Download GTU MBA 2019 Winter 3rd Sem 3539271 Project Management Question Paper

Download GTU (Gujarat Technological University) MBA 2019 Winter 3rd Sem 3539271 Project Management Previous Question Paper

Page 1 of 2


Seat No.: ________ Enrolment No.___________

GUJARAT TECHNOLOGICAL UNIVERSITY
MBA ? SEMESTER III ? EXAMINATION ? WINTER 2019

Subject Code: 3539271 Date:03/12/2019
Subject Name: Project Management
Time: 10.30 AM TO 01.30 PM Total Marks: 70
Instructions:
1. Attempt all questions.
2. Make suitable assumptions wherever necessary.
3. Figures to the right indicate full marks.

Q.1 Briefly discuss the following:
(a) Responsibility matrices
(b) Critical path
(c) Characteristics of a good project manager
(d) Estimates in project
(e) Work package
(f) Causes of project failure
(g) Venture capital

14
Q.2 (a) Depict your understanding for project. Also discuss the importance of project
management.
07
(b) Work breakdown structure must match with Organizational breakdown
structure. Support the statement with real life example.
07


OR
(b) Explain the stages of project life cycle. 07

Q.3 (a) Discuss various sources of financing a project. 07
(b) Discuss implications of organizational culture on project management. 07
OR
Q.3 (a) Explain various types of project closures in brief. 07
(b) For any project, project manager has to set the priorities among time, cost and
quality of the project. How priority Metrix is helpful to the project manager in
managing a project.
07

Q.4 (a) Discuss various factors influencing the site selection for setting up a
manufacturing plant of motorcycles.
07
(b) Write a note on conflict resolution mechanism. 07
OR
Q.4 (a) Depict your understanding for network techniques. What are the network
techniques used in project management?
07
(b) Briefly explain the risk management process in project management. 07
FirstRanker.com - FirstRanker's Choice
Page 1 of 2


Seat No.: ________ Enrolment No.___________

GUJARAT TECHNOLOGICAL UNIVERSITY
MBA ? SEMESTER III ? EXAMINATION ? WINTER 2019

Subject Code: 3539271 Date:03/12/2019
Subject Name: Project Management
Time: 10.30 AM TO 01.30 PM Total Marks: 70
Instructions:
1. Attempt all questions.
2. Make suitable assumptions wherever necessary.
3. Figures to the right indicate full marks.

Q.1 Briefly discuss the following:
(a) Responsibility matrices
(b) Critical path
(c) Characteristics of a good project manager
(d) Estimates in project
(e) Work package
(f) Causes of project failure
(g) Venture capital

14
Q.2 (a) Depict your understanding for project. Also discuss the importance of project
management.
07
(b) Work breakdown structure must match with Organizational breakdown
structure. Support the statement with real life example.
07


OR
(b) Explain the stages of project life cycle. 07

Q.3 (a) Discuss various sources of financing a project. 07
(b) Discuss implications of organizational culture on project management. 07
OR
Q.3 (a) Explain various types of project closures in brief. 07
(b) For any project, project manager has to set the priorities among time, cost and
quality of the project. How priority Metrix is helpful to the project manager in
managing a project.
07

Q.4 (a) Discuss various factors influencing the site selection for setting up a
manufacturing plant of motorcycles.
07
(b) Write a note on conflict resolution mechanism. 07
OR
Q.4 (a) Depict your understanding for network techniques. What are the network
techniques used in project management?
07
(b) Briefly explain the risk management process in project management. 07
Page 2 of 2

Q.5

















Two friends, Jim King and Brad Mount, started a book publishing company. In the new
business Jim focused on editing, sales and marketing while Brad Mount did the
electronic assembly and publishing of books for the company. Their business was
successful and profitable in the first two years, largely due to contracts from two big
businesses. In their third year they got very busy thanks to their third major customer,
a local college that needed customized eBooks. They hired several part time
employees. But by the end of third year of operation, Global Green Books started
experiencing critical problems including
? unable to utilize all the new employees effectively
? unable to deliver eBooks to their customers on schedule
? unable to provide quality texts
? unable to control costs
The company saw a significant rise in issues, a lot of unpleasant ?surprises?
were cropping up; business was down as new resources were hired, also some of the
projects were poorly estimated. The local university was unhappy as their eBook
products. Since the courses must start on schedule and students need their books at the
beginning of their courses, the new lucrative college customer was unhappy. One of
the new part-time employees hired by Jim and Brad, Samantha, had taken a project
management course at college. Samantha was excited about the discipline of project
management and had intentionally selected a job with the company as she saw an
opportunity to polish her project management skills. One fine day, Jim invited
Samantha, for a lunch meeting. He was aware that Samantha was familiar with project
management, and wanted to hear what she had to say about the problems he and Brad
were facing. Over lunch he questioned why their small business which had operated
and implemented projects so successfully over the first two years was being challenged
significantly now. He specifically listed the problems they were facing and asked for
input to solve them. Samantha asked for more time to research all the issues but noted
that company, while being innovative, completed projects without a roadmap or a
project plan and lacked a disciplined approach to project management. She noted that
Jim and Brad did not use any project software for scheduling and they did not use tools
or techniques to estimate, budget or to communicate with stakeholders. Finally, they
had no processes in place to manage project risks and quality. Impressed with this and
other conversations, Jim King asked Samantha if she would consider joining them as a
project associate or project manager on a full-time basis to help them introduce project
management practices and help them tide over their current crisis. Samantha accepted
the offer! She has several key skills?she is an excellent communicator with very good
interpersonal skills and detail-oriented. Within nine months Samantha had fully turned
things around. Due to proactive risk analysis and risk response planning, surprises and
issues reduced. Communication with stakeholders was enhanced. Brad and Jim noted
that the company was delivering projects on schedule, the quality processes worked?
and customers were happy with the products.

Summarize the case and answer the following questions:
1. What were the main issues you think for the struggle of the company?
2. What were the specific project management solutions that were introduced by
Samantha that worked?
OR
1. What kind of suggestions would you give to Brad and Jim if you were the
project manager?
2. Do you think technical knowledge is necessary to become a project
manager?

*******

14