is Rs. 50,000. [07]
Year(n) | 1 | 2 | 3 | 4 | 5 |
---|---|---|---|---|---|
Cost of spares | 10,000 | 12,000 | 14,000 | 15,000 | 17,000 |
Resale value | 40,000 | 32,000 | 28,000 | 25,000 | 22,000 |
Overhead cost | 5,000 | 5,000 | 6,000 | 6,000 | 8,000 |
Determine the optimal period for replacement.
Q.5 (a) Discuss in brief: (1) total float, (2) free float. Also Explain their uses in network. [03]
(b) Differentiate PERT & CPM. [04]
(c) Find an optimal sequence for the following sequencing problems of four jobs and five machines, when passing is not allowed. Its processing time(in hour) is given below: [07]
--- Content provided by FirstRanker.com ---
Job | Machine | ||||
---|---|---|---|---|---|
M1 | M2 | M3 | M4 | M5 | |
A | 7 | 5 | 2 | 3 | 4 |
B | 6 | 6 | 4 | 5 | 10 |
C | 5 | 4 | 5 | 6 | 8 |
D | 8 | 3 | 3 | 2 | 6 |
OR
Q.5 (a) Determine given terminology from sequencing problems: (1). Number of machines, (2) Idle time on a machine, (3) Total elapsed time. [03]
(b) What is EMV (expected monetary value)? How it is computed to be used a criterion of decision making and when? [04]
(c) For the given activities determine: [07]
(1). Critical path using PERT
--- Content provided by FirstRanker.com ---
(2). Calculate variance and standard deviation for each activity.
(3). Calculate the probability of completing the project in 26 days.
Activity | to | tm | tp |
---|---|---|---|
1-2 | 6 | 9 | 12 |
1-3 | 3 | 4 | 11 |
2-4 | 2 | 5 | 14 |
3-4 | 4 | 6 | 8 |
3-5 | 1 | 1.5 | 5 |
2-6 | 5 | 6 | 7 |
4-6 | 7 | 8 | 15 |
5-6 | 1 | 2 | 3 |
Date: 03/12/2019
Total Marks: 70
--- Content provided by FirstRanker.com ---
This download link is referred from the post: GTU BE/B.Tech 2019 Winter Question Papers || Gujarat Technological University