FirstRanker Logo

FirstRanker.com - FirstRanker's Choice is a hub of Question Papers & Study Materials for B-Tech, B.E, M-Tech, MCA, M.Sc, MBBS, BDS, MBA, B.Sc, Degree, B.Sc Nursing, B-Pharmacy, D-Pharmacy, MD, Medical, Dental, Engineering students. All services of FirstRanker.com are FREE

📱

Get the MBBS Question Bank Android App

Access previous years' papers, solved question papers, notes, and more on the go!

Install From Play Store

Download GTU BE/B.Tech 2019 Winter 7th Sem New 2174002 Construction Planning And Management Question Paper

Download GTU (Gujarat Technological University) BE/BTech (Bachelor of Engineering / Bachelor of Technology) 2019 Winter 7th Sem New 2174002 Construction Planning And Management Previous Question Paper

This post was last modified on 20 February 2020

GTU BE/B.Tech 2019 Winter Question Papers || Gujarat Technological University


FirstRanker.com

Enrolment No.

GUJARAT TECHNOLOGICAL UNIVERSITY

--- Content provided by⁠ FirstRanker.com ---

BE - SEMESTER- VII (New) EXAMINATION — WINTER 2019

Subject Code: 2174002 Date: 26/11/2019

Subject Name: Construction Planning & Management

Time: 10:30 AM TO 01:00 PM Total Marks: 70

Instructions:

--- Content provided by FirstRanker.com ---

  1. Attempt all questions.
  2. Make suitable assumptions wherever necessary.
  3. Figures to the right indicate full marks.
MARKS
Q.1 (a) Explain major problems currently faced by the Construction industry in India. 03
(b) What are the functions of Construction Project Management? 04
(c) Write down the cost associated with site establishment of a construction project. 03
(d) What are the major risks to be addressed at construction site? 04
Q.2 (a) What is the difference between Resource Allocation and Resource Levelling of a project? 03
(b) Total project consist of 8 activities as follows: 04
Activity A B C D E F G H
Duration(weeks) 2 1 4 2 4 6 4 5

The precedence relationships are as follows:

  • A & B can be performed in parallel:
  • --- Content provided by⁠ FirstRanker.com ---

  • C & D cannot start until A is completed.
  • E cannot start until half the work of activity C is complete.
  • F can start only after activity D is complete.
  • G succeeds C
  • H is last activity which should succeed E
  • --- Content provided by‍ FirstRanker.com ---

Prepare a linked bar chart for the project also find out the total time of completion of project.

(c) Draw AON network diagram for the activities given below. Also find event times and various Floats of each activity 07
Activity Duration (days) IPA
A 3 --
B 10 A
C 7 A
D 6 B
E 5 B,C
F 4 C
G 2 D
H 4 D,E
I 10 E
J 6 E,F
K 4 G,H,I
L 2 H,I
M 1 J,L

FirstRanker.com

Activity Duration (days) IPA Cost (Rs.)
A 2 - 2000
B 7 A 5000
C 10 A 7000
D 5 A 6000
E 4 B 8000
F 4 B,C 3000
G 3 C 2000
H 6 C,D 6000
I 3 D 5500
J 6 E,F,G 8000
K 8 F,G,H 7000
L 5 H,I 10000
M 3 K,L 9000
Q.3 (a) Enlist the different levels of Work Breakdown Structure. 03
(b) Draw Work Breakdown Structure for a ‘Township Planning and Construction’. 04
(c) Draw AOA network diagram for the following activities. 07
Activity IPA Activity IPA
A - H C,D
B A I D
C A J E,F,G
D A K F,G,H
E B L H,I
F B,C M K,L
G C

OR

Q.3 (a) What do you mean by Dummy activity? When it is used? 03
(b) Draw Work Breakdown Structure for a ‘Construction of a Culvert’. 04
(c) A network is given below, for a project. At the end of 10 days, following information are available from site on the project status. Draw an updated network diagram using status report: 07
  • Activity D takes 6 days to finish.
  • Activity F takes 5 more days to complete.
  • --- Content provided by FirstRanker.com ---

  • It is expected that it will take total 15 days to finish activity B.
  • Activity H cannot start until day 17 because of the delay of material.

FirstRanker.com

Q4

(a) The time estimates for three activities A,B and C are as follows: 03
Optimistic Time Most Likely Time Pessimistic Time
A 10 12 14
B 6 8 12
C 5 10 12

Determine expected time and variance for each activity. Which activity has more reliable time estimates?

--- Content provided by​ FirstRanker.com ---

(b) Enumerate the steps taken in scheduling with LOB and how it is advantageous in construction field? Explain briefly. 04
(c) For the project data given in Q.2 (c) (or) calculate cash out flow requirement for first 20 days if the project is scheduled based on Late Finish of activities. (LF Schedule) 07

OR

Q4 (a) How % project progress, % cost overrun and % time overrun are calculated using variance analysis? 03
(b) Explain the term ‘Slack’. What is the meaning of Positive Slack, Zero Slack and Negative Slack. 04
(c) For the project data given in Q.2 (c) (or) calculate cash out flow requirement for first 20 days if the project is scheduled based on early start of activities. (ES Schedule) 07
Q.5 (a) Explain the method of time-cost optimization of project network. 03
(b) A small building construction of 10 units involves 5 operations (A, B, C, D and E) in series with duration and other resource requirements are as given below. Using Line of Balance (LOB) concept, schedule the project. Use a minimum buffer of 1 week between operations. 04
Operations Duration (Weeks) Labour (No. of gangs) Operations Duration (Weeks) Labour (No. of gangs)
A 2 2 D 4 3
B 3 E 2 2
C 1 1
(c) A construction company has an opportunity to submit a bid for a new apartment building. From the specification provided by the developer the PERT network with the three time estimates (in weeks) for each activity are shown in figure. 07

Determine:

  1. Critical path and its standard deviation.
  2. Probability of completing the work in 38 weeks.

FirstRanker.com

--- Content provided by⁠ FirstRanker.com ---

completion time duration for which the company should bid to provide 95% the project.

OR

Q.5 (a) Draw Precedence diagram for the following activities. Also find critical path and project completion time. 03
Activity Duration (days) IPA Relation type Lag
A 3 - -
B 5 A SS 3
C 2 A FS -
D 6 B FF --
C FS -
(b) Figure shows the network for a project, the data for the duration and cost of each activity are given in the table. Normal time and crash time (bracket) are also mentioned in the diagram. 04
Activity Normal duration (in weeks) Normal cost (Rs.) Crash duration (in weeks) Crash cost (Rs.)
1-2 6 7000 3 14500
1-3 8 4000 5 8500
2-3 4 6000 1 9000
2-4 5 8000 3 15000
3-4 5 5000 3 11000

The direct cost of the project is Rs. 3000 per week. Determine the optimum duration of the project and corresponding minimum cost.

(c) Figure shows the network for a construction project, with the three time estimates of each activity marked. Determine, 07
  1. Critical path and its standard deviation.
  2. Probability of completion of the project in 40 days.
  3. --- Content provided by​ FirstRanker.com ---

  4. The duration that will provide 95% probability of its completion in time.

FirstRanker.com

Normal Distribution Function

Normal Deviate Probability (%) Normal Deviate Probability (%)
0 50.0 0 50.0
- 0.1 46.0 + 0.1 54.0
- 0.2 42.1 + 0.2 57.9
- 0.3 38.2 + 0.3 61.8
- 0.4 34.5 + 0.4 65.5
- 0.5 30.8 + 0.5 69.2
- 0.6 27.4 + 0.6 72.6
- 0.7 24.2 + 0.7 75.5
- 0.8 21.2 + 0.8 78.8
- 0.9 18.4 + 0.9 81.6
- 1.0 15.9 + 1.0 84.1
- 1.1 13.6 + 1.1 86.4
- 1.2 11.5 + 1.2 88.5
- 1.3 9.7 + 1.3 90.3
- 1.4 8.1 + 1.4 91.3
- 1.5 6.7 + 1.5 93.3
- 1.6 5.5 + 1.6 94.5
- 1.7 4.5 + 1.7 95.5
- 1.8 3.6 + 1.8 96.4
- 1.9 2.9 + 1.9 97.1
- 2.0 2.3 + 2.0 97.7
- 2.1 1.8 + 2.1 98.2
- 2.2 1.4 + 2.2 98.6
- 2.3 1.1 + 2.3 98.9
- 2.4 0.8 + 2.4 99.2
- 2.5 0.6 + 2.5 99.4
- 2.6 0.5 + 2.6 99.5
- 2.7 0.3 + 2.7 99.7
- 2.8 0.3 + 2.8 99.7
- 2.9 0.2 + 2.9 99.8
- 3.0 0.1 + 3.0 99.9

Fkkkthdhh bt

FirstRanker.com

--- Content provided by‍ FirstRanker.com ---



This download link is referred from the post: GTU BE/B.Tech 2019 Winter Question Papers || Gujarat Technological University

--- Content provided by FirstRanker.com ---