Download GTU BE/B.Tech 2018 Winter 7th Sem New 2171501 Operations Planning And Control Question Paper

Download GTU (Gujarat Technological University) BE/BTech (Bachelor of Engineering / Bachelor of Technology) 2018 Winter 7th Sem New 2171501 Operations Planning And Control Previous Question Paper

This post was last modified on 20 February 2020

GTU BE/B.Tech 2018 Winter Question Papers || Gujarat Technological University


FirstRanker.com

Subject Code: 2171501

Subject Name: Operations Planning & Control

--- Content provided by‌ FirstRanker.com ---

FirstRanker.com

GUJARAT TECHNOLOGICAL UNIVERSITY

BE - SEMESTER-VII (NEW) EXAMINATION - WINTER 2018

Time: 10:30 AM TO 01:00 PM

Date: 15/11/2018

--- Content provided by FirstRanker.com ---

Instructions:

  1. Attempt all questions.
  2. Make suitable assumptions wherever necessary.
  3. Figures to the right indicate full marks.
Q.1 (a) What is Process planning? 03
(b) Explain Index method of scheduling. 04
(c) What are the conditions under which you apply Johnson’s rule for finding Optimal Sequence of operations? 07
OR
(a) What is scheduling? 03
(b) Discuss Economic Manufacturing Quantity. 04
(c) Discuss Production planning v/s Project planning. 07
Q.2 (a) Discuss MRP and its four fundamental inputs. 03
OR
(b) Discuss a composite production system. 04
(c) Short note on: Line of balance technique. 07
Q.3 (a) The sequence of manufacturing a product is as follows; Find out minimum no. of work stations and line efficiency: 03
(b) Explain scope of scheduling with example. 04
(c) Explain method of regression-analysis. 07
OR
(a) Discuss aggregate planning: Justify use of mixed strategy. 03
(b) Classify sales forecasting techniques. 04
(c) Discuss Master Production Scheduling. 07
Q.4 (a) Discuss how PPC function is carried out in Job Production, Batch Production and Continuous production. 03
(b) What is ‘Break even analysis’? 04
(c) Discuss usefulness and limitations of ‘Break even analysis’ 07
OR
(a) Use Johnson’s rule to find out the best sequence and find total idle time from the following data : 03
Operation A B C D E G H
Time (In Min.) 3 7 8 4 23
Job 1 3 4 5 6
Milling M/c 1 4 2 2 4
Drilling M/c 3 5 2 7
Q.5 (a) What is dispatching? 03
(b) Explain the procedure of decentralizing dispatching system. 04
(c) Discuss Route sheet preparation with an example. 07
OR
(b) Discuss forecasting for a new product being launched, with an example. 04
(c) Define OPC function in an organization. Discuss different phases of PPC. 07

Total Marks: 70