- (a) Briefly explain the concept of project management [03]
--- Content provided by FirstRanker.com ---
(b) What is “ project” ? Explain project “S” curve [04]
(c) Explain EPC and BOOT contracts with suitable examples [07] - (a) List out various types of projects and explain any one type. [03]
(b) Explain work break down structure (WBS). [04]
(c) Explain project management functions in detail. [07]--- Content provided by FirstRanker.com ---
OR
(c) Explain interpersonal influence and standard communication process in detail. [07] - (a) Explain the concept of project cost. [03]
(b) Briefly explain any one type of software used for project management. [04]
(c) Explain PERT and CPM techniques in detail [07]--- Content provided by FirstRanker.com ---
OR
(a) What do you mean by control valve sizing? Briefly explain it. [03]
(b) Describe the specifications of an industrial control valve. [04]
(c) Explain project engineering documents'and drawings in detail [07] - (a) What do you mean by intrinsic safety? [03]
--- Content provided by FirstRanker.com ---
(b) Explain the selection criteria for control valve. [04]
(c) Draw and explain the characteristics of control valve in detail. [07]
OR
(a) What is the meaning of erection and commissioning of plant? [03]
(b) Briefly explain the elements of closed loop control system in the plant. [04]--- Content provided by FirstRanker.com ---
(c) Explain plant start up procedure in detail. [07] - (a) Explain selection criteria for pressure instruments [03]
(b) What is loop check? Explain it with example. [04]
(c) What is ISO? Explain ISO 9000 for quality systems [07]
OR--- Content provided by FirstRanker.com ---
(a) Explain selection criteria for flow instruments [03]
(b) Explain installation of rota meter and orifice. [04]
(c) Explain the quality management practices worldwide and also explain the concept of certifying agencies. [07]