GUJARAT TECHNOLOGICAL UNIVERSITY
BE - SEMESTER-VII (NEW) EXAMINATION - WINTER 2018
Subject Code: 2170901 Date: 26/11/2018
Subject Name: Inter Connected Power System
Time: 10:30 AM TO 01:00 PM Total Marks: 70
--- Content provided by FirstRanker.com ---
Instructions:
- Attempt all questions.
- Make suitable assumptions wherever necessary.
- Figures to the right indicate full marks.
Q.1 (a) What is the importance of interconnected power system? 03
--- Content provided by FirstRanker.com ---
(b) Explain Cascade Tripping. 04(c) Discuss Zbus building algorithm. Explain all types of modifications when transmission lines are added between the buses. 07
Q.2 (a) Give reasons: Bus admittance matrix is a sparse Matrix. 03
(b) Explain the following. 04
1) Bus Incidence matrix
--- Content provided by FirstRanker.com ---
2) Primitive network(c) The fuel cost of two unit plants are given by 07
C1 =100 + 2P1 +0.005 P1^2
C2 =200 + 2P2 + 0.01 P2^2 where P1 and P2 in MW. The plant supplies a load of 450 MW. Find economic load scheduling of two unit and find incremental fuel cost, neglecting losses:
OR
--- Content provided by FirstRanker.com ---
(c) A constant load of 300 MW is supplied by two 200 MW generators 1 and 2, for which the respective incremental fuel cost are 07
dC1/dPG1=0.1 PG1+ 20
dC2/dPG2=0.12 PG2 +15
With Power Pg in MW and cost C in Rs/hr. Determine
1) The most economical division of the load between the generators and
--- Content provided by FirstRanker.com ---
2) The saving in Rs/day thereby obtained compared to equal sharing between the machines.Q.3 (a) Explain Properties of Y- bus matrix. 03
(b) Write a Short Note on Unit Commitment. 04
(c) State the assumptions made for load flow studies and applications of load flow studies. 07
OR
--- Content provided by FirstRanker.com ---
Q.3 (a) Explain the main features of Load Dispatch centre. 03
(b) Define following : 04
1) Steady-state stability
2) Transient stability
(c) Explain GS method with the help of flowchart. 07
--- Content provided by FirstRanker.com ---
Q.4 (a) What is critical clearing angle? 03
(b) Explain Incremental fuel cost and penalty factor with its equation. 04
(c) State the methods of Load frequency control and explain bias tie line frequency control. 07
--- Content provided by FirstRanker.com ---
OR
Q.4 (a) What is primitive network? 03
(b) Draw the block diagram of AGC. 04
(c) Describe the methods of voltage control adopted for large size power system in detail. 07
Q.5 (a) What are the advantages of FDLF method over NR method? 03
--- Content provided by FirstRanker.com ---
(b) Explain Power angle curve. 04(c) A 100 MVA, 2 pole, 60 Hz generator has a moment of inertia 50 x 10^3 kg. m^2. 1) What is energy stored in the rotor at rated speed? 2) What is the corresponding angular momentum? 3) Determine the inertia constant H. 07
OR
Q.5 (a) Classify various types of buses in power system for load flow analysis. 03
(b) Explain Equal area criteria of stability. 04
--- Content provided by FirstRanker.com ---
(c) Discuss in brief the methods for improving transient stability. 07--- Content provided by FirstRanker.com ---