Download GTU BE/B.Tech 2018 Winter 6th Sem New 2160601 Advanced Construction And Equipments Question Paper

Download GTU (Gujarat Technological University) BE/BTech (Bachelor of Engineering / Bachelor of Technology) 2018 Winter 6th Sem New 2160601 Advanced Construction And Equipments Previous Question Paper

www.FirstRanker.com
1
Seat No.: ________ Enrolment No.___________

GUJARAT TECHNOLOGICAL UNIVERSITY

BE - SEMESTER ?VI (NEW) EXAMINATION ? WINTER 2018
Subject Code:2160601 Date:16/11/2018

Subject Name:Advanced Construction and Equipments

Time: 02:30 PM TO 05:00 PM Total Marks: 70

Instructions:

1. Attempt all questions.

2. Make suitable assumptions wherever necessary.

3. Figures to the right indicate full marks.

MARKS

Q.1 (a) Enlist the different type of cast in situ pile. Explain Simplex
pile in detail
03
(b) Discuss the different causes of failure of piles.

04
(c) What is a cassion? Explain with sketch well type of cassion. 07

Q.2 (a) Define the term with sketches 1) Stop- end pipe 2) Guide
wall
03
(b) Explain vibro flotation a ground water control technique. 04
(c) What is coffer dam? Enlist the different type of coffer dam
and explain any one with sketch.
07
OR
(c) Write a short note on ?Diaphragm wall construction. 07
Q.3 (a) Define the term 1) Rim pull 2) Draw bar pull 3) Gradability 03
(b) What is owning and operating cost of equipment 04
(c) What is formwork? Discuss the formwork of RCC Beam
and wall with neat sketches.
07
OR
Q.3 (a) What is a tall structure? 03
(b) Where the slip form work can be used? Explain with neat
sketch.
04
(c) Enlist various methods of demolition and explain any two in
detail.
07
Q.4 (a) Differentiate between Precast pile Vs Cast in situ pile. 03
(b) Why Bulldozer is an versatile equipment? Explain with
reason.
04
(c) Enlist the different Excavating equipment. Explain with
sketches of Power shovel.
07
OR
Q.4 (a) Define the term 1) Depreciation 2) Scrape value 3)
Obsolesce
03
(b) Discuss the causes of failure of false work. 04
(c) Write a short note on Tunnel Boring Machine. 07
Q.5 (a) Define: (1) Pile Shoe (2) Down time cost (3) Owing cost 03
(b) Write the importance of Air compressor. 04
(c) Calculate the depreciation for each year by Straight line
method for the Back hoe loader having purchase cost of Rs
26,00,000/- and scrap value at the end of useful life of five
years equal to 10% of its original purchase price
07
OR

www.FirstRanker.com www.FirstRanker.com
www.FirstRanker.com
FirstRanker.com - FirstRanker's Choice
www.FirstRanker.com
1
Seat No.: ________ Enrolment No.___________

GUJARAT TECHNOLOGICAL UNIVERSITY

BE - SEMESTER ?VI (NEW) EXAMINATION ? WINTER 2018
Subject Code:2160601 Date:16/11/2018

Subject Name:Advanced Construction and Equipments

Time: 02:30 PM TO 05:00 PM Total Marks: 70

Instructions:

1. Attempt all questions.

2. Make suitable assumptions wherever necessary.

3. Figures to the right indicate full marks.

MARKS

Q.1 (a) Enlist the different type of cast in situ pile. Explain Simplex
pile in detail
03
(b) Discuss the different causes of failure of piles.

04
(c) What is a cassion? Explain with sketch well type of cassion. 07

Q.2 (a) Define the term with sketches 1) Stop- end pipe 2) Guide
wall
03
(b) Explain vibro flotation a ground water control technique. 04
(c) What is coffer dam? Enlist the different type of coffer dam
and explain any one with sketch.
07
OR
(c) Write a short note on ?Diaphragm wall construction. 07
Q.3 (a) Define the term 1) Rim pull 2) Draw bar pull 3) Gradability 03
(b) What is owning and operating cost of equipment 04
(c) What is formwork? Discuss the formwork of RCC Beam
and wall with neat sketches.
07
OR
Q.3 (a) What is a tall structure? 03
(b) Where the slip form work can be used? Explain with neat
sketch.
04
(c) Enlist various methods of demolition and explain any two in
detail.
07
Q.4 (a) Differentiate between Precast pile Vs Cast in situ pile. 03
(b) Why Bulldozer is an versatile equipment? Explain with
reason.
04
(c) Enlist the different Excavating equipment. Explain with
sketches of Power shovel.
07
OR
Q.4 (a) Define the term 1) Depreciation 2) Scrape value 3)
Obsolesce
03
(b) Discuss the causes of failure of false work. 04
(c) Write a short note on Tunnel Boring Machine. 07
Q.5 (a) Define: (1) Pile Shoe (2) Down time cost (3) Owing cost 03
(b) Write the importance of Air compressor. 04
(c) Calculate the depreciation for each year by Straight line
method for the Back hoe loader having purchase cost of Rs
26,00,000/- and scrap value at the end of useful life of five
years equal to 10% of its original purchase price
07
OR

www.FirstRanker.com www.FirstRanker.com
www.FirstRanker.com
www.FirstRanker.com
2
Q.5 (a) Write advantages and disadvantages of Trenching machine. 03
(b) Draw a neat sketches of different component of Concrete
Batching plant.
04
(c) Enlist the different type of lifting equipment. Explain with
sketches of Tower Crane.
07

*************