FirstRanker Logo

FirstRanker.com - FirstRanker's Choice is a hub of Question Papers & Study Materials for B-Tech, B.E, M-Tech, MCA, M.Sc, MBBS, BDS, MBA, B.Sc, Degree, B.Sc Nursing, B-Pharmacy, D-Pharmacy, MD, Medical, Dental, Engineering students. All services of FirstRanker.com are FREE

📱

Get the MBBS Question Bank Android App

Access previous years' papers, solved question papers, notes, and more on the go!

Install From Play Store

Download GTU BE/B.Tech 2019 Summer 8th Sem New 2180901 Testing And Commissioning Of Electrical Equipments Question Paper

Download GTU (Gujarat Technological University) BE/BTech (Bachelor of Engineering / Bachelor of Technology) 2019 Summer 8th Sem New 2180901 Testing And Commissioning Of Electrical Equipments Previous Question Paper

This post was last modified on 20 February 2020

GTU BE 2019 Summer Question Papers || Gujarat Technological University


FirstRanker.com

A Firstranker's choice

Instructions:

--- Content provided by⁠ FirstRanker.com ---

  1. Attempt all questions.
  2. Make suitable assumptions wherever necessary.
  3. Figures to the right indicate full marks.

GUJARAT TECHNOLOGICAL UNIVERSITY
BE - SEMESTER-VIII(NEW) EXAMINATION - SUMMER 2019

--- Content provided by⁠ FirstRanker.com ---

Subject Code:2180901
Subject Name:Testing and Commissioning of Electrical Equipments
Time:10:30 AM TO 01:00 PM
Date:17/05/2019
Total Marks: 70

--- Content provided by​ FirstRanker.com ---

Q.1 (a) List the factor affecting earth resistance. MARKS 03

(b) List the methods of slip measurement in induction motor. Briefly explain slip measurement by rotor frequency. MARKS 04

(c) For below listed troubles in power transformer, state its causes and remedies: 1) Internal short circuit 2) Overheating 3) Rapid deterioration of oil MARKS 07

Q.2 (a) State the purpose of the following tests: Type tests, Routine tests, Special tests, Development tests MARKS 03

(b) Before installation of the machine what general checkups needs to be performed? MARKS 04

--- Content provided by‌ FirstRanker.com ---

(c) List various methods of neutral grounding. Explain in detail the method of solid grounding with its merits and demerits. MARKS 07

OR

(c) List various methods for earth resistance measurement. Explain fall of potential method for measurement of earth resistance. MARKS 07

Q.3 (a) What is polarization index? What is its significance? MARKS 03

(b) Explain the drying out procedure of power transformer with necessary graph. MARKS 04

--- Content provided by‍ FirstRanker.com ---

(c) State the purpose of high voltage testing of power transformer. Describe test set up for impulse testing of power transformer. MARKS 07

OR

(c) Explain the polarity of windings. MARKS 07

Q.4 (a) What are the causes of low value of insulation resistance in the power transformer? How insulation resistance can be brought to required level? MARKS 03

(b) Draw DY1 & DY11 type transformer connections & state feasibility of connecting them in parallel with reason. MARKS 04

--- Content provided by​ FirstRanker.com ---

(c) Explain the cause of noise produced by the rotating machine. MARKS 07

Q.5 (a) For the following troubles with slip ring induction motor, state its possible causes: 1) Motor runs slow 2) Motor fails to start MARKS 03

(b) Explain the no load test and blocked rotor test of an induction motor. What data such test provides? MARKS 04

OR

(b) Enlist different tests to be performed on busbar. MARKS 04

--- Content provided by‌ FirstRanker.com ---

(c) Explain any one test to be performed on three phase synchronous machine to find out its synchronous impedance. MARKS 07

Q.5 (a) Define the making and breaking rating of the circuit breaker. MARKS 03

(b) Explain mechanical endurance test on circuit breaker. MARKS 04

(c) Explain the working of ELCB? What are the different tests performed on it? MARKS 07

OR

--- Content provided by‌ FirstRanker.com ---

Q.5 (a) Discuss the need for gas insulated substation. MARKS 03

(b) Discuss different cooling system of rotating electrical machines in brief. MARKS 04

(c) Explain Murray loop test for ground fault location in underground cable. MARKS 07

(c) What is degree of protection? How it is designated? What is IP and IC code? MARKS 07


--- Content provided by FirstRanker.com ---