Download GTU BE/B.Tech 2018 Winter 7th Sem New 2174002 Construction Planning And Management Question Paper

Download GTU (Gujarat Technological University) BE/BTech (Bachelor of Engineering / Bachelor of Technology) 2018 Winter 7th Sem New 2174002 Construction Planning And Management Previous Question Paper

This post was last modified on 20 February 2020

GTU BE/B.Tech 2018 Winter Question Papers || Gujarat Technological University


FirstRanker.com

Seat No.: Enrolment No.

GUJARAT TECHNOLOGICAL UNIVERSITY

--- Content provided by‌ FirstRanker.com ---

BE - SEMESTER-VII (NEW) EXAMINATION - WINTER 2018

Subject Code: 2174002 Date: 19/11/2018

Subject Name: Construction Planning & Management

Time: 10:30 AM TO 01:00 PM Total Marks: 70

Instructions:

--- Content provided by⁠ FirstRanker.com ---

  1. Attempt all questions.
  2. Make suitable assumptions wherever necessary.
  3. Figures to the right indicate full marks.

MARKS

Q.1 (a) Differentiate between logical dummy and numbering dummy in a CPM network with suitable example. 03

--- Content provided by​ FirstRanker.com ---

(b) Activity i and j (duration di and dj) are having following logical relationships: Start to Start, Start to Finish, Finish to Finish. Derive equations for calculating event times of Activities i & J. ) 04

(c) Draw a CPM-AOA network for following project data and find out the floats available for all the activities 07

Activity IPA Duration (weeks) Activity IPA Duration (weeks)
A - 4 G D 6
B - 6 H C,G 4
C A 5 I D 7
D A 6 J H,F,I 3
E A 5 K I 5
F E 3 L K 3

Draw the linked bar chart for the project data also.

Q.2 (a) Briefly explain the situations where a numbering dummy is included in a CPM-AOA network. Support your explanation with a network sketch. 02

(b) Draw the CPM-AON diagram and calculate the critical, total floats and free floats for the schedule shown below. 05

--- Content provided by⁠ FirstRanker.com ---

Activity IPA Duration (weeks) Activity IPA Duration (weeks)
A - 2 H D 9
B A 7 I F,G 12
C A 10 J F 5
D A 4 K E,J 5
E B 6 L G,H 6
F B,C 5 M F,H 4
G C,D 8 N L,K,M 3

FirstRanker.com

(c) Draw a Late Start (LS) based resource histogram for the project data given in Q.1 (c) with following resource requirements 07

Activity Total Resources (No) Activity Total Resources (No)
A 16 G 18
B 12 H 8
C 25 I 49
D 20 J 6
E 5 K 20
F 9 L 6

OR

(c) Draw the AON diagram and perform the CPM network computations (including floats) for the schedule shown next. 07

Activity IPA Duration (weeks)
A - 2
B - 6
C A 3
D B 1
E B 4
F C,D 8
G C,D 2
H E 11
I F,G,H 4

Q.3 (a) The expected completion time for a project is 32 months with a variance of 7.6 months. What is the probability that project will be completed in 30 months. 03

--- Content provided by⁠ FirstRanker.com ---

(b) Perform the forward and backward pass for the network shown below and calculate the activity times (ES, EF, LS & LF) 04

(c) A contractor agreed to build 30 dog houses in 90 days at a price of Rs. 8000 per unit. Twenty days later, the contractor has finished 8 dog houses with an actual total cost (that includes his overhead and profit) of Rs. 68000. What is the status of the project? 07

OR

Q.3 (a) Draw LOB Planning Diagram for following situations 03

Activity B is faster than Activity A

--- Content provided by⁠ FirstRanker.com ---

FirstRanker.com

Activity D is faster than Activity C but both are to be completed together

(b) Briefly explain Work Break Down Structure and its use in project management. Use sketch to explain different hierarchy in WBS 04

(c) In Q. 2 (c), 10 days after the project has started, you receive the following report: 07

Activities A and D are complete, actual dates: A (0, 2), D (5, 9).

--- Content provided by⁠ FirstRanker.com ---

Activity B started on day 5. Remaining duration: 2 days.

Activity C started on day 2. Some problems were encountered. Remaining duration 4 days.

The duration for activity F was adjusted to 8 days.

Activity J has been canceled.

The duration for new activity P is 4 days. New logical relations: New IPA: E and F. Immediately succeeding activity) is K.

--- Content provided by FirstRanker.com ---

Update the network diagram.

Q.4 (a) Briefly explain how direct cost and indirect cost of a project vary with project completion time. How activities are prioritized/selected for crashing? 03

(b) Draw the network for the following project. 04

Activity IPA Duration (Days)
Optimistic (To) Most Likely (Tm) Pessimistic (Tp)
A - 4 5 6
B A 10 12 14
C A 7 9 16
D B 14 17 22
E B,C 10 15 30
F C 4 7 13
G D 12 20 40
H D,E 10 12 15
I F,H 8 9 10

Compare the three paths: ABDHI, ABDG, and ABEHI. Calculate the Expected Duration and Standard Deviation for each path. Considering all three paths, what is the duration of the project with at least 95% confidence? 07

(c) Perform the forward and backward passes on the precedence network shown in Figure below. 07

--- Content provided by‍ FirstRanker.com ---

FirstRanker.com

OR

Q.4 (a) Draw the status bar chart (linked) of the above project data (Q.4b) at the end of 12 weeks.

Activity A, B, C are completed, C is 50% completed. 03

Q.5 (b) Activity details of a construction project are given below. Complete the following scheduling tasks: 04

--- Content provided by‌ FirstRanker.com ---

Activity IPA Duration (Weeks) Cost (Rs)
A - 5 4000
B - 7 20000
C A 3 6000
D A 10 10000
E B 4 9000
F B 5 8000
G C,D 6 6000
H E,F 2 10000

Calculate the cash flow requirement for first 10 weeks if the project is scheduled as per early start of activities (ES Schedule). 07

(a) Following data is available for a project. Find out the expected completion time of the project along with its standard deviation. What is the probability that the project will be completed in 19 months? 04

Activity (i-j) Expected Time (months) Variance
1-2 4 2
1-3 6 2
2-4 5 9
3-4 7 7
2-5 9 10
4-6 10 1
5-6 8 0

(b) How resource leveling is different from resource allocation? 03

(c) Enlist the steps/rules involved in the resource smoothening/leveling process in project planning/scheduling. 04

A real estate villa project of 15 houses involves 7 operations (A, B, C, D, E, F, G) in series with duration and other resource requirements are as given below. Using Line of Balance (LOB) concept, schedule the project. Use a minimum buffer of 0.5 weeks between operations. 07

--- Content provided by‍ FirstRanker.com ---

Operation Duration for one house (Weeks) Labor Required (Number of Gangs)
A 2 1
B 5 2
C 4 1
D 1 2
E 6 4
F 4 1
G 2 2

FirstRanker.com

OR

FirstRanker.com

Q.5 (a) State the suitability of Line of Balance (LOB} method as a construction project scheduling tool. 03

(b) A 10 story building construction involves 4 operations (A, B, C, D) in series with duration and other resource requirements are as given below. Using Line of Balance (LOB) concept, schedule the project. 04

--- Content provided by‍ FirstRanker.com ---

Operation Duration (Weeks) Labour Required (Number of Gangs)
A 4 2
B 3 3
C 6 4
D 2 2

(c) Calculate the normal, least-cost, and crash durations for the following project‘. Calculate the cost associated with each duration. Indirect (overhead) costs are Rs.120 per day. 07

Activity IPA Duration (Days) Cost (Rs.)
Normal Crash Normal Crash
A - 5 4 500 600
B A 7 5 350 500
C A 8 5 800 920
D A 11 7 1200 1400
E C 6 4 600 700
F C 4 4 500 500
G D,F 7 5 700 1000
H E,F 6 5 300 420

FirstRanker.com

FirstRanker.com

Normal Distribution Function

Normal Deviate (-) Probability (%) Normal Deviate (+) Probability (%)
0 50.0 0 50.0
-0.1 46.0 + 0.1 54.0
-0.2 42.1 + 0.2 57.9
-0.3 38.2 + 0.3 61.8
-0.4 34.5 + 0.4 65.5
-0.5 30.8 + 0.5 69.2
-0.6 27.4 + 0.6 72.6
-0.7 24.2 + 0.7 75.5
-0.8 21.2 + 0.8 78.8
-0.9 18.4 + 0.9 81.6
-1.0 15.9 + 1.0 84.1
-1.1 13.6 + 1.1 86.4
-1.2 11.5 + 1.2 88.5
-1.3 9.7 + 1.3 90.3
-1.4 8.1 + 1.4 91.3
-1.5 6.7 + 1.5 93.3
-1.6 5.5 + 1.6 94.5
-1.7 4.5 + 1.7 95.5
-1.8 3.6 + 1.8 96.4
-1.9 2.9 + 1.9 97.1
-2.0 2.3 + 2.0 97.7
-2.1 1.8 + 2.1 98.2
-2.2 1.4 + 2.2 98.6
-2.3 1.1 + 2.3 98.9
-2.4 0.8 + 2.4 99.2
-2.5 0.6 + 2.5 99.4
-2.6 0.5 + 2.6 99.5
-2.7 0.3 + 2.7 99.7
-2.8 0.3 + 2.8 99.7
-2.9 0.2 + 2.9 99.8
-3.0 0.1 + 3.0 99.9

FirstRanker.com

--- Content provided by FirstRanker.com ---