Download PTU B.Tech 2021 Jan EE 3rd Sem 72165 Power System I Transmission And Distribution Question Paper

Download PTU (Punjab Technical University) B.Tech (Bachelor of Technology) / BE (Bachelor of Engineering) 2021 January EE 3rd Sem 72165 Power System I Transmission And Distribution Previous Question Paper

Roll No.
Total No. of Pages : 02
Total No. of Questions : 18
B.Tech. (EE) PT (Sem.?3)
POWER SYSTEM - I (Transmission & Distribution)
Subject Code : BTEE-405
M.Code : 72165
Time : 3 Hrs. Max. Marks : 60
INST RUCT ION TO CANDIDAT ES :
1 .
SECT ION-A is COMPULSORY cons is ting of TEN questions carrying TWO marks
each.
2 .
SECT ION-B c ontains F IVE questions c arrying FIVE marks eac h and s tud ents
have to atte mpt any FOUR q ues tions.
3 .
SECT ION-C contains THREE questions carrying T EN marks each and s tudents
have to atte mpt any T WO questio ns.
SECTION-A
Write briefly :
1)
Show that Insulation Resistance of a cable is inversely proportional to its length.
2)
What is meant by capacitance grading of cables?
3)
Compare the cross-sectional areas of conductors for DC two wire system and single phase
AC system assuming equal length, equal power and equal losses.
4)
What is `Bundling of conductors'?
5)
Explain the terms GMR and self GMD of a conductor.
6)
What is the most economical cross-sectional area? Deduce its expression using Kelvin's
Law.
7)
State the relevance of string efficiency to overhead transmission system.
8)
What is a power circle diagram?
9)
State Ferranti effect.
10) Enlist the main causes for failure of insulators.
1 | M-72165
(S2)-531

SECTION-B
11) Develop the long line exact equations in hyperbolic terms for sending end voltage and
current.
12) A transmission line conductor having a diameter of 19.5 mm weighs 0.85 kg/m. The span
is 275m. The wind pressure is 39 kg/m2 of projected area with ice coating of 13mm. The
ultimate strength of the conductor is 8000kg. Calculate the maximum sag if the factor of
safety is 2 and ice weighs 910kg/m3.
13) The cost per km for each of the copper conductor of a section a sq-cm for a transmission
line is [Rs.(2800a + 1300)]. The load factor of the load current is 80% and the load factor
of the losses is 65%. The rate of interest and depreciation is 10% and the cost of energy is
50 paisa per kWh. Find the most economical current density of the transmission line. Given
= 0.000178 -m.
14) What are Synchronous Phase Modifiers? Explain its use for voltage regulation/line
compensation?
15) Explain the various types of Pressure Cables.
SECTION-C
16) a) What is String Efficiency?
b) Each conductor of a 3 phase overhead transmission line is suspended from a cross arm
of a steel tower by a string of four suspension insulators. The voltage across the second
unit is 15KV and across the third is 27KV. Find the voltage between conductor and
String Efficiency.
17) a) Discuss in detail the various methods of laying underground cables.
b) Draw comparison between Over Head Transmission Line System and Underground
Transmission System.
18) Write a short note on the following :
a) Voltage regulation and efficiency
b) Proximity effect
c) Arcing horn and grading ring
d) Power factor on Voltage regulation
NOTE : Disclosure of Identity by writing Mobile No. or Making of passing request on any
page of Answer Sheet will lead to UMC against the Student.
2 | M-72165
(S2)-531

This post was last modified on 26 June 2021