Download GTU BE/B.Tech 2019 Summer 6th Sem New 2163201 Operation Research Question Paper

Download GTU (Gujarat Technological University) BE/BTech (Bachelor of Engineering / Bachelor of Technology) 2019 Summer 6th Sem New 2163201 Operation Research Previous Question Paper

This post was last modified on 20 February 2020

GTU BE 2019 Summer Question Papers || Gujarat Technological University


FirstRanker.com

GUJARAT TECHNOLOGICAL UNIVERSITY

SEMESTER-VI(NEW) — EXAMINATION - SUMMER 2019

--- Content provided by‍ FirstRanker.com ---

Subject Code:2163201 Date:10/05/2019

Subject Name:Operation Research

Time:10:30 AM TO 01:00 PM Total Marks: 70

Instructions:

  1. Attempt all questions.
  2. --- Content provided by FirstRanker.com ---

  3. Make suitable assumptions wherever necessary.
  4. Figures to the right indicate full marks.

MARKS

Q.1 (a) Discuss the advantages of Model Building in Operations research. 03

(b) Use simplex method to maximize z = 4x; + 3x,

--- Content provided by‌ FirstRanker.com ---

Subject to constraints

2xq + x5, <1000, x; +x, <800, x; <400, x, £700,x4,x, =0 04

(¢) What are the features of Operations research approach? Discuss in brief. 07

Q.2 (a) Solve the following LPP graphically 03

Minimize Z = 600x + 400y

--- Content provided by​ FirstRanker.com ---

Subject to 3x + 3y > 40,3x +y = 40,2x + 5y = 44,x,y = 0

(b) Explain the primal — dual relationship. 04

(¢) Maximize Z = 2x, + 3x, + 4x3 07

Subject to constraints

3x; +x, + 4x5 < 600, 2x; + 4x, + 2x5 > 480,

--- Content provided by​ FirstRanker.com ---

2x1 + 3x, + 3x3 = 540,%1,%x,,x3 =0

OR

(¢) Use Two phase method to solve the following LPP 07

Minimize z = x1 + x5

Subject to the constraints

--- Content provided by FirstRanker.com ---

ZX1+XZ24, X1+7XZ27, xl,xZZO

Q.3 (a) Give an algorithm for solving a transportation problem. 03

(b) Solve the following Assignment problem 04

I 1I 111 v Vv
A 10 5 13 15 16
B 3 9 18 13 6
C 10 7 2 2 2
D 7 11 9 7 12
E 7 9 10 4 12

(¢) Solve the transportation problem (find initial basic solution with VAM and 07

Optimal Solution using MODI method)

--- Content provided by⁠ FirstRanker.com ---

To D1 D2 D3 D4 Supply

From

S1 19 30 50 10 7

S2 70 30 40 60

S3 40 8 70 20 18

--- Content provided by‍ FirstRanker.com ---

Demand 5 8 7 14

OR

Q.3 (a) How would you solve the assignment problem where the objective 03

function is of maximization type?

(b) Explain Degeneracy in Transportation problem and its resolution. 04

--- Content provided by⁠ FirstRanker.com ---

(¢) A manufacturer wants to ship 22 loads of his product as shown below. 07

FirstRanker.com

D1 D

S1 5 6 3

S2 4 6 5 5

--- Content provided by FirstRanker.com ---

S3 8 9 6 4

Demand | 4 4 8

The shipping cost is Rs. 10 per load per km. What shipping schedule

should be used in order to minimize the total transportation cost?

[Use VAM to find the initial basic feasible solution and MODI method

--- Content provided by‍ FirstRanker.com ---

for Optimal solution]

Q4 (a) Draw the network diagram for following 03

Activity | A B C D E F G

Pre. - A A B B,C |E D,F

(b) What is critical activity in network diagram? What is the importance of 04

--- Content provided by FirstRanker.com ---

critical path in any project?

(c) Information on the activities required for a project is as follows: 07

Activity | A B (¢ D E F G H 1 J K

Name

Activity | 1-2 | 1-3 | 14 |2-5 [3-5 [3-6 | 3-7 |4-6 | 5-7 | 6-8 | 7-8

--- Content provided by⁠ FirstRanker.com ---

Node

Duration | 2 7 8 3 6 10 |4 6 2 5 6

(Days)

Find total float, free float and independent float for each activity.

OR

--- Content provided by⁠ FirstRanker.com ---

Q.5 (a) Define Reneging, Balking and Jockeying in Queuing System. 03

(b) A TV repairman finds that the time spent on his job has an exponential 04

distribution with a mean of 30 minutes. If he repairs the sets in order in

which they came in, and if the arrival rate of sets follows a poisson

distribution with an average rate of 10 per/8-hour a day, what is the

--- Content provided by‌ FirstRanker.com ---

repairman’s expected idle time each day? Find the expected number of

TV sets in the system.

(c) The data on the running costs per year.and resale price of equipment A, 07

whose price is Rs. 2,00,000 are as follows.

Year 1 2 3 4 5 6 7
Running cost 30000 38000 46000 58000 72000 90000 110000
Resale value 100000 50000 25000 12000 8000 8000 8000

What is the optimum period of replacement?

--- Content provided by FirstRanker.com ---

OR

Q.5 (a) Define Simulation. Enlist the types of simulation. 03

(b) Explain the Group replacement policy versus Individual replacement 04

policy.

(c) A company trading in motor vehicle spare parts wishes to determine the 07

--- Content provided by‍ FirstRanker.com ---

levels of stock it should carry for the items in its range. The demand is not

certain and there is a lead time for stock replenishment. For an item A,

the following information is obtained;

Demand (units/day 3 4 5 6 7
Probability 0.1 0.2 0.3 0.3 0.1

Carrying cost: Rs. 2 /unit/ day

Ordering cost: Rs. 50/ oder

--- Content provided by⁠ FirstRanker.com ---

Lead time for replenishment: 3 days

Stock on hand at the beginning of simulation process was 20 units

Carry out the simulation over a period of 10 days with the objective of

evaluating the inventory rule: Oder 15 units when present inventory plus

any outstanding oder falls below 15 units.

--- Content provided by​ FirstRanker.com ---

Random number: 0,9,1,1,5,1,8,6,3,5

Your calculation should include the total cost of operating inventory rule

for 10 days.

Q4 (a) What is Random number? 03

(b) What are the advantages of Simulation? 04

--- Content provided by FirstRanker.com ---

(c) The following mortality rates have been observed for certain type of fuse: 07

Week 1 2 3 4 5
% failing by the end of week 5 15 35 57 100

There are 1000 fuses in use and it costs Rs. 5 to replace an individual

fuse. If all fuses were replaced simultaneously it would cost Rs. 1.25 per

fuse. What is the optimal replacement plan?

FirstRanker.com

--- Content provided by⁠ FirstRanker.com ---



This download link is referred from the post: GTU BE 2019 Summer Question Papers || Gujarat Technological University

--- Content provided by‌ FirstRanker.com ---