FirstRanker Logo

FirstRanker.com - FirstRanker's Choice is a hub of Question Papers & Study Materials for B-Tech, B.E, M-Tech, MCA, M.Sc, MBBS, BDS, MBA, B.Sc, Degree, B.Sc Nursing, B-Pharmacy, D-Pharmacy, MD, Medical, Dental, Engineering students. All services of FirstRanker.com are FREE

📱

Get the MBBS Question Bank Android App

Access previous years' papers, solved question papers, notes, and more on the go!

Install From Play Store

Download AKTU B-Tech 8th Sem 2014-15 EME 051 Operations Research Question Paper

Download AKTU (Dr. A.P.J. Abdul Kalam Technical University (AKTU), formerly Uttar Pradesh Technical University (UPTU) B-Tech 8th Semester (Eight Semester) 2014-15 EME 051 Operations Research Question Paper

This post was last modified on 29 January 2020

DUET Last 10 Years 2011-2021 Question Papers With Answer Key || Delhi University Entrance Test conducted by the NTA


Printed Pages : 7

*140851* EME051

(Following Paper ID and Roll No. to be filled in your Answer Book)

--- Content provided by FirstRanker.com ---

PAPER ID: 140851

Roll No.

B. Tech.

(SEM. VIII) THEORY EXAMINATION, 2014-15

OPERATIONS RESEARCH

--- Content provided by‍ FirstRanker.com ---

Time: 3 Hours]

[Total Marks: 100

Note: Attempt all the questions. Assume missing data suitably.

Attempt any two of the following questions- 10x2=20

  1. (a) What is meant by a mathematical model of a real situation? Discuss the importance of models in the solution of OR problems.
  2. --- Content provided by‍ FirstRanker.com ---

  3. (b) Use the graphical method to solve the following LP problem:
    Maximize Z = 3x1 + 4x2
    Subject to the constraints
    (i) X1 - X2 =-1
    (ii) -x1 + x2 = 0 and x1, x2 = 0.
  4. --- Content provided by‍ FirstRanker.com ---

  5. (c) Solve the following LP problem by using the two-phase simplex method
    Minimize Z = x1 - 2x2 - 3x3
    Subject to the constraints :
    (1) -2x1 + x2 + 3x3 = 2
    (2) 2x1 + 3x2 + 4x3 = 1 and X1, X2, X3 = 0
  6. --- Content provided by‌ FirstRanker.com ---

Attempt any two of the following questions : 10x2=20

  1. (a) A manufacturer wants to ship 22 loads of his products as shown below. The matrix gives the kilometers from sources of supply to the destinations.
    D1 D2 D3 D4 D5 Supply
    S1 5 8 6 6 3 8
    S2 4 7 7 6 5 5
    S3 8 4 6 6 4 9
    Demand 4 4 5 4 8 25

    The shipping cost is Rs. 10 per load per km.
    What shipping schedule should be used in order to minimize the total transportation cost?
  2. --- Content provided by‍ FirstRanker.com ---

  3. (b) A Marketing manager has five salesman and five sales districts. Considering the capabilities of the salesman and the nature of the districts, the marketing manager estimates that the sales per month (in hundred rupees) for each salesman in each district would be as follows:
    A B C D E
    1 32 38 40 28 40
    2 40 24 28 21 36
    3 41 27 33 30 37
    4 22 38 41 36 36
    5 29 33 40 35 39

    Find the assignment of salesman to district that will remain in maximum sales.
  4. (c) State Bellman's "principle of optimality" and explain with the help of an illustrative example how it can be used to solve a multistage decision problem.

Attempt any two of the following questions : 10x2= 20

--- Content provided by​ FirstRanker.com ---

  1. (a) An investor is given the following investment alternatives and percentage rates of return.
    Low Medium High
    Regular shares 7% 10% 15%
    Risky shares -10% 12% 25%
    Property -12% 18% 30%

    Over the past 300 days, 150 days have been medium market conditions and 60 days have had high market increases. On the basis of these data, state the optimum investment strategy for the investment.
  2. (b) For what value of X, the game with following pay-off matrix is strictly determinable?
    B1 B2 B3
    A ? 6 2
    A2 -1 ? -7
    A3 -2 4 ?
  3. --- Content provided by⁠ FirstRanker.com ---

  4. (c) There are seven jobs, each of which has to go through the machines A and B in the order AB. Processing times in hours are as follows:
    Job 1 2 3 4 5 6 7
    Machine A 3 12 15 6 10 11 9
    Machine B 8 10 10 6 12 1 3

    Determine a sequence of these jobs that will minimize the total elapsed time T. Also find T and idle time for machine A and B.

Attempt any two of the following questions : 10x2=20

  1. (a) The demand for an item in a company is 18,000 units per year, and the company can produce the item at a rate of 3,000 per month. The cost of one set up is Rs 500 and the holding cost of one unit per month is 15 paise. The shortage cost of one unit is Rs 240 per year. Determine the optimum manufacturing quantity and the number of shortages. Also determine the manufacturing time and the time between set-ups.
  2. --- Content provided by‍ FirstRanker.com ---

  3. (b) What is Monte Carlo simulation? Describe the idea of experimentation (Random Sampling) in simulation.
  4. (c) Using random numbers to simulate a sample, find the probability that a packet of 6 products does not contain any defective product, when the production line produces 10 percent defective products. Compare the answer with the expected probability.

Attempt any two of the following questions : 10x2=20

  1. (a) Explain the following terms in PERT/CPM.
    1. Earliest time
    2. Latest time
    3. --- Content provided by FirstRanker.com ---

    4. Total activity time
    5. Event slack
    6. Critical path.
  2. (b) The following tasks has to be performed periodically on the heat exchangers in a refinery:

    --- Content provided by⁠ FirstRanker.com ---

    Task Immediate predecessors Time (days)
    A - 14
    B A 22
    C B 10
    D B 16
    E B 12
    F C 10
    G C 6
    H F,G 8
    I D,E,H 24
    J I 16
    1. Draw a network diagram of activities for the project.
    2. Identify the critical path. What is its length?
  3. (c) In a railway marshalling yard, goods trains arrive at a rate of 30 trains per day. Assuming that the inter arrival time follows an exponential distribution and the service time (the time taken to hump a train) distribution is also exponential with an average of 36 minutes. Calculate:
    1. expected queue size (line length)
    2. Probability that the queue size exceeds 10.
    3. --- Content provided by‌ FirstRanker.com ---

    If the input of trains increases to an average of 33 per day, What will be the change in (a) and (b) ?