1 | M - 4 5 0 5 4 ( S 1 7 ) - 2 8 4 9

Roll No. Total No. of Pages : 02
Total No. of Questions : 05
B.Arch. (Sem.?8)
BUILDING CONSTRUCTION-VII
Subject Code : AR-424
M.Code : 45054
Time : 4 Hrs. Max. Marks: 100
INSTRUCTION TO CANDIDATES :
1. QUESTION No. 1 is COMPULSORY and carries 40 Marks.
2. Attempt any TWO more questions from the REST which have equal weightage.

Q1. Draw the working details of the following :
a. Expansion joint detail between RCC slabs on Roof top.
b. Typical detail for Showcase window of Books Shop.
c. Water proofing treatment for a building having plinth 1.5 meters above ground level
d. Thermal insulation for RCC roof
Q2. Draw the complete interior layout for a Hotel reception lobby. Also draw the construction
details of Reception counters. (Plan enclosed)
Q3. What do you understand by Water Proofing? Draw the typical construction details of
Water proofing of a basement retaining wall.
Q4. Draw the construction details for shop front of an Antiques sale shop having a width of
4.5 meters.
Q5. Draw the typical false ceiling construction details for a Medicine shop including lighting
along with display counters.
FirstRanker.com - FirstRanker's Choice
1 | M - 4 5 0 5 4 ( S 1 7 ) - 2 8 4 9

Roll No. Total No. of Pages : 02
Total No. of Questions : 05
B.Arch. (Sem.?8)
BUILDING CONSTRUCTION-VII
Subject Code : AR-424
M.Code : 45054
Time : 4 Hrs. Max. Marks: 100
INSTRUCTION TO CANDIDATES :
1. QUESTION No. 1 is COMPULSORY and carries 40 Marks.
2. Attempt any TWO more questions from the REST which have equal weightage.

Q1. Draw the working details of the following :
a. Expansion joint detail between RCC slabs on Roof top.
b. Typical detail for Showcase window of Books Shop.
c. Water proofing treatment for a building having plinth 1.5 meters above ground level
d. Thermal insulation for RCC roof
Q2. Draw the complete interior layout for a Hotel reception lobby. Also draw the construction
details of Reception counters. (Plan enclosed)
Q3. What do you understand by Water Proofing? Draw the typical construction details of
Water proofing of a basement retaining wall.
Q4. Draw the construction details for shop front of an Antiques sale shop having a width of
4.5 meters.
Q5. Draw the typical false ceiling construction details for a Medicine shop including lighting
along with display counters.
2 | M - 4 5 0 5 4 ( S 1 7 ) - 2 8 4 9



NOTE : Disclosure of Identity by writing Mobile No. or Making of passing request on any
page of Answer Sheet will lead to UMC against the Student.

FirstRanker.com - FirstRanker's Choice